QAs- Overhead Doors.pdf

PDF 101 KB Posted

Attached to
Overhead Doors Federal contract opportunity
Solicitation number
FA301621U0242
Issued by
Department of the Air Force Air Education and Training Command

View the file

Other files for this federal contract opportunity

Other files attached to Overhead Doors, newest first.
File Type Posted
Overhead doors RFQ_3Sep2021.pdf PDF
Attachment 1 - Overhead Doors SOW_3Sep2021.pdf PDF
Attachment 1 - Overhead Doors SOW.pdf PDF
Overhead doors RFQ_26Aug2021.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS and ANSWERS

1) Do we have the door numbers that are being replaced?

ANSWER: No. However, all doors are similar.

2) The doors that have been replaced recently have new track. I would like to replace the track also, is this an option?

ASNWER: Yes

3) Does all of the low voltage wiring for controls and photocells need to be in conduit?

ANSWER: Yes

4) What is the voltage and phase of the new operators?

ANSWER: 120 volt single phase

5) There may be some lights that will need to be moved. Is this something CE will do?

ANSWER: Yes. The government will move lights as required.

6) Do you have approximate door measurements?

ANSWER: All are approximately 11feet 6 inch width and 11 feet 9 inch height

7) The install of the exterior mount key switch to operate the door is at each location, correct?

ANSWER: Yes.

8) Per the SOW, Electrical to the operators will be ran/installed by CE personnel. Is that pre job or post and will they be connecting Operators?

ANSWER: An Electrical disconnect will be installed by CE at ea operator. Contractor will need to connect from disconnect to operator. If contractor needs to test the doors functionality, once the door and motor is installed, an extension plug cord can be used (110 volts).

File details come from the government source that posted it. Updated .