Questions and Answers.pdf
PDF 59 KB Posted
- Attached to
- JBSA Fire Suppression Systems Maintenance Services Federal contract opportunity
- Solicitation number
- FA301621R0028
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 2 - WD - 2015-5253 - Rev 14.pdf | ||
| Attachment 1 - PWS 7 Sep 21.pdf | ||
| Solicitation Amendment FA301621R00280003 SF 30.pdf | ||
| Solicitation Amendment FA301621R00280002 SF 30.pdf | ||
| Solicitation Amendment FA301621R00280001 SF 30.pdf | ||
| Solicitation - FA301621R0028.pdf | ||
| Attachment 1 - FY22 Fire Suppression PWS.pdf | ||
| Attachment 2 - Wage Determination No 2015-5253.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA301621R0028 – Questions and Answers JBSA Fire Suppression System Maintenance
Question Government Response 1 Can you confirm if the 150 Fire
Extinguishers are to be inspected Annually or Monthly by the contractor?
The extinguishers are inspected annually per NFPA standards, but not all are due at the same time.
Contractor is to provide reports monthly of what was done that month.
2 PWS Section 1.2 - Can you confirm which CLIN Labor and Parts for the Fire Extinguisher 6yr Internal Examination will be billed against?
The cost of labor should be included in the price of CLIN 0X04; the cost of parts should be billed to CLIN 0X05.
3 PWS Section 1.3 - Can you confirm which CLIN Labor and Parts for the Fire Extinguisher 12yr Hydrostatic Testing will be billed against?
The cost of labor should be included in the price of CLIN 0X03; the cost of parts should be billed to CLIN 0X05.
4 PWS Section 1.5.2 - Can you confirm which CLIN Labor and Parts for the Kitchen Hood System Tank12yr Hydrostatic Testing will be billed against?
The cost of labor should be included in the price of CLIN 0X09; the cost of parts should be billed to CLIN 0X10.
5 PWS Section 1.6 - How will needed maintenance repairs be covered on the UV system? For instance bad bulbs, bad cassettes, ballast box inop, etc? If that cost is to be in the regular monthly charge then we would need to know all current deficiencies.
The cost of labor should be included in the price of CLIN 0X11; the cost of parts should be billed to CLIN 0X13.
6 PWS Section 1.6 - How will the labor and parts cost of replacing UV Bulbs be covered during quarterly maintenance?
The cost of labor should be included in the price of CLIN 0X11; the cost of parts should be billed to CLIN 0X13.
7 PWS Section 1.6.1 - How long does the quarterly cleaning usually take on average?
The amount of time required to perform this task is not dictated by the Government; however, all work shall be performed within the constraints of the PWS.
8 PWS Section 1.7 - Will the contractor labor be reimbursed for emergency service call response when that work is requested?
Emergency services calls shall be billed to CLIN 0X14.
9 WS Section 1.9 - How are the kitchen hood suppression systems inspections currently scheduled?
Do all the semi-annual inspections take place in a 3 month group like (Feb, March, April & Aug, Sep, Nov)? Can you provide some
Fire suppression system inspections are due semi-annually, so they are typically all done around the same time twice per year. Some of the systems are off schedule, but are not the norm. Schedule will be provided to the contractor receiving the award.
FA301621R0028 – Questions and Answers JBSA Fire Suppression System Maintenance timeframe as to when (what month) each bldg fire suppression inspection is due?
10 PWS Section Appendix B - Can you provide the quantity of smoke detectors, heat detectors, duct detectors and pull stations for each Halon/C02 System?
This information is not readily available.
11 PWS Section Appendix B - Can you provide the size for each of the Halon 1301 cylinders and Lackland Hush House?
500 lbs