This is a Statement of Work for the Radar, Airfield & Weather Systems (RAWS) Schoolhouse Test Equipment Modernization project at Keesler Air Force Base, Mississippi. The objective is to consolidate and replace eleven legacy instruments (signal generator, oscilloscope, dummy load, wattmeter, AM-48, T-attenuator, mixer, Field Fox, frequency counter, spectrum analyzer, and Data Scout) with modern unified test systems. The vendor must deliver 26 TF300 DOD ATG test systems, each equipped with CX300-SVNA and CX300-SSPAR options for full Instrument Landing Systems (ILS) testing capability. Additionally, the vendor shall provide two TACAN Upgrade Kits with CX300-SPSB External Power Sensor Support options and Bird 5012-TACAN Power Sensors, ten spare CM300/350 cable and adapter kits, 26 four-year extended hardware warranties (providing five years total coverage), and one TF300 DOD ATG ILS SIM software simulator package.
All systems must function as single, portable units capable of testing UHF/VHF radios and ILS systems, with two configured for TACAN testing. Each system must include proprietary setup files, pre-loaded automated test procedures for USAF CM300/350 radio systems, and hardware kits with cables and adapters. The vendor must provide familiarization and operational training for 30 instructors from the 334 TRS, delivered either virtually or in-person at Keesler AFB, coordinated post-award. The vendor must also deliver a laptop-based software simulator package that replicates the actual CX300 user interface and contains complete AFFSA-approved HTML-based procedures for DUT setup, connection, and test execution without licensing limitations. Equipment shall be shipped FOB Destination to Keesler AFB, with the software simulator package delivered six months after receipt of order.
View the file
On GovTribe
Work with this file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Radar, Airfield & Weather Systems (RAWS) Schoolhouse Test Equipment Modernization
1. Objective
The new systems must consolidate and replace the functionality of the following legacy equipment:
1. Signal Generator
2. Oscilloscope
3. Dummy Load
4. Wattmeter
5. AM-48
6. T-Attenuator
7. Mixer
8. Field Fox
9. Frequency Counter
10. Spectrum Analyzer
11. Data Scout
2. Items Requested The vendor shall provide the following exact line items:
• 26 (Each) - TF300 DOD ATG test systems, each including CX300-SVNA and CX300- SSPAR options to provide full ILS test capability.
• 2 (Each) - TACAN Upgrade Kits, each including one (1) CX300-SPSB External Power Sensor Support option and one (1) Bird 5012-TACAN Power Sensor.
• 10 (Each) - Spare CM300/350 Cable and Adapter Kits
• 26 (Each) - 4-Year Extended Hardware Warranty to provide a total of 5 years of warranty coverage for each system.
• 1 (Each) - TF300 DOD ATG ILS SIM software simulator package.
3. Equipment Requirements
The systems must meet the following minimum characteristics:
• Must function as a single, portable unit replacing the 11 legacy instruments listed in
Section 2.
• All 26 systems must provide testing for UHF/VHF radios and Instrument Landing
Systems (ILS). Two of these systems must also provide testing for Tactical Air Navigation (TACAN) systems as specified in the line items below.
• Must include proprietary setup files and pre-loaded automated test procedures developed specifically for USAF CM300/350 radio systems.
• Must include hardware kits, including but not limited to cables and adapters designed to connect the test set directly to the CM300/350 radios. The two TACAN configurations must include the specific external power sensor required for that function.
• All systems must include four-year extended hardware warranty past the base one-year hardware warranty.
• The vendor must provide familiarization and operational training for the 334 TRS instructors (30 personnel), covering all system configurations. This training shall be delivered either virtually or in-person (on-site) at Keesler AFB, MS, as coordinated between the Government and the vendor post-award.
• Vendor must provide a software simulator package for laptop-based training. The software must simulate how to set up TF300 for CM-300/350 Radios, ILS, and TACAN systems. The simulator shall provide trainees with the same user interface on a laptop or PC that is displayed on the actual CX300 front screen. It must contain the complete, AFFSA-approved, HTML-based procedures identical to those on the physical test system. These procedures will provide step-by-step instructions for DUT setup, connection, and test execution using the predefined configurations. Software will not be limited to a set amount of training laptops and used on government devices on Keesler
AFB.
4. Delivery Equipment shall be shipped FOB Destination to Keesler AFB, MS.
Software simulator package to be delivered 6 Months After Receipt of Order (ARO).
| Radar, Airfield & Weather Systems (RAWS) Schoolhouse Test Equipment Modernization |
| 1. Objective |
| 2. Items Requested |
| 3. Equipment Requirements |
| 4. Delivery |
File details come from the government source that posted it. Updated .