Maxwell_BOS_Draft_RFP.doc

DOC document 3 MB Posted

Attached to
Maxwell-Gunter BOS Federal contract opportunity
Solicitation number
FA300213R0012
Issued by
Department of the Air Force Materiel Command Installation and Mission Support Center Installation Contracting Agency

About this file

Attached is the Draft RFP for the Maxwell BOS requirment. If there are any questions regarding the Draft RPS please let me know.

View the file

Other files for this federal contract opportunity

Other files attached to Maxwell-Gunter BOS, newest first.
File Type Posted
Memorandum_of_Agreement_002.tif TIF image
FA3002-13-R-0012-0007.docx DOCX document
MFR_correcting_due_date_in_Amend_0007.docx DOCX document
9504_CBA_Maxwell.pdf PDF
Amendment_0007_Conform_Copy.doc DOC document
Amendment_0006.pdf PDF
Vehicle_Replacement_Schedule_-_Maxwell_AFB_BOS.pdf PDF
Maxwell_BOS_RFP_Amendment_0005.pdf PDF
Maxwell_BOS_PWS_11_Sep_2015.pdf PDF
SCA_WD_2005-2011_Rev_19.pdf PDF
Maxwell_Manpower_Matrix_Atch_9_14_Sep_2015.xlsx XLSX spreadsheet
Maxwell_BOS_RFP_(Conformed_Copy).pdf PDF
Maxwell_Memorandum_Amendment_0004.docx DOCX document
Maxwell_BOS_PWS_26_Aug_2015.pdf PDF
Amendment_0003.pdf PDF
Signed_DD254.pdf PDF
RFP_QAs_Consolidated_Final.xlsx XLSX spreadsheet
SCA_WD_2005-2011_Rev_18-Amendment_0003.pdf PDF
Maxwell_BOS_PWS_5_Aug_15_-_Amendment_0003.pdf PDF
Maxwell-Gunter_Contractor_Workforce_Demographics_.pdf PDF
FA3002-13-R-0012_-_Maxwell_RFP_Amend_0002.pdf PDF
Proposal_Due_Date_Extension.pdf PDF
WBS_-_Example-_3_Apr_15.xlsx XLSX spreadsheet
Maxwell_BOS_Technical_Requirements.pptx PPTX presentation
Maxwell_BOS__Past_Performance_(13_May_15).pptx PPTX presentation
Maxwell_BOS_Welcome_(13_May_2015).pptx PPTX presentation
Maxwell_BOS_PWS.pptx PPTX presentation
Mission_Essential_Services.pdf PDF
Maxwell-Gunter_Site_Visit_Letter.pdf PDF
CBA_9504 _Effective_Date_1_Jul_12.pdf PDF
Executive_Summary_-_Maxwell_BOS.pdf PDF
(Highway).pdf PDF
Attachment_for_Section_L_-_PPI_Tool_Instructions.pdf PDF
SubC_Checklist.pdf PDF
Maxwell_BOS_PWS_9_Apr_15.pdf PDF
Client_authorization_letter.pdf PDF
(Residential).pdf PDF
FA3002-13-R-0012_Maxwell_BOS_Pre-Solicitation_Notice_(30_Dec_15).docx DOCX document
Maxwell_BOS_-_Section_M.docx DOCX document
BOS_Comment_Matrix.docx DOCX document
DRAFT_Maxwell_BOS_PWS.pdf PDF
Consolidated_Response_to_Industry_Questions_as_of_18_Mar_14.pdf PDF
Maxwell_CE_Staged_Tier_Workload.xlsx XLSX spreadsheet
Maxwell_DRAFT_Schedule_B.xlsx XLSX spreadsheet
Maxwell_Additional_Workload_in_Tech_Library.zip ZIP file
Support_Agreements.zip ZIP file
General_Transformation_Information.zip ZIP file
DRAFT_Concept_PI_Clause.docx DOCX document
PWS_Draft_(v1)_-_File_2_of_3.zip ZIP file
PWS_Draft_(v1)_-_File_1_of_3.zip ZIP file
Show all 50

Maxwell-Gunter BOS has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section B - Supplies or Services and Prices

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

All Services

FFP

Manage and perform all activities and functions related to leading, managing, training, and directing people and resources dedicated to performing all activities of the PWS. PWS Section 2 Para. 2.1.

FOB: Destination

SIGNAL CODE: C

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Maintenance (FOD)

PWS Section 3 Para. 3.1.3

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Resource Management

PWS Section 5 Para. 5.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Telecom/Telephone Wire Services

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1., 7.1.2.1.1.7., 7.1.2.1.1.13., 7.1.2.1.1.14.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Telephone: Moves, Adds, and Changes

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1.17.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Telephone Switch System O&M

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

E911 System

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1.18

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

BTS Work Center Records

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.2.1

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Manhole/Handhole

COMM & IT: Manhole/Handhole and Building Terminal Inspection/Maintenance/Repair IAW - PWS Section 7 Para. 7.1.2.1.2.1.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Long/Haul/Commercial Telecom MGT

COMM & IT: Long-Haul/Commercial Telecommunication Mangement - IAW - PWS Section 7 Para. 7.1.2.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Personal Wireless Communications

COMM & IT: Personal Wireless Communicaitons Systems Work Center - IAW - PWS Section 7 Para. 7.1.2.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Land Mobile Radio

COMM & IT: Land Mobile Radio Services and Network System - IAW - PWS Section 7 Para. 7.1.2.2.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Asset Mgt Work Center

COMM & IT: Asset Management Work Center - IAW - PWS Section 7 Para. 7.1.2.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Plans and Implementation Work Center

COMM & IT Plans and Implementation (P & I) Work Center - IAW - PWS Section 7 Para. 7.1.2.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Contingency Operations

COMM & IT: Contingency Operations For Displaced Gov Agencies - IAW - PWS Section 7 Para. 7.1.2.4.14.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Information Technology Asset Mgt

COMM & IT Information Technology Asset Management - IAW - PWS Section 7 Para. 7.1.2.5.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Network Enterprise Technology Mgt

COMM & IT: Network Enterprise Technology Management and Network Performance Management - IAW - PWS Section 7 Para. 7.1.2.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Network Infrastrucure Management

COMM & IT: Network Infrastructure Management - IAW - PWS Section 7 Para. 7.1.2.5.12.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Network and Information Security MGT

COMM & IT: Network and Information Security Management - IAW - PWS Section 7 Para. 7.1.2.5.13.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Web Services Administration

COMM & IT: Web Services Administration - IAW - PWS Section 7 Para. 7.1.2.5.13.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Network Server/Services/Systems Support

COMM & IT: Network Server/Services/Systems and Applications Support - IAW - PWS Section 7 Para. 7.1.2.5.14.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Data Center Consolidation

COMM & IT: Data Center Consolidation (DCC) - IAW - PWS Section 7 Para. 7.1.2.5.14.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Publishing Management

Provide the administration of the Publications and Forms Management Programs. IAW - PWS Section 9.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Financial Management (Resources)

CE: Provide Financial Management and support to CE activities. IAW - PWS Section 10 Para. 10.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Real Estate/Real Property

CE: Provide real estate/real property management and accountabily support for all DoD and AF real property under the control of the installation. IAW - PWS Section 10 Para. 10.1.2.2., 10.1.2.6. and 10.1.2.6.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

NexGen IT

CE: IAW - PWS Section 10 Para. 10.1.2.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

General Officers Homes (GOH)

CE: IAW - PWS Section 10 Para. 10.1.2.4.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Family Housing Management

CE: IAW - PWS Section 10 Para. 10.1.2.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

UH (Dormitory Managment

CE: IAW - PWS Section 10 Para. 10.1.2.4.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Furnishing Management Office (FMO)

CE: Management and perform all activities and functions related to leading, managing, and directing people and resources didicated to performing FMO activities. IAW - PWS Section 10 Para. 10.1.2.4.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Environmental

CE: Manage and provide oversight to ensure compliance, conservation, and pollution prevention. IAW - PWS Section 10 Para. 10.1.2.5. and 10.1.2.6.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Operations Management

CE: Manage and perform all activities and functionrelated to leading, managing, training, and directing people and resources dedicated to performing opertions and mantenance activities. IAW - PWS Section 11 Para. 11.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

O&M (Sustainment)

CE: Provide professional inspection, maintenance, repair, opertions, and minor alterations. IAW - PWS Section 11 Para. 11.1.2.2. except 11.1.2.2.2.1.1., 11.1.2.2.1.2., 11.1.2.2.1.3., 11.1.2.2.2.1.4., 11.1.2.2.2.1.5., 11.1.2.2.2.2., 11.1.2.2.4.5. and 11.1.2.2.4.6.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Pavement Clearance

CE: Provide removal of debris, snow, and ice. IAW - PWS Section 11 Para. 11.1.2.2.1.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Electrical Distribution System

CE: Maintain, repair, and replace the electrical distributions, real property, accountable RPIE, and associated non-RPIE items. IAW - PWS Section 11 Para. 11.1.2.2.2.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Sewer/Waste Water System

CE: IAW - PWS Section 11 Para. 11.1.2.2.2.1.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Water Distribution

CE: Maintain, repair, replace,and operate the water distribution and water store tank sysems, fire hydants, real property, accountable RPIE, and associated non- RPIE items. IAW - PWS Section 11 Para. 11.1.2.2.2.1.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Gas Distribution

CE: Maintain, repair, replace, and operate the gas distribution system, real property, accountable RPIE, and associated non-RPIE items. IAW - PWS Section 11 Para. 11.1.2.2.2.1.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Heat Generating, Boiler Operations

CE: IAW - PWS Section 11 Para. 11.1.2.2.2.1.5.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Water Plant Operation (chilled Water)

CE: Maintain, repair, and operate the chilled water system. IAW - PWS Section 11 Para. 11.1.2.2.2.1.5.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Pest Control (Entomology)

CE: Provide pest control activities. IAW - PWS Section 11 Para. 11.1.2.2.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Custodial Services

CE: Manage and perform custodial services IAW higher headquarters PWS. IAW - PWS Section 11 Para. 11.1.2.2.4.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Engineering (Sustainment)

CE: Manage and provide portfolio optimization . IAW - PWS Section 12 except Para. 12.1.2.1., 12.1.2.2.6 and 12.1.2.3.4.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Energy & Utility Management

CE: Manage all activies and functions related to leading, managing and directing the people and resouces dedicated to performing utility and energy management activities. IAW - PWS Section 12 Para. 12.1.2.2.6.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

IGI&S (GEOBASE)

CE: Manage, collect, maintain, analyze, and display geo-referended data to support the installation mission. IAW - PWS Section 12 Para. 12.1.2.3.4.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Installation Engineering Management

CE: Provide a dedicated CE director. IAW - PWS Section 12 Para. 12.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Readiness & Emergency Management

CE: IAW - PWS Section 14 Para. 14.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Expeditionary Engineering

CE: IAW - PWS Section 14 Para. 14.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Transient Maintenance Service Requiremen

Transient Maintenance Service Requirements: IAW - PWS Section 3 Para. 3.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Airfield Management

Airfield Management: IAW - PWS Section 21.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Supply Asset Management Program

Supply Asset Management Program: IAW - PWS Section 23-1 Para. 23.1.2.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Supply (IPE) Function

Supply Individual Protective Equipment (IPE) Function: IAW- PWS Section 23-1 Para. 23.1.2.1.1.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Supply Customer Support Program

Supply Customer Support Program: IAW - PWS Section 23-1 Para. 23.1.2.1.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Supply Computer/Systems Ops Program

Supply Computer/Systems Operations Program: IAW - PWS Section 23-1 Para. 23.1.2.1.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Munitions

Munitions: IAW - PWS Section 23 Para. 23.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Transportation Cargo Transportation

Transportation Cargo Transportation: IAW - PWS Section 25-1 Para. 25.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Transportation Passenger Processing

Transportation Passenger Processing and Transportation: IAW - PWS Section 25-1 Para. 25.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Transportation Vehicle Operations

Transportation Vehicle Operations: IAW - PWS Section 25-1 Para. 25.1.2.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Transportation Vehicle Management

Transportation Vehicle Management and Maintenance Support: IAW - PWS Section 25-1 Para. 25.1.2.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Static Display Aircraft Maintenance Svs

Static Display Aircraft Maintenance Service Requirments: IAW - PWS Section 3 Para 3.1.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Community Services Fitness/Sports Center

Community Services Fitness/Sports Center: IAW - PWS Section 28 Para. 28.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Human Resources

Human Resources Military and Civilian Personnel Services: IAW - PWS Section 30.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Human Resources Managment

Human Resources Management and Administration of A&FRC Services: IAW - PWS Section 30 Para. 30.1.2.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
5.50
Months

Weather Services

Weather Services: IAW - PWS Section 32.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot

CE GFP Replacement

COST

CE GFP Replacement: IAW - PWS Section 2 Para. 2.1.2.17.

(Cost Reimbursable) NTE - $1 million

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot

Replacement of Government-Furnished IT

Replacement of Government-furnished (IT Equipment): IAW - PWS Section 7 Para. 7.1.2.5.12.6.

(Cost Reimbursable) NTE - $1 million

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot

Projects

Projects: IAW - PWS Section 11 Para. 11.1.2.2.4.1.5. and 12.1.2.1.

(Cost Reimbursable) NTE - $750K

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot

Government Directed Travel

Government Directed Travel/Per Diem/Conferences, Seminars, Classes, Training: IAW - PWS Section 2 Para. 2.1.2.27.

(Cost Reimbursable) NTE - $30K

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot

CEMAS

CEMAS: IAW - PWS Section 11 Para. 11.1.2.2.

(Cost Reimbursable) NTE - $150K

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot

CE Routine and Planned Work

CE Routine and Planned Work O&M (Sustainment): IAW - PWS Section 11 Para. 11.1.2.2.

(Cost Reimbursable) NTE - $1 million

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot

Transporting of DoDS

Transporting of Department of Defense School (DoDS): IAW - PWS Section 25 Para. 25.1.2.8.

(Cost Reimbursable)

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.50
Months

Mobilization

Execute the changeover plan as proposed and negotiated IAW - PWS Section 2 Para. 2.1.2.26.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
All Services

FFP

Manage and perform all activities and functions related to leading, managing, training, and directing people and resources dedicated to performing all activities of the PWS. PWS Section 2 Para. 2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Maintenance (FOD)

FFP

PWS Section 3 Para. 3.1.3

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Resource Management

FFP

PWS Section 5 Para. 5.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Telecom/Telephone Wire Services

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1., 7.1.2.1.1.7., 7.1.2.1.1.13., 7.1.2.1.1.14.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Telephone: Moves, Adds, and Changes

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1.17.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Telephone Switch System O&M

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
E911 System

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1.18

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
BTS Work Center Records

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.2.1

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Manhole/Handhole

FFP

COMM & IT: Manhole/Handhole and Building Terminal Inspection/Maintenance/Repair IAW - PWS Section 7 Para. 7.1.2.1.2.1.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Long/Haul/Commercial Telecom MGT

FFP

COMM & IT: Long-Haul/Commercial Telecommunication Mangement - IAW - PWS Section 7 Para. 7.1.2.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Personal Wireless Communications

FFP

COMM & IT: Personal Wireless Communicaitons Systems Work Center - IAW - PWS Section 7 Para. 7.1.2.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Land Mobile Radio

FFP

COMM & IT: Land Mobile Radio Services and Network System - IAW - PWS Section 7 Para. 7.1.2.2.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Asset Mgt Work Center

FFP

COMM & IT: Asset Management Work Center - IAW - PWS Section 7 Para. 7.1.2.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Plans and Implementation Work Center

FFP

COMM & IT Plans and Implementation (P & I) Work Center - IAW - PWS Section 7 Para. 7.1.2.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Contingency Operations

FFP

COMM & IT: Contingency Operations For Displaced Gov Agencies - IAW - PWS Section 7 Para. 7.1.2.4.14.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Information Technology Asset Mgt

FFP

COMM & IT Information Technology Asset Management - IAW - PWS Section 7 Para. 7.1.2.5.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Network Enterprise Technology Mgt

FFP

COMM & IT: Network Enterprise Technology Management and Network Performance Management - IAW - PWS Section 7 Para. 7.1.2.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Network Infrastrucure Management

FFP

COMM & IT: Network Infrastructure Management - IAW - PWS Section 7 Para. 7.1.2.5.12.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Network and Information Security MGT

FFP

COMM & IT: Network and Information Security Management - IAW - PWS Section 7 Para. 7.1.2.5.13.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Web Services Administration

FFP

COMM & IT: Web Services Administration - IAW - PWS Section 7 Para. 7.1.2.5.13.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Network Server/Services/Systems Support

FFP

COMM & IT: Network Server/Services/Systems and Applications Support - IAW - PWS Section 7 Para. 7.1.2.5.14.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Data Center Consolidation

FFP

COMM & IT: Data Center Consolidation (DCC) - IAW - PWS Section 7 Para. 7.1.2.5.14.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Publishing Management

FFP

Provide the administration of the Publications and Forms Management Programs. IAW - PWS Section 9.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Financial Management (Resources)

FFP

CE: Provide Financial Management and support to CE activities. IAW - PWS Section 10 Para. 10.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Real Estate/Real Property

FFP

CE: Provide real estate/real property management and accountabily support for all DoD and AF real property under the control of the installation. IAW - PWS Section 10 Para. 10.1.2.2., 10.1.2.6. and 10.1.2.6.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
NexGen IT

FFP

CE: IAW - PWS Section 10 Para. 10.1.2.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
General Officers Homes (GOH)

FFP

CE: IAW - PWS Section 10 Para. 10.1.2.4.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Family Housing Management

FFP

CE: IAW - PWS Section 10 Para. 10.1.2.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
UH (Dormitory Managment

FFP

CE: IAW - PWS Section 10 Para. 10.1.2.4.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Furnishing Management Office (FMO)

FFP

CE: Management and perform all activities and functions related to leading, managing, and directing people and resources didicated to performing FMO activities. IAW - PWS Section 10 Para. 10.1.2.4.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Environmental

FFP

CE: Manage and provide oversight to ensure compliance, conservation, and pollution prevention. IAW - PWS Section 10 Para. 10.1.2.5. and 10.1.2.6.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Operations Management

FFP

CE: Manage and perform all activities and functionrelated to leading, managing, training, and directing people and resources dedicated to performing opertions and mantenance activities. IAW - PWS Section 11 Para. 11.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
O&M (Sustainment)

FFP

CE: Provide professional inspection, maintenance, repair, opertions, and minor alterations. IAW - PWS Section 11 Para. 11.1.2.2. except 11.1.2.2.2.1.1., 11.1.2.2.1.2., 11.1.2.2.1.3., 11.1.2.2.2.1.4., 11.1.2.2.2.1.5., 11.1.2.2.2.2., 11.1.2.2.4.5. and 11.1.2.2.4.6.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Pavement Clearance

FFP

CE: Provide removal of debris, snow, and ice. IAW - PWS Section 11 Para. 11.1.2.2.1.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Electrical Distribution System

FFP

CE: Maintain, repair, and replace the electrical distributions, real property, accountable RPIE, and associated non-RPIE items. IAW - PWS Section 11 Para. 11.1.2.2.2.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Sewer/Waste Water System

FFP

CE: IAW - PWS Section 11 Para. 11.1.2.2.2.1.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Water Distribution

FFP

CE: Maintain, repair, replace,and operate the water distribution and water store tank sysems, fire hydants, real property, accountable RPIE, and associated non- RPIE items. IAW - PWS Section 11 Para. 11.1.2.2.2.1.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Gas Distribution

FFP

CE: Maintain, repair, replace, and operate the gas distribution system, real property, accountable RPIE, and associated non-RPIE items. IAW - PWS Section 11 Para. 11.1.2.2.2.1.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Heat Generating, Boiler Operations

FFP

CE: IAW - PWS Section 11 Para. 11.1.2.2.2.1.5.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Water Plant Operation (chilled Water)

FFP

CE: Maintain, repair, and operate the chilled water system. IAW - PWS Section 11 Para. 11.1.2.2.2.1.5.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Pest Control (Entomology)

FFP

CE: Provide pest control activities. IAW - PWS Section 11 Para. 11.1.2.2.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Custodial Services

FFP

CE: Manage and perform custodial services IAW higher headquarters PWS. IAW - PWS Section 11 Para. 11.1.2.2.4.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Engineering (Sustainment)

FFP

CE: Manage and provide portfolio optimization . IAW - PWS Section 12 except Para. 12.1.2.1., 12.1.2.2.6 and 12.1.2.3.4.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Energy & Utility Management

FFP

CE: Manage all activies and functions related to leading, managing and directing the people and resouces dedicated to performing utility and energy management activities. IAW - PWS Section 12 Para. 12.1.2.2.6.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
IGI&S (GEOBASE)

FFP

CE: Manage, collect, maintain, analyze, and display geo-referended data to support the installation mission. IAW - PWS Section 12 Para. 12.1.2.3.4.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Installation Engineering Management

FFP

CE: Provide a dedicated CE director. IAW - PWS Section 12 Para. 12.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Readiness & Emergency Management

FFP

CE: IAW - PWS Section 14 Para. 14.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Expeditionary Engineering

FFP

CE: IAW - PWS Section 14 Para. 14.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Transient Maintenance Service Requiremen

FFP

Transient Maintenance Service Requirements: IAW - PWS Section 3 Para. 3.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Airfield Management

FFP

Airfield Management: IAW - PWS Section 21.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Supply Asset Management Program

FFP

Supply Asset Management Program: IAW - PWS Section 23-1 Para. 23.1.2.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Supply (IPE) Function

FFP

Supply Individual Protective Equipment (IPE) Function: IAW- PWS Section 23-1 Para. 23.1.2.1.1.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Supply Customer Support Program

FFP

Supply Customer Support Program: IAW - PWS Section 23-1 Para. 23.1.2.1.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Supply Computer/Systems Ops Program

FFP

Supply Computer/Systems Operations Program: IAW - PWS Section 23-1 Para. 23.1.2.1.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Munitions

FFP

Munitions: IAW - PWS Section 23 Para. 23.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Transportation Cargo Transportation

FFP

Transportation Cargo Transportation: IAW - PWS Section 25-1 Para. 25.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Transportation Passenger Processing

FFP

Transportation Passenger Processing and Transportation: IAW - PWS Section 25-1 Para. 25.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Transportation Vehicle Operations

FFP

Transportation Vehicle Operations: IAW - PWS Section 25-1 Para. 25.1.2.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Transportation Vehicle Management

FFP

Transportation Vehicle Management and Maintenance Support: IAW - PWS Section 25-1 Para. 25.1.2.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Static Display Aircraft Maintenance Svs

FFP

Static Display Aircraft Maintenance Service Requirments: IAW - PWS Section 3 Para 3.1.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Community Services Fitness/Sports Center

FFP

Community Services Fitness/Sports Center: IAW - PWS Section 28 Para. 28.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Human Resources

FFP

Human Resources Military and Civilian Personnel Services: IAW - PWS Section 30.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Human Resources Managment

FFP

Human Resources Management and Administration of A&FRC Services: IAW - PWS Section 30 Para. 30.1.2.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Weather Services

FFP

Weather Services: IAW - PWS Section 32.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
CE GFP Replacement

COST

CE GFP Replacement: IAW - PWS Section 2 Para. 2.1.2.17.

(Cost Reimbursable) NTE - $1 million

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
Replacement of Government-Furnished IT

COST

Replacement of Government-furnished (IT Equipment): IAW - PWS Section 7 Para. 7.1.2.5.12.6.

(Cost Reimbursable) NTE - $1 million

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
Projects

COST

Projects: IAW - PWS Section 11 Para. 11.1.2.2.4.1.5. and 12.1.2.1.

(Cost Reimbursable) NTE - $750K

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
Government Directed Travel

COST

Government Directed Travel/Per Diem/Conferences, Seminars, Classes, Training: IAW - PWS Section 2 Para. 2.1.2.27.

(Cost Reimbursable) NTE - $30K

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
CEMAS

COST

CEMAS: IAW - PWS Section 11 Para. 11.1.2.2.

(Cost Reimbursable) NTE - $150K

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
CE Routine and Planned Work

COST

CE Routine and Planned Work O&M (Sustainment): IAW - PWS Section 11 Para. 11.1.2.2.

(Cost Reimbursable) NTE - $1 million

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
Transporting of DoDS

COST

Transporting of Department of Defense School (DoDS): IAW - PWS Section 25 Para. 25.1.2.8.

(Cost Reimbursable)

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
All Services

FFP

Manage and perform all activities and functions related to leading, managing, training, and directing people and resources dedicated to performing all activities of the PWS. PWS Section 2 Para. 2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Maintenance (FOD)

FFP

PWS Section 3 Para. 3.1.3

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Resource Management

FFP

PWS Section 5 Para. 5.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Telecom/Telephone Wire Services

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1., 7.1.2.1.1.7., 7.1.2.1.1.13., 7.1.2.1.1.14.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Telephone: Moves, Adds, and Changes

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1.17.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Telephone Switch System O&M

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
E911 System

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1.18

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
BTS Work Center Records

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.2.1

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Manhole/Handhole

FFP

COMM & IT: Manhole/Handhole and Building Terminal Inspection/Maintenance/Repair IAW - PWS Section 7 Para. 7.1.2.1.2.1.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Long/Haul/Commercial Telecom MGT

FFP

COMM & IT: Long-Haul/Commercial Telecommunication Mangement - IAW - PWS Section 7 Para. 7.1.2.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Personal Wireless Communications

FFP

COMM & IT: Personal Wireless Communicaitons Systems Work Center - IAW - PWS Section 7 Para. 7.1.2.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Land Mobile Radio

FFP

COMM & IT: Land Mobile Radio Services and Network System - IAW - PWS Section 7 Para. 7.1.2.2.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Asset Mgt Work Center

FFP

COMM & IT: Asset Management Work Center - IAW - PWS Section 7 Para. 7.1.2.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Plans and Implementation Work Center

FFP

COMM & IT Plans and Implementation (P & I) Work Center - IAW - PWS Section 7 Para. 7.1.2.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Contingency Operations

FFP

COMM & IT: Contingency Operations For Displaced Gov Agencies - IAW - PWS Section 7 Para. 7.1.2.4.14.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Information Technology Asset Mgt

FFP

COMM & IT Information Technology Asset Management - IAW - PWS Section 7 Para. 7.1.2.5.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Network Enterprise Technology Mgt

FFP

COMM & IT: Network Enterprise Technology Management and Network Performance Management - IAW - PWS Section 7 Para. 7.1.2.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Network Infrastrucure Management

FFP

COMM & IT: Network Infrastructure Management - IAW - PWS Section 7 Para. 7.1.2.5.12.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Network and Information Security MGT

FFP

COMM & IT: Network and Information Security Management - IAW - PWS Section 7 Para. 7.1.2.5.13.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Web Services Administration

FFP

COMM & IT: Web Services Administration - IAW - PWS Section 7 Para. 7.1.2.5.13.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Network Server/Services/Systems Support

FFP

COMM & IT: Network Server/Services/Systems and Applications Support - IAW - PWS Section 7 Para. 7.1.2.5.14.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Data Center Consolidation

FFP

COMM & IT: Data Center Consolidation (DCC) - IAW - PWS Section 7 Para. 7.1.2.5.14.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Publishing Management

FFP

Provide the administration of the Publications and Forms Management Programs. IAW - PWS Section 9.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Financial Management (Resources)

FFP

CE: Provide Financial Management and support to CE activities. IAW - PWS Section 10 Para. 10.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Real Estate/Real Property

FFP

CE: Provide real estate/real property management and accountabily support for all DoD and AF real property under the control of the installation. IAW - PWS Section 10 Para. 10.1.2.2., 10.1.2.6. and 10.1.2.6.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
NexGen IT

FFP

CE: IAW - PWS Section 10 Para. 10.1.2.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
General Officers Homes (GOH)

FFP

CE: IAW - PWS Section 10 Para. 10.1.2.4.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Family Housing Management

FFP

CE: IAW - PWS Section 10 Para. 10.1.2.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
UH (Dormitory Managment

FFP

CE: IAW - PWS Section 10 Para. 10.1.2.4.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Furnishing Management Office (FMO)

FFP

CE: Management and perform all activities and functions related to leading, managing, and directing people and resources didicated to performing FMO activities. IAW - PWS Section 10 Para. 10.1.2.4.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Environmental

FFP

CE: Manage and provide oversight to ensure compliance, conservation, and pollution prevention. IAW - PWS Section 10 Para. 10.1.2.5. and 10.1.2.6.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Operations Management

FFP

CE: Manage and perform all activities and functionrelated to leading, managing, training, and directing people and resources dedicated to performing opertions and mantenance activities. IAW - PWS Section 11 Para. 11.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
O&M (Sustainment)

FFP

CE: Provide professional inspection, maintenance, repair, opertions, and minor alterations. IAW - PWS Section 11 Para. 11.1.2.2. except 11.1.2.2.2.1.1., 11.1.2.2.1.2., 11.1.2.2.1.3., 11.1.2.2.2.1.4., 11.1.2.2.2.1.5., 11.1.2.2.2.2., 11.1.2.2.4.5. and 11.1.2.2.4.6.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Pavement Clearance

FFP

CE: Provide removal of debris, snow, and ice. IAW - PWS Section 11 Para. 11.1.2.2.1.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Electrical Distribution System

FFP

CE: Maintain, repair, and replace the electrical distributions, real property, accountable RPIE, and associated non-RPIE items. IAW - PWS Section 11 Para. 11.1.2.2.2.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Sewer/Waste Water System

FFP

CE: IAW - PWS Section 11 Para. 11.1.2.2.2.1.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Water Distribution

FFP

CE: Maintain, repair, replace,and operate the water distribution and water store tank sysems, fire hydants, real property, accountable RPIE, and associated non- RPIE items. IAW - PWS Section 11 Para. 11.1.2.2.2.1.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Gas Distribution

FFP

CE: Maintain, repair, replace, and operate the gas distribution system, real property, accountable RPIE, and associated non-RPIE items. IAW - PWS Section 11 Para. 11.1.2.2.2.1.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Heat Generating, Boiler Operations

FFP

CE: IAW - PWS Section 11 Para. 11.1.2.2.2.1.5.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Water Plant Operation (chilled Water)

FFP

CE: Maintain, repair, and operate the chilled water system. IAW - PWS Section 11 Para. 11.1.2.2.2.1.5.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Pest Control (Entomology)

FFP

CE: Provide pest control activities. IAW - PWS Section 11 Para. 11.1.2.2.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Custodial Services

FFP

CE: Manage and perform custodial services IAW higher headquarters PWS. IAW - PWS Section 11 Para. 11.1.2.2.4.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Engineering (Sustainment)

FFP

CE: Manage and provide portfolio optimization . IAW - PWS Section 12 except Para. 12.1.2.1., 12.1.2.2.6 and 12.1.2.3.4.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Energy & Utility Management

FFP

CE: Manage all activies and functions related to leading, managing and directing the people and resouces dedicated to performing utility and energy management activities. IAW - PWS Section 12 Para. 12.1.2.2.6.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
IGI&S (GEOBASE)

FFP

CE: Manage, collect, maintain, analyze, and display geo-referended data to support the installation mission. IAW - PWS Section 12 Para. 12.1.2.3.4.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Installation Engineering Management

FFP

CE: Provide a dedicated CE director. IAW - PWS Section 12 Para. 12.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Readiness & Emergency Management

FFP

CE: IAW - PWS Section 14 Para. 14.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Expeditionary Engineering

FFP

CE: IAW - PWS Section 14 Para. 14.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Transient Maintenance Service Requiremen

FFP

Transient Maintenance Service Requirements: IAW - PWS Section 3 Para. 3.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Airfield Management

FFP

Airfield Management: IAW - PWS Section 21.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Supply Asset Management Program

FFP

Supply Asset Management Program: IAW - PWS Section 23-1 Para. 23.1.2.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Supply (IPE) Function

FFP

Supply Individual Protective Equipment (IPE) Function: IAW- PWS Section 23-1 Para. 23.1.2.1.1.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Supply Customer Support Program

FFP

Supply Customer Support Program: IAW - PWS Section 23-1 Para. 23.1.2.1.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Supply Computer/Systems Ops Program

FFP

Supply Computer/Systems Operations Program: IAW - PWS Section 23-1 Para. 23.1.2.1.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Munitions

FFP

Munitions: IAW - PWS Section 23 Para. 23.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Transportation Cargo Transportation

FFP

Transportation Cargo Transportation: IAW - PWS Section 25-1 Para. 25.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Transportation Passenger Processing

FFP

Transportation Passenger Processing and Transportation: IAW - PWS Section 25-1 Para. 25.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Transportation Vehicle Operations

FFP

Transportation Vehicle Operations: IAW - PWS Section 25-1 Para. 25.1.2.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Transportation Vehicle Management

FFP

Transportation Vehicle Management and Maintenance Support: IAW - PWS Section 25-1 Para. 25.1.2.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Static Display Aircraft Maintenance Svs

FFP

Static Display Aircraft Maintenance Service Requirments: IAW - PWS Section 3 Para 3.1.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Community Services Fitness/Sports Center

FFP

Community Services Fitness/Sports Center: IAW - PWS Section 28 Para. 28.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Human Resources

FFP

Human Resources Military and Civilian Personnel Services: IAW - PWS Section 30.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Human Resources Managment

FFP

Human Resources Management and Administration of A&FRC Services: IAW - PWS Section 30 Para. 30.1.2.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Weather Services

FFP

Weather Services: IAW - PWS Section 32.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
CE GFP Replacement

COST

CE GFP Replacement: IAW - PWS Section 2 Para. 2.1.2.17.

(Cost Reimbursable) NTE - $1 million

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
Replacement of Government-Furnished IT

COST

Replacement of Government-furnished (IT Equipment): IAW - PWS Section 7 Para. 7.1.2.5.12.6.

(Cost Reimbursable) NTE - $1 million

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
Projects

COST

Projects: IAW - PWS Section 11 Para. 11.1.2.2.4.1.5. and 12.1.2.1.

(Cost Reimbursable) NTE - $750K

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
Government Directed Travel

COST

Government Directed Travel/Per Diem/Conferences, Seminars, Classes, Training: IAW - PWS Section 2 Para. 2.1.2.27.

(Cost Reimbursable) NTE - $30K

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
CEMAS

COST

CEMAS: IAW - PWS Section 11 Para. 11.1.2.2.

(Cost Reimbursable) NTE - $150K

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
CE Routine and Planned Work

COST

CE Routine and Planned Work O&M (Sustainment): IAW - PWS Section 11 Para. 11.1.2.2.

(Cost Reimbursable) NTE - $1 million

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
OPTION
Transporting of DoDS

COST

Transporting of Department of Defense School (DoDS): IAW - PWS Section 25 Para. 25.1.2.8.

(Cost Reimbursable)

ESTIMATED COST

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
All Services

FFP

Manage and perform all activities and functions related to leading, managing, training, and directing people and resources dedicated to performing all activities of the PWS. PWS Section 2 Para. 2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Maintenance (FOD)

FFP

PWS Section 3 Para. 3.1.3

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Resource Management

FFP

PWS Section 5 Para. 5.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Telecom/Telephone Wire Services

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1., 7.1.2.1.1.7., 7.1.2.1.1.13., 7.1.2.1.1.14.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Telephone: Moves, Adds, and Changes

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1.17.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Telephone Switch System O&M

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
E911 System

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.1.18

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
BTS Work Center Records

FFP

COMM & IT: IAW - PWS Section 7 Para. 7.1.2.1.2.1

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Manhole/Handhole

FFP

COMM & IT: Manhole/Handhole and Building Terminal Inspection/Maintenance/Repair IAW - PWS Section 7 Para. 7.1.2.1.2.1.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Long/Haul/Commercial Telecom MGT

FFP

COMM & IT: Long-Haul/Commercial Telecommunication Mangement - IAW - PWS Section 7 Para. 7.1.2.1.2.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Personal Wireless Communications

FFP

COMM & IT: Personal Wireless Communicaitons Systems Work Center - IAW - PWS Section 7 Para. 7.1.2.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Land Mobile Radio

FFP

COMM & IT: Land Mobile Radio Services and Network System - IAW - PWS Section 7 Para. 7.1.2.2.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Asset Mgt Work Center

FFP

COMM & IT: Asset Management Work Center - IAW - PWS Section 7 Para. 7.1.2.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Plans and Implementation Work Center

FFP

COMM & IT Plans and Implementation (P & I) Work Center - IAW - PWS Section 7 Para. 7.1.2.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Contingency Operations

FFP

COMM & IT: Contingency Operations For Displaced Gov Agencies - IAW - PWS Section 7 Para. 7.1.2.4.14.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Information Technology Asset Mgt

FFP

COMM & IT Information Technology Asset Management - IAW - PWS Section 7 Para. 7.1.2.5.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Network Enterprise Technology Mgt

FFP

COMM & IT: Network Enterprise Technology Management and Network Performance Management - IAW - PWS Section 7 Para. 7.1.2.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Network Infrastrucure Management

FFP

COMM & IT: Network Infrastructure Management - IAW - PWS Section 7 Para. 7.1.2.5.12.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Network and Information Security MGT

FFP

COMM & IT: Network and Information Security Management - IAW - PWS Section 7 Para. 7.1.2.5.13.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Web Services Administration

FFP

COMM & IT: Web Services Administration - IAW - PWS Section 7 Para. 7.1.2.5.13.5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Network Server/Services/Systems Support

FFP

COMM & IT: Network Server/Services/Systems and Applications Support - IAW - PWS Section 7 Para. 7.1.2.5.14.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Data Center Consolidation

FFP

COMM & IT: Data Center Consolidation (DCC) - IAW - PWS Section 7 Para. 7.1.2.5.14.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Publishing Management

FFP

Provide the administration of the Publications and Forms Management Programs. IAW - PWS Section 9.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Financial Management (Resources)

FFP

CE: Provide Financial Management and support to CE activities. IAW - PWS Section 10 Para. 10.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Real Estate/Real Property

FFP

CE: Provide real estate/real property management and accountabily support for all DoD and AF real property under the control of the installation. IAW - PWS Section 10 Para. 10.1.2.2., 10.1.2.6. and 10.1.2.6.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
NexGen IT

FFP

CE: IAW - PWS Section 10 Para. 10.1.2.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
General Officers Homes (GOH)

FFP

CE: IAW - PWS Section 10 Para. 10.1.2.4.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Family Housing Management

FFP

CE: IAW - PWS Section 10 Para. 10.1.2.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
UH (Dormitory Managment

FFP

CE: IAW - PWS Section 10 Para. 10.1.2.4.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Furnishing Management Office (FMO)

FFP

CE: Management and perform all activities and functions related to leading, managing, and directing people and resources didicated to performing FMO activities. IAW - PWS Section 10 Para. 10.1.2.4.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Environmental

FFP

CE: Manage and provide oversight to ensure compliance, conservation, and pollution prevention. IAW - PWS Section 10 Para. 10.1.2.5. and 10.1.2.6.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Operations Management

FFP

CE: Manage and perform all activities and functionrelated to leading, managing, training, and directing people and resources dedicated to performing opertions and mantenance activities. IAW - PWS Section 11 Para. 11.1.2.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
O&M (Sustainment)

FFP

CE: Provide professional inspection, maintenance, repair, opertions, and minor alterations. IAW - PWS Section 11 Para. 11.1.2.2. except 11.1.2.2.2.1.1., 11.1.2.2.1.2., 11.1.2.2.1.3., 11.1.2.2.2.1.4., 11.1.2.2.2.1.5., 11.1.2.2.2.2., 11.1.2.2.4.5. and 11.1.2.2.4.6.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Pavement Clearance

FFP

CE: Provide removal of debris, snow, and ice. IAW - PWS Section 11 Para. 11.1.2.2.1.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Electrical Distribution System

FFP

CE: Maintain, repair, and replace the electrical distributions, real property, accountable RPIE, and associated non-RPIE items. IAW - PWS Section 11 Para. 11.1.2.2.2.1.1.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Sewer/Waste Water System

FFP

CE: IAW - PWS Section 11 Para. 11.1.2.2.2.1.2.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Water Distribution

FFP

CE: Maintain, repair, replace,and operate the water distribution and water store tank sysems, fire hydants, real property, accountable RPIE, and associated non- RPIE items. IAW - PWS Section 11 Para. 11.1.2.2.2.1.3.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
12
Months
OPTION
Gas Distribution

FFP

CE: Maintain, repair, replace, and operate the gas distribution system, real property, accountable RPIE, and associated non-RPIE items. IAW - PWS Section 11 Para. 11.1.2.2.2.1.4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT

This is the start of the file's text. The full file is on GovTribe.