- Install Outriggers/Wire, Bldg 1721
- Solicitation number
- FA283519RA019
About this file
Government Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Revised_Government_Statement_of_Work_19_Apr_19.pdf | ||
| Wage_Determination.pdf | ||
| Solicitation_-_FA283519RA019.pdf | ||
| Site_Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
For
Install Outriggers/Wire Location Building: 1721
By: Lenore Gerossie
WORK ORDER NUMBER: 67452
DATED: 25 January 2019
1. GENERAL INFORMATION:
This project is intended to install outriggers/wire in accordance with all applicable National, Air Force, State and local building codes and regulations. This work will consist of supplying/furnishing all labor, materials, tools, equipment, shop drawings, and expenses necessary to accomplish the work described below in compliance with the Commonwealth of Massachusetts Building Code and Massachusetts General Law requirements, Unified Facilities Criteria (UFC) state and federal codes, base standards and manufacturer’s instructions. Where there is a conflict between nationally recognized codes and local codes, the most stringent shall apply. Effective immediately: Due to safety concerns the use of manhole fixed ladders on Hanscom AFB is prohibited for the purpose of entry and egress is prohibited. An alternative means is authorized (i.e. appropriate portable ladder/personnel lowering device).
2. SCOPE: Install Outriggers/Wire
Chain link fence is approximately 130 feet long Add an additional chain link fence with outriggers around fire station plastic fencing (see attached drawing for reference) Install concrete terminal post footings and concrete line post footings. Concrete terminal post footings and concrete line post footings shall be 36” deep and 12” in diameter. (3”) terminal posts shall be installed at the beginning, in the center, and at the end of the length of fence to be installed. (2-3/8”) line posts shall be installed equally spaced between the terminals posts and spacing shall be no greater than eight feet on center.
Pour concrete terminal post and concrete line post.
Install (3”) terminal posts and (2-3/8”) line posts. All fence posts shall be installed plumb and all fence posts shall be aligned in a straight line.
Install approx. 130 feet of chain link fence and all necessary hardware which shall include but not limited to top rails, caps, tension bars, tension clips, stretcher bars, bottom rails, nuts, bolts, washers
Field verify measurements New fencing to match existing This includes 3 gates 1 20 ft. and 2 10 ft.
Install triple strand outriggers to top of fencing and 3 gates Dig Safe is required for this project
3. GENERAL REQUIREMENTS:
Work includes, but is not limited to the following:
a. Provide resolutions of any technical problems that arise during the construction.
b. Should any change in scope be required, it must be coordinated with the Project POC and approved as a change order prior to performing the change in work.
c. Provide updates to Project POC. Any construction issues, changes to schedule, or schedule slippages with justification must be reported at the periodic updates.
d. The Contractor is solely responsible for compliance with the Occupational Safety and
Health Act of 1974 (OSHA) and the protection of their employees and all sub-contractor employees. In performing work under this contract on a Government installation, the contractor shall report any accidents involving Air Force property/equipment damage, or contractor personnel injuries occurring on the job or an accident resulting in death, injury, occupational disease, or adverse environmental impact to the contracting officer within five days.
e. Any modifications and addition on a facility that contains Lightning Protections System (LPS) This includes paint projects, roofing projects, projects requiring roof penetrations, installation of new HVAC or other metallic equipment, antenna installation, or other work.
Additions and modifications to the facility envelope require re-evaluation of the LPS for the completed facility as a whole. The LPS required by the addition or modification shall not be a simple addition to the LPS. The LPS must be considered a single entity and must comply with requirements of a single LPS upon completion. The LPS shall be inspected by a commercial, third-party inspector whose sole work is lightning protection, and shall be certified by this third-party inspector as compliant with AFI 32-1065 and NFPA 780, in that priority order. Projects calling for an LPS addition to an existing LPS project shall consider the configuration of the final LPS in the initial design. Projects of this type shall ensure the final LPS as a whole is compliant with AFI 32-1065 and NFPA 780, in that priority order. The same third-party inspector requirements shall apply.
f. Complete the “builder data inventory and assessment sheet” for newly installed assets, ensuring the bar code number is attached to the new equipment. Transfer bar codes from any removed equipment to the builder assessment ½ sheet form
g. Provide three (3) copies of O & M manuals and warranty letter
h. Period of Performance 60 days after award of contract
4. ADMINISTRATION:
Points of Contact (POC):
POC: Lenore Gerossie ___________________ Phone Number. (781) 225-2960 Alternate POC: Roland Hartz________________ Phone Number. (781) 225-5924