Q&A dated 22 July 2019
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Combined_Synopsis_-_Solicitation_(amended).pdf | ||
| Combined_Synopsis_-_Solicitation_Will-Burt's_Stiletto_Mast.pdf | ||
| DFARs_252_209-7999.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
22 July 2019
Q&A FOR FA2823-19-Q-9033
Q1) Please address the conflicting delivery request dates.
A: Delivery is requested to be made NLT 15 November, 2019, but expedited shipment is encouraged. Solicitation will be updated to address this discrepancy.
Q2) Please address the conflicting DFARS 252.213-7000 title and date.
A: Solicitation will be updated to address this discrepancy.
Q3) What is the size of the cable conduit and the respective basket that is being requested?
A: Please provide quote for 1.0” ID cable conduit and the respective basket that can capture the conduit when it is nested.
Q4) What kind of cables will be used with this equipment and will you require a quote for inserting the cables into coiling cable conduit?
A: Cable that is to be inserted into the conduit will be provided by the requirement owner (2x 0.25” CAT 6 cables). If there is a fee that is required for insertion of the cables into the coiling cable conduit, a quote is being requested to capture that service/fee.
Q5) Addressing “Must have PC operation capabilities,” is PC Interface Cable required?
A: Additional configuration(s) that are required to have “PC operation capabilities” is not being requested at this time. However, the stiletto mast must have option(s) to allow for this capability to be purchased to be added on to the equipment should additional funding become available for this requirement.
The combined Synopsis/Solicitation has been amended to address the above concerns. The following changes have been made:
1) Specifications/salient characteristic line 12 now requests for “an option” for PC operation capabilities
2) Specifications/salient characteristic line 13 now specifies the desired size of the coiling cable conduit.
3) One additional specification/salient characteristic has been added requesting cable insertion service for the coiling cable conduit
4) Specifications/salient characteristic line 15 has been updated to be in parallel with the update of line 13.
File details come from the government source that posted it.