Repair HVAC and Interior of Dining Hall, Bldg 3017, Duke Field, Eglin AFB, FL
Solicitation number
FA282315R4020
Issued by

About this file

Statement of Work FTFA 13-9005

View the file

Other files

File Type Posted
FTFA_13-9005_Specifications_Final_REV_1.pdf PDF
DRWGS_13-9005_Sol_15R4020.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

FOR CONSTRUCTION

FTFA 13-9005

Repair HVAC and Interior, Dining Hall, Bldg 3017

22 April 2015

1. STATEMENT OF WORK: In general, the work will consist of HVAC system repair and serving line enlargement, and interior improvements, associated electrical work and incidental related work, as indicated on the contract documents.

The Contractor shall furnish all parts, labor, tools, materials, plant, and transportation necessary to perform work required in this contract. Work shall be performed in accordance with the requirements and regulations set forth in the plans, specifications, and the contract documents.

Provide (1) hard copy set, and one (1) Mylar set of As-Built drawings upon completion of the construction of the project. As-builts are also to be provided in .pdf format and .dwg format

(AutoCAD). Electronic Design Deliverables are to comply with UFC 1-300-10, Electronic

Design Deliverables (EDD) Manual of Policies and Procedures.

2. LOCATION: The work is located at Duke Field, Eglin AFB Reservation, FL. The exact location will be indicated to you by the Contracting Officer.

3. SITE INSPECTION: Prospective bidders are expected to visit the areas of work and verify all conditions and dimensions.

4. SUBMITTALS: To be discussed at the preconstruction meeting include, but may not be limited to: Project Schedule, Shop Drawings, Material Submittals, Work permits, Utility Outage

Requests, Utility Connection Requests, Welding Permits, and Burning Permits.

-The contractor is responsible for marking and verifying all utilities not marked.

5. CONFLICTS: In case of conflict between different Air Force standards or other any information herein this document, the more stringent requirement criteria and/or work-effort shall apply and take precedence.

6. COMPLETION DATE: The Period of Performance (POP) is 305 Calendar days (10 months) from the Notice to Proceed.