APPENDIX A-

SCOPE OF WORK

ACJP082133

ACJP082133 1 Date Feb. 25, 2009

SYSTEM DESCRIPTION

Repair Domestic Water Main Valves, ACJP082133

Isolation Valves

Provide isolation valves for the domestic water system.

These valves are to separate L.A. Air Force Base into four Quadrangles. Contractor is to identify and define isolation locations. At a minimum, contractor is to coordinate approval of isolation locations through Los

Angeles Air Force Civil Engineering PM, Fire Chief, and Plumber. No construction work is to begin without a set of working drawings and approval from 61 CELS.

For the contractor convenience, enclosed is a CAD drawing (CAD 1) showing the existing water line system.

NOTE:

1. CONTRACTOR IS RESPONSIBLE FOR

VERIFYING LOCATION OF UTILITY

LINES VIA THEIR OWN MEANS. 61 CELS

STAFF MAY ASSIST IN LOCATING

LINES HOWEVER; CONTRACTOR IS

FULLY RESPONSIBLE FOR PROPER

LOCATION OF LINES.

At a minimum the Contractor shall address the following in his/her specifications and plans:

Excavation

“Dead Man” Trust Blocks

Pipe and fittings Materials

Valves installations

Backfilling

Gate Valves

Valve Boxes

Details

Flushing and Disinfection of water line

Pressure Testing

General Construction Standard of Care – Minimum

Requirements:

SITE EARTHWORK

COMMON EXCAVATION

The contractor is to follow design engineer’s construction drawings, and design specifications. Note:

All construction drawings must be approved by Air

Force Civil Engineering prior to construction. All work must follow approved schedule any acceleration or delay of schedule must be approved by Air Force

Contracting officer.

COMPACTION

The contractor is to follow design engineer’s or geotechnical engineer’s compaction specification.

Certified Compaction testing results MUST be supplied to

Air Force Civil Engineering PM with in 24 hours after testing or 24 hours prior to placement of any structure above compacted material.

SHORING

The Contractor is to follow the design engineer’s shoring plan. Shoring requirements shall be described on applicable Health and Safety Plan.

TEMPORARY DEWATERING

The Contractor is to follow the design engineer’s dewatering plan, and or phasing plan. Dewatering requirements shall be described on applicable Health and

Safety Plan, and on Environmental Protection Plan.

OTHER SITE EARTHWORK

RE-SURFACING

Disturbance of existing finished road surfaces, sidewalks, grassed areas etc. must be identified and approved by Los

Angeles Air Force Base 61 CELS prior to commencement of construction excavation. If and when different sections of the base are to be disturbed it is recommended that these sections be identified on a phasing plan. Disturbed areas must be made whole (i.e. grades to match existing provide proper drainage etc.) once construction and or installations are accomplished.

BASE & SUBBASE MATERIALS

Base and Sub-Base Materials for use to be identified and specified on plans by design engineer / geotechnical engineer, or any qualified professional in the geo-engineering sciences.

CURBS & BUTTERS

Finished grade elevations for curbs and gutters shall be shown on construction drawings and shall tie into adjacent grades.

ASPHAL PLACEMENT

Design engineer to specified type of asphalt cement to be used on construction drawings. Contractor shall submit bill of materials showing type of asphalt placed within 24 hours after placement. Deviation of placement material will not be allowed without design engineer’s approval.

Recycled asphalt pavement material may be used for bituminous concrete pavement as long as it is approved by design engineer. Used quantities of recycled asphalt pavements and areas paved with such materials shall be reported to Civil Engineering PM with in 24 hours of placement.

APPENDIX A-

SCOPE OF WORK

ACJP082133

ACJP082133 2 Date Feb. 25, 2009

MARKING & SIGNAGE

Disturbance to markings and signage shall be kept to a minimum and / or replaced once construction is complete.

PAVED SURFACES

Disturbance of existing finished road surfaces, side-walks, grassed areas etc. must be identified and approved by Los Angeles Air Force Base 61 CELS prior to commencement of construction / excavation. If and when different sections of the base are to be disturbed it is recommended that these sections be identified on a phasing plan. Disturbed areas must be made whole (i.e. grades to match existing, and provide proper drainage etc.) once construction and or installations are accomplished.

EROSION CONTROL MEASURES

If applicable, develop erosion protection plan.

TOPSOIL AND PLANTING BEDS

Protect, minimize, disturbance to topsoil and planting beds.

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .