Atch3_Q&A_18SEP2018.pdf

PDF 50 KB Posted

Attached to
Central Utility Plant Breakers Repair at Schriever AFB
Solicitation number
FA255018Q2030
Issued by

About this file

Attachment 3 - Q&A dated 18 September 2018

View the file

Other files

File Type Posted
SF30.pdf PDF
Atch2_WD_15-5417.pdf PDF
Atch4_CircuitBreaker_Photos.pdf PDF
Atch1_PWS_18SEP2018.pdf PDF
CupBreakers1449.pdf PDF
Atch1_PWS_7UN2018.pdf PDF
Atch3_Q&A_13SEP2018.pdf PDF
Atch2_WD_15-5417.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Market Research/Site Visit Questions & Answers 18 September 2018

Question #1: Do all of the breakers require repair/calibration?

Answer: Not all breakers require repair/calibration, but all the breakers are due certification.

Question #2: Do the breakers have to be repaired on site?

Answer: No. The breakers will be delivered to 780 Enoch Rd, Schriever AFB, CO 80912 for the contractor to pickup.

Question #3: Do the contractors have to hold a NATE certification?

Answer: Yes, the contractors need to be NATE certified.

Question #4: Have the breakers been rebuilt before?

Answer: Yes some breakers were rebuilt, and the rest certified back in 2017 by a CEMIRT team.

Question #5: What is the delivery date?

Answer: The period of performance for this requirement is 27 September 2018 – 27 November 2018.

Question #6: Does the government want the breakers to just be cleaned and tested, or do they want an overhaul?

Answer: The government wants the breakers to be cleaned, tested, overhauled, provided with a new inspection sticker, and delivered with the breakers wrapped up/sealed.

Question #7: 1.3 SCOPE OF PROCEDURE – This sections does not include any discussions of repairs. Is this RFQ for the testing only and a price will then be submitted to the Government for the repairs to be made? Will this repair price be put out for bid as well?

Answer: Please refer to the answer for question number 6. Please provide pricing for what the requirements in the PWS.

Question #8: 1.21 SERVICES SUMMARY – In the table provided there is a requirement for Emergency Maintenance. Since this isn’t an annual maintenance contract, how long would this Emergency Maintenance period last?

Answer: Emergency maintenance and technical support have been deleted from the PWS.

Please see the PWS dated 18 September 2018.