Q and A_Answered.pdf

PDF 182 KB Posted

Attached to
KSCC 18-1575 Replace Tower 110 Federal contract opportunity
Solicitation number
FA252125B0006
Issued by
Department of the Air Force Space Command

About this file

This document is a Questions and Answers (Q&A) form for the KSCC 18-1575 project to replace Tower 110 at Kennedy Space Center. The solicitation involves constructing a new 210-foot self-supporting tower to replace an existing 204-foot aluminum scaffold tower, with work to be completed within 265 calendar days after notice to proceed. Key technical requirements include providing a new foundation design, lightning protection system, ground loop, and FAA beacon lights, while maintaining continuous weather instrumentation operations during the tower replacement.

Significant project details include constructing the new tower 30 feet east of the current tower location, with the existing tower remaining operational during construction. The government anticipates 25 non-access days due to launch activities, and contractors must coordinate closely with launch operations. Additional requirements include obtaining necessary permits, providing PE-stamped shop drawings, meeting FAA lighting specifications, and ensuring all on-site operations are performed by Florida-licensed personnel. The contract is contingent on fund availability, with the government reserving the right to cancel the solicitation.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTION AND ANSWER FORM

Project Number: KSCC 18-1575

Project Description: Replace Tower 110, Bldg. 63302

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page ___________

Other (Specify) launch schedules

Question #1: Do you have the launch schedules that you can provide for the Cape and Kennedy Space

Center?

Answer: Rough schedule can be tracked on Spaceflightnow.com. Construction execution will require daily contact with our Cape Support Office, which will provide daily updates for launch operations and critical days.

RFP Section __Section B________ Paragraph ____1_____

SOW/Technical Specification/Drawings paragraph/page ____Attachment # 2 ____Sheet # S-101___

Other (Specify) Replace Tower 110, Bldg. 63302, in accordance with the attached project specifications and drawings ________________________

Question #2: May we get a copy of the Final Stamped Tower Designs please? What was attached we believe is not the final stamped drawings.

Answer: The 100% final drawings are the drawings to be used for this solicitation.

RFP Section Section B Paragraph 1

SOW/Technical Specification/Drawings paragraph/page Attachment # 2 Sheet # S-501

Other (Specify) Replace Tower 110, Bldg. 63302, in accordance with the attached project specifications and drawings

Question #3: May we get a final copy of the Geotech report that the final foundations were designed to, please?

Answer: Geotech report provided with this response.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page 01 11 00.00 30 / 1.2

Other (Specify) ___________________________

Question #4: Specifications reference to provide foundation design for the new 205-foot tower. Is this a design build project? Is the foundation a design element to be signed and sealed by an engineer?

Answer: This is not a design-build project, the foundation design is provided. See note AP-10, S-

501, installing contractor is required to provide two non-production test piles, under the direction of certified engineer.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page 01 11 00.00 30 / 1.6

Other (Specify) ___________________________

Question #5: Other than holidays what are the number of anticipated non-access days that all contractors are to use for scheduling?

Answer: This solicitation anticipates 25 days of non-access. Foundation and tower installation days will need to be pre-coordinated with the neighboring Launch Service Provider.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page _01 11 00.00 30 / 1.10

Other (Specify) ___________________________

Question #6: Will a complete outage of the existing tower be allowed during the full construction duration of the new tower?

Answer: The new foundation and tower shall be constructed while the current tower is in operation. Once the new tower is in place, instrument government owners will take a short outage to remove instruments off former tower and place on new tower. Demolition will take place operation last.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page 01 35 26 / 1.6.1.1

Other (Specify) ___________________________

Question #7: Specification requires a SSHO to be at the work site at all times. It further allows the

SSHO to share duties with the QCM (Quality Control Manager). The QCM is not required to be at the work site at all times but must be available at the work site within 30 minutes upon request. May the

SSHO also work remove and be available at the work site within 30 minutes upon request similar to the

QCM?

Answer: SSHO must be on site at all times. Past experience has had superintendent carrying duties of SSHO.

SOW/Technical Specification/Drawings paragraph/page Division 03 – Cast-In-Place Piles

Other (Specify) ___________________________

Question #8: Will any additional specification be provided other than what is noted on the plans?

Answer: The full specification has been provided.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page C-101 / Flag Note 1.

Other (Specify) ___________________________

Question #9: Flag note 1 requires “New tower will be in exact location as the demolished tower.” At the site visit it was requested to keep the current tower in operation during the construction of the new tower to limit the outage of the existing tower. To complete the project based on Sheet C-101 the existing tower will need to be completely removed and placed in an outage during the duration of construction. Will an outage of the existing tower be allowed during the duration of construction? If a complete outage is not allowed what is the maximum offset allowed and any additional Clearing, Earthwork, and Embankment specifications needed?

Answer: A lengthy outage is not able to be approved. The new foundation and tower shall be constructed 30’ east of current tower location, and while the current tower is in operation. Once new tower is in place, instrument government owners will take a short outage to remove instruments off the unused tower and place on new tower. Once instrument operation is confirmed, the unused tower will be demolished.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page : N/A

Other (Specify) ___________________________

Question #10: Subsurface investigations, geotechnical reports and boring information is not found within the solicitation. Is this information available?

Answer: Geotech report provided with this response.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page General Notes #9

Other (Specify) ___________________________

Question #11: ALL STRUCTURES REQUIRE PERIODIC MAINTENANCE TO EXTEND LIFE

SPAN AND TO ENSURE STRUCTURAL INTEGRITY FROM EXPOSURE TO THE

ENVIRONMENT. A PLANNED PROGRAM OF MAINTENANCE SHALL BE ESTABLISHED BY

THE OWNER. THIS PROGRAM SHALL INCLUDE ITEMS SUCH AS, BUT NOT LIMITED TO,

PAINTING OF STRUCTURAL STEEL, PROTECTIVE COATINGS FOR CONCRETE, SEALANTS,

CAULKED JOINTS, EXPANSION JOINTS, CONTROL JOINTS, SPALLS AND CRACKS IN

CONCRETE, AND PRESSURE WASHING OF EXPOSED STRUCTURAL ELEMENTS EXPOSED

TO SALT ENVIRONMENT OR OTHER HARSH CHEMICALS.

Do we need to provide a maintenance period?

Answer: A period of maintenance does not need to be provided. Project deliverable is for a maintenance plan that can be used once the project/contract is completed.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page C-101___

Other (Specify) ___________________________

Question #12: Drawings on page C-101 show the new tower being located at same location as existing tower foundation. On the site visit, the government indicated that the new tower would be located about

19’ east of existing tower. Please advise.__________________________________________

Answer: A lengthy outage is not able to be approved. The new foundation and tower shall be constructed 30’ east of current tower location, and while the current tower is in operation. Once new tower is in place, instrument government owners will take a short outage to remove instruments off then unused tower and place on new tower. Once instrument operation is confirmed, the unused tower will be demolished.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/ PageS-101__

Other (Specify) ___________________________

Question #13: Drawings page S-101 shows table labeled “Tower Design Loading” for new tower, lists

(14) mounts. Can you further clarify if the Contractor is to purchase and/or install these mounts?______________________________________

Answer: Same table, note column “Mount Provided”, all lines are stated as “no”. Contract includes the need to provide and install all mounts.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page __________

Other (Specify) General Scope of Work______________________

Question #14: Do we install and wire-in any of the weather instruments?

Answer: No. As Government Furnished Instruments, government will keep requirement for those installations.

SOW/Technical Specification/Drawings paragraph/page __________

Other (Specify) Normal Working Hours_____________________

Question #15: For weekend work hour requests, do we need an escort and is there a cost?

Answer: Specification states work hours 0700- 1600, M-F. Work beyond these hours, or on weekends, will require request. If approved, that work will not require escort.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page __________

Other (Specify) Normal Working Hours/Mobilization_____________________

Question #16: Are enclosed equipment trailers and other equipment allowed to remain at job site overnight?

Answer: Due to proximity to launch operations, storage of overnight unanchored wheeled vehicles will not be allowed. A laydown area will be identified.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page __________

Other (Specify) Existing Conditions_____________________

Question #17: Is it possible to obtain the As-Built drawings and specs on the original tower?

Answer: The as-built is not available.

RFP Section ____I______ Paragraph _FAR Clauses by Reference________

SOW/Technical Specification/Drawings paragraph/page __________

Other (Specify) 252.243-7002 Requests for Equitable Adjustment.

Question #18: Should costs be incurred due to launches, weather, etc., beyond the allotted days per the

Specs, will an REA or MOD be granted? i.e. Crane is delivered on site, then site is shut down for 2-3 weeks, at a rate of several thousands of dollars per day, etc.

Answer: A REA will be assessed on a case-by-case basis.

RFP Section __Section B________ Paragraph ____1_____

SOW/Technical Specification/Drawings paragraph/page ____Attachment # 2 ____Sheet # CD-101___

Other (Specify) ___Current Tower site plan for demo shows foundation footprints only no tower

Question #19: _________May we get a copy of the current guyed drawings?______

Answer: The as-built is not available.

RFP Section _ Section B _________ Paragraph _____1____

SOW/Technical Specification/Drawings paragraph/page __Attachment # 2 ___Sheet # S-502__________

Other (Specify) ______ Replace Tower 110, Bldg. 63302, in accordance with the attached project specifications and drawings _____________________

Question #20: Are existing MET materials, removal, for reuse and installation on the new structure to be included in our proposal?

Answer: Meteorological equipment will be removed and installed on new tower by government.

RFP Section __ Section B _________ ________ Paragraph ____7 & 8_____

SOW/Technical Specification/Drawings paragraph/page ____ Attachment # 2 ___Sheet # E-501_______

Other (Specify) ____

Question #21: Has the FAA/ FCC determinations already been advised if so is painting of the structure required?

Answer: Per FAA Circular AC 70-7460, obstruction lighting at top and midlevel elevations is acceptable notification, painting is not required. Note: Design page S-101, “notes” section bottom right, states requirements for FAA approval, to be accomplished by contractor.

RFP Section Specifications__________ Paragraph ___ 1.11______

SOW/Technical Specification/Drawings paragraph/page: Section 01 11 00, Pages 9-10

Other (Specify) ___________________________

Question #22: Are there hazardous materials involved (lead-based paint, asbestos, etc.) regarding the removal of the existing tower?

Answer: The existing tower is an aluminum scaffold tower, has not been painted.

RFP Section _Specifications_________ Paragraph ___1.10.1______

SOW/Technical Specification/Drawings paragraph/page: Section 01 11 00, Page 7

Other (Specify) ___________________________

Question #23: Are there specific systems or utilities that must remain operational at all times?

Answer: The weather instrumentation must remain in operation at all times, with exception of when they are moved by the government to the new tower. The timing of that move will have to be approved by owners of the instruments.

RFP Section __Specifications________ Paragraph ___1.6______

SOW/Technical Specification/Drawings paragraph/page: Section 01 11 00, Page 4

Other (Specify) ___________________________

Question #24: Does this project site fall within a US Customs and Border Protection (CBP) controlled area? If so, what are the procedures for obtaining appropriate access or badges?

Answer: No.

RFP Section ___Specifications_______ Paragraph ___3.7.1______

SOW/Technical Specification/Drawings paragraph/page: Section 01 11 00, Page 15

Other (Specify) ___________________________

Question #25: Is a PE-stamped Lifting Operation Plan required, or will an in-house engineered plan be acceptable if it includes all required calculations and drawings?

Answer: A P.E. stamp is required for lift plan.

RFP Section _Specifications_________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page: Section 26 41 00, Electrical Spec Section

Other (Specify) ___________________________

Question #26: Who is responsible for determining FAA lighting requirements and coordinating with the FAA? Will final lighting layout require FAA approval, or is this contractor-driven?

Answer: Design page S-101, “notes” section bottom right, states requirements for FAA approval, to be accomplished by contractor.

RFP Section __Specifications________ Paragraph ___3.1.2______

SOW/Technical Specification/Drawings paragraph/page: Section 01 11 00, Page 11

Other (Specify) ___________________________

Question #27: What is the current processing time for Restricted Area Badges (RAB) at CCSFS, and are subcontractors permitted to be escorted by badged personnel?

Answer: Any person requiring access to CCSFS requires full badging as described in specification.

With full badging, escort is not required. A three day lead time is required for all badging requests.

This location does not require RAB.

RFP Section __Specifications________ Paragraph __3.6_______

SOW/Technical Specification/Drawings paragraph/page: Section 01 11 00, Page 13

Other (Specify) ___________________________

Question #28: Will the government provide existing survey control points and benchmarks for use in required record drawings?

Answer: Survey markers used for design will be provided.

SOW/Technical Specification/Drawings paragraph/page _C-001______

Other (Specify) __Listed Species Notes_________________________

Question #29: Will the contractor be required to provide a permit for the protected species noted on drawing C-001? If so, what is the review period and approval process by the government for this permit application. If there is a lengthy permit approval period, will the NTP be issued after the permit is approved?_

Answer: An AF form 103 dig permit is required to be completed before any subsurface work may start. The contractor is required to assure all tasks and utility locates of that permit are completed.

Government will accomplish natural resources reviews and actions as identified by the 103 process.

Typically permit is issued before NTP. Separate note, while no protected species (nesting) were noted on this tower at walkdown, it is always a possibility.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page _S-501__________

Other (Specify) __General Note 2_________________________

Question #30: _It states that per drawing S-501 that there is a geotechnical survey completed by

Universal Engineering. Can you please provide the geotechnical survey for review purposes? __________

Answer: Geotech report provided with this response.

RFP Section _13 36 00_________ Paragraph __2.1_______

SOW/Technical Specification/Drawings paragraph/page ___________

Other (Specify) ___________________________

Question #31: __Per spec section 13 36 00, para. 2.1, it states that we are to provide a complete tower design that should include drawings, specifications, bill of materials, and structural calculations. This is a bid build project and the design and specifications have already been provided by the government for pricing purposes. Other than the tower shop drawings that we are to provide, what additional information is the government requesting that would be different than the design and specifications that are in the

RFP?

Answer: Delivery of shop drawings will require a design, list and depiction of materials, calculations, and P.E. stamp. That delivery should be based on, and therefore identical, to the project design.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page ___________

Other (Specify) __General/ Site Visit_________________________

Question #32: _It was noted at the site visit that the existing tower should be removed after the new tower is installed. However; the exiting tower is in the same location where the new one is going. Please provide direction as to what the contractor should do?_

Answer: The new foundation and tower shall be constructed 30’ east of current tower location, and while the current tower is in operation. Once new tower is in place, instrument government owners will take a short outage to remove instruments off then unused tower and place on new tower. Once instrument operation is confirmed, the unused tower will be demolished.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page _S-501__________

Other (Specify) _General__________________________

Question #33: _Will there be a specification provided for the auger cast piles? And can the contractor provide an alternate design for the foundation design? If so, will drilled caissons be an approved alternate for the auger cast piles and pile caps? __

Answer: Installation method (and means) is typically determined by contractor. Identification of auger cast piles in design is due to depth of piles, location near a Launch Service Provider

(restriction on vibrations), and soil types. The soil types include several layers of marl and very loose clays, such that auger cast is one of the few methods that will work in this location. Yes, alternate methods may be recommended for consideration.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page ___________

Other (Specify) _RFP__________________________

Question #34: _The period of performance is stated to be 265 calendar days after NTP is issued.

However; the shop drawings will take approx.. eight weeks to submit and the procurement of the new tower will take approx.. 10-12 weeks from submittal approval. Therefore, this will only leave approx.. 8-

10 weeks to install the new foundation, tower, electrical, demo the old tower, and the project closeout. We feel that this is not an adequate amount of time to perform the work per the RFP requirements and are recommending that the contract period of performance be 365 calendar days from the issuance of the

NTP.___

Answer: PoP will remain 265 calendar days.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page ___________

Other (Specify) ___General__________________

Question #35: _What is the height of the existing tower?

Answer: 204 feet.

RFP Section Paragraph

SOW/Technical Specification/Drawings paragraph/page: Sheet S-501, General Note 2

Question #36: General Note 2 on Sheet S-501 references a subsurface exploration performed by

Universal Engineering Sciences and their report (0330.2300031.000) dated 25 April 23. We request that a copy of that report be provided.

Answer: Geotech report provided with this response.

RFP Section Paragraph

SOW/Technical Specification/Drawings paragraph/page: Sheet C-101, Flag Note 1

Question #37: During the site visit, the subjects of phasing and the 90-day outage limit for the existing weather instrumentation were discussed. During that discussion, it was mentioned that the new tower would first be erected east of the existing tower, then base personnel would transfer the instrumentation from the existing tower to the new tower before demolishing the existing tower. However, Flag Note 1 on Sheet C-101 states the “new tower will be in exact location as demolished tower”. Please verify the exact location of the new tower.

Answer: The new foundation and tower shall be constructed 30’ east of current tower location, and while the current tower is in operation. Once new tower is in place, instrument government owners will take a short outage to remove instruments off then unused tower and place on new tower. Once instrument operation is confirmed, the unused tower will be demolished.

RFP Section Paragraph

SOW/Technical Specification/Drawings paragraph/page: Sheet E-101, Flag Notes 10 & 11

Question #38: There are two Flag Notes (10 & 11) shown on the New Electrical Site Plan; however, there is no information provided for these Flag Notes. Please provide that information.

Answer: Note 11 will be added to state: Provide new L-810 obstruction light, steadily burning red, mounted at mid level of tower. Provide conduit and wire to obstruction lighting controller. Refer to flag note 3 on sheet E-501 for additional information.

Note 10 will be added to state: provide new medium intensity dual lighting system, red/white, obstruction light fixture, 'astronics' DME type l-864/l-865, mounted on support arm. Provide (1) 1" conduit and wiring for power from obstruction lighting controller at base of tower. Provide obstruction lighting controller in NEMA 4x 316 stainless steel enclosure. Refer to flag note 4 on sheet E-501 for additional information.

RFP Section Paragraph

SOW/Technical Specification/Drawings paragraph/page: Sheet E-601, General Note 1

Question #39: General Note 1 on Sheet E-601 indicates that five (5) circuits are required; however, only one (1) circuit is shown on the panel schedule. Furthermore, Flag Note 1 on Sheet E-501 states that all tower elevations are to be fed from a single circuit originating in the service building. Please clarify the total number of circuits required under this scope and identify the intended purpose of each circuit.

Answer: Circuits are identified on design page E-501, flagnote 1-4. Midlevel lights on separate circuit. Obstruction lights on separate circuit.

RFP Section Paragraph

SOW/Technical Specification/Drawings paragraph/page: Sheet E-601, Existing Panel in Bldg. 63303

Question #40: The service building was not accessible during the site visit. Please provide a photo or documentation showing the existing panelboard, including schedule and panel specifications.

Answer: Photographs cannot be provided in this forum. Reference design page E-601.

RFP Section Paragraph

SOW/Technical Specification/Drawings paragraph/page:

Question #41: Flag Note 3 & 4 on Sheet E-501 call for obstruction lighting to be powered from a new obstruction lighting controller. Please provide the specifications or requirements for the new obstruction lighting controller.

Answer: See response to question 39. Controller constraints fall under electrical requirements for enclosure and corrosion control, to perform tasks identified by FAA, and otherwise are identified by vendor.

RFP Section Paragraph

SOW/Technical Specification/Drawings paragraph/page: Sheet E-101, Flag Note 8

Question #42: Please confirm the required size of the new communications enclosure per Flag Note 8 on

Sheet E-101. Additionally, clarify whether this enclosure is to be furnished by the Government or the

Contractor.

Answer: Enclosure must be sized to account for scope of work.

RFP Section SF1442 Paragraph 13d

SOW/Technical Specification/Drawings paragraph/page:

Question #43: Item 13d of the SF1442 calls for offers to be held for 155 calendar days. Given the current tariff situation and potential volatility in material pricing, it may be difficult for material suppliers to hold their pricing for that period of time. Could the amount of time that pricing needs to be held be reduced?

Please advise.

Answer: Due to funding restraints, the Government is requesting to be valid until 30 Sept 25.

RFP Section Paragraph

SOW/Technical Specification/Drawings paragraph/page: Spec 01 11 0.00 30-1.6 “Work Scheduling”

Question #44: Specification Section 01 11 00.00 30-1.6 “Work Scheduling” states the “Contractor shall allow for non-access days where construction activity is prohibited due to hazardous operations or launch activity”. How many “non-access” days should the Contractor reasonable expect during the project?

Please advise.

Answer: This solicitation anticipates 25 days of non-access.

RFP Section Paragraph

SOW/Technical Specification/Drawings paragraph/page: Sheet S-501, Pile Cap Detail

Question #45: Provided that all structural requirements are met, can a ButtonHead mechanical terminator be used in lieu of the 90 degree hook at the top of the pile caps? This will help facilitate the installation of the new auger cast piles without obstruction from overburden. Please advise.

Answer: Use features as determined by design. This can be readdressed after award.

RFP Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page _N/A______

Other (Specify) ___________________________

Question #46: In regard to the solicitation listed above we wanted to use an out-of-state company to fabricate the towers, would that company be able to operate under our Florida license to perform the task.

Answer: Specs 3.8.1 Licenses - Contractor or their subcontractors shall be licensed by the State of

Florida or have an equivalent out-of-state license in all areas applicable to this contract or as otherwise stated elsewhere in this contract. Spec 05 12 00 (structural steel) and 13 36 00 (self supporting towers), only license reference I see is regarding the shop drawings, they have to come from a li-censed P.E. Looks to me all operations on site need to be Florida Licensed, like crane and equip-ment operators, design engineering work, etc.