Questions and Answers_Final.pdf

PDF 107 KB Posted

Attached to
Bldg. 673 Access Control
Solicitation number
FA252124QB098
Issued by

About this file

This document contains the Questions and Answers related to a federal contract opportunity for building access control at Bldg. 673.

The key details are:

  • The contract opportunity is for installing an access control system, including 4 keypad card readers, at Bldg. 673.
  • The agency involved is the Department of the Air Force Space Command.
  • Questions cover various technical requirements such as cabling, power, equipment substitutions, after-hours access, and door hardware.
  • Responses indicate that drawings and blueprints are available, but the government cannot provide budget or cost information.
  • Progress payments are not allowed, and the contractor must bill when parts arrive on site.
  • The contract opportunity appears to be a commercial acquisition, with no set-asides mentioned.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers

1. Are Scaled Drawings available, if so please post.

Answer: Yes, refer to building drawing attachment.

2. Are Ceilings Suspended? Or Hard Lid?

Answer: drop ceiling

3. Are there existing Cable Trays for wiring above ceilings?

Answer: NO

4. Can Existing Wiring be utilized?

Answer: no existing wiring since no cypher system previously existed

5. Is a "UPS" required? If so, What Time/Power Duration is required?

Answer: No

6. Are "Or Equal" Equipment substitutions allowed?

7. Is "Plenum Wire" acceptable?

Answer: Unk

8. Is "After Hours Access" for said work, available to contractor at no add'I cost to the Gov't?

9. What is the height of Exterior Cameras? (If any) Answer: N/A

10.Please provide a list of equipment to be installed Answer: provided by contractor

11 Are there pipe chases between floors?

Answer: single story

12. What is the range of the budget for this project, and is it already appropriated?

Answer: Government can’t provide information because it is commercial acquisition.

13. Because of the high cost of the parts can we bill when parts arrive on site, or in the alternative are progress payments allowed?

Answer: NO

15. How many feet of new wire will have to be run?

Answer: look at bldg. blue print

16. What kind of cipher lock and quantities are required e.g. X-10 Answer: 4 keypad card readers

17. Is there is a door hardware schedule and plan showing every door for access control?

Answer: yes, see blueprint with labeling

18. Can we have a diagram of the building showing the doors that need access control and where you want the door controller to be installed?

Answer: yes, see blueprint attachment.

19. Can we have pictures of the doors and their handles/knobs?

Answer: yes

20. What is the approximate length of each run from the door controller to the door?

Answer: refer to blueprint/drawing attachment.

21. Can you show pictures of the ceilings and walls for us to determine if conduit is necessary?

Answer: yes