01 00 00 - Edited.pdf

PDF 100 KB Posted

Attached to
Simplified Acquisition of Base Engineering Requirements, Multi-Base, Multi-Award Federal contract opportunity
Solicitation number
FA2517-08-R-5002
Issued by
Department of the Air Force Space Command

About this file

Specification

View the file

Other files for this federal contract opportunity

Other files attached to Simplified Acquisition of Base Engineering Requirements, Multi-Base, Multi-Award, newest first.
File Type Posted
Amend3.doc DOC document
Attachment3.pdf PDF
Attachment19.pdf PDF
Attachment8.pdf PDF
Attachment5.pdf PDF
Attachment17.pdf PDF
Attachment11.pdf PDF
Attachment6.pdf PDF
Attachment15.pdf PDF
Div07.zip ZIP file
Div13.zip ZIP file
Div28.zip ZIP file
Div32.zip ZIP file
Attachment13.pdf PDF
Attachment24ClientAuthorization_Letter.docx DOCX document
Attachment23ConsentLetter.docx DOCX document
Attachment11.pdf PDF
Attachment21DemonstrationProjectSOW.zip ZIP file
Div27.zip ZIP file
Attachment5.pdf PDF
43 21 13.pdf PDF
Div33.zip ZIP file
Attachment6.pdf PDF
Attachment20Past Performance Questionnaire.doc DOC document
Div03.zip ZIP file
44 10 00.pdf PDF
43 21 29.pdf PDF
Div26.zip ZIP file
Div07.zip ZIP file
Attachment3.pdf PDF
Div02.zip ZIP file
04 20 00.pdf PDF
Div01.zip ZIP file
Div23.zip ZIP file
RequestforIndustryDay.docx DOCX document
01 55 07.pdf PDF
01 57 20.00 10 PAFB Environmental Protection.pdf PDF
01 35 00.pdf PDF
01 00 07.pdf PDF
Draft6April09.doc DOC document
01 57 20.00 10 SAFB Environmental Protection.pdf PDF
01 57 20.00 10 Environmental Protection.pdf PDF
01 55 07.pdf PDF
01 78 23.pdf PDF
01 55 04.pdf PDF
01 62 35 Recycled Recovered Materials.pdf PDF
01 78 00.pdf PDF
01 55 03.pdf PDF
01 00 02.pdf PDF
Draft6April09.doc DOC document
Show all 50

Simplified Acquisition of Base Engineering Requirements, Multi-Base, Multi-Award has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SABER Solicitation FA2517-08-R-5002

01 00 00-1 03/24/09

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 DEFINITION OF INSTALLATION

1.1.1 Installation will be defined as the property and facilities located within the jurisdiction of the particular base, post, air station, or compound where work is being accomplished.

1.2 PRECEDENCE

1.2.1 Individual installation specific requirements specification sections shall take precedence over the requirements in this section.

1.3 PROJECT DESCRIPTION

1.3.1 The Contractor shall furnish all management, supervision, labor, materials, equipment, and incidentals required for a broad range of maintenance, repair, and minor construction work on various real property facilities at installations covered under this contract, including design and engineering services incidental to construction. The Contracting

Officer (CO) will conduct negotiations with the Contractor and issue individual task orders for maintenance, repair and minor construction projects identified by the Base

Civil Engineer (BCE) or Director of Public Works (DPW) as part of the Simplified

Acquisition of Base Engineering Requirements (SABER) program. Individual task order projects will vary in size, with the majority expected to be less than $750,000, including, but not limited to trades such as carpentry, plumbing, electrical, mechanical, painting, pipe fitting, sheet metal, welding, roofing, site work, site utilities, excavation, concrete, masonry, pavement repair, asbestos and lead paint removal, security hardware installation, and demolition.

1.4 CONTRACT DOCUMENTS, REFERENCE STANDARDS, AND PUBLICATIONS

1.4.1 The following documents are a part of the solicitation and any resultant contract. The

Contractor shall utilize the referenced documents in the accomplishment of tasks prescribed in task orders. The standards and publications listed in each section of the specifications form part of these specifications to the extent referenced. The Contractor shall conform to the provisions of the most recent issue of the listed standard or publication.

1.4.1.1 SABER Specification

a. This SABER Specification is numbered and organized in accordance with the

Construction Specification Institute's (CSI) Master Format. All specifications are filed in division 2 through 48 per CSI guidelines. The specifications are taken from the

Unified Facilities Guide Specifications (UFGS). The UFGS website is http://www.wbdg.org/ccb. The specifications have been edited for this specific contract and will remain unchanged throughout the contract unless officially modified.

http://www.wbdg.org/ccb

01 00 00-2 03/24/09

(1) Standards

(a) The SABER specification furnishes concise industrial and/or commercial standards for maintenance, repair, and minor construction of government facilities.

1.4.1.2 Unit Price Book

a. The Unit Price Book (UPB) is described in Section 01 04 00. The UPB shall be furnished by the Contractor.

1.4.1.3 Unified Facilities Criteria (UfC)

a. The UFC shall be used as the standard building code for all construction under this contract. The UFC website is http://65.204.17.188/report/doc_ufc.html. Any and all changes to the UFC will immediately become requirements of this contract. The UFC references the International Building Code (IBC) 2006 as the basic requirement. The

UFC modifies those basic requirements in UFC 01-200-01.

1.4.1.4 Installation Design Standards

a. Each installation’s facilities excellence plans, design guides, and standards shall be adhered to on all construction projects. Any possible deviations from these standards shall be brought to the Contracting Officer (CO) before implementation. These are listed in each installation specific specification.

1.5 EXECUTION

1.5.1 Pre-Performance Construction Meeting

1.5.1.1 Before work begins on this contract, the Contracting Officer will arrange for a meeting with the Contractor to discuss the contract in general, including administrative matters, project requirements, submittal procedures, approval and payment schedule, quality control expectations, request for proposal and task order procedures, traffic control, construction access requirements, as-built criteria, performance requirements, security procedures, accident prevention, safety, and fire prevention briefings.

1.5.2 Business Telephone

1.5.2.1 At the beginning of this contract, the Contractor shall provide the applicable

Contracting Officers a contractor personnel telephone number, e-mail, and website for regular working hours. The Contractor shall also provide after hours (emergency) telephone numbers for the Program Manager and Installation Construction Manager, as a minimum. The Contractor shall provide the CO with an updated phone list whenever changes in personnel or phone numbers occur. The Contractor is required to provide a means of mobile communications (i.e., cellular phone and/or pager) for the Program

Manager and Installation Construction Manager, and their respective alternates, for the life of the contract. Communications equipment will require special coordination and clearance with installation communications authorities.

1.5.3 Work Hours

1.5.3.1 The Contractor shall complete the work of this project between the hours of 7:00 a.m.

http://65.204.17.188/report/doc_ufc.html

01 00 00-3 03/24/09 and 4:00 p.m. local time, excluding Saturdays, Sundays, and Federal Holidays. See site specific specifications for further information on standard hours. Access to work sites may be restricted to these hours and days. All other times shall be considered non-standard hours and multiplied by the appropriate coefficient. Work during non-standard hours not specified as required by the Contracting Officer will be priced using the coefficient for standard hours. The Contractor may not work during non-standard hours unless the request and justification is approved by the Contracting Officer. The

Contractor must submit a request and justification for working non-standard hours to the Contracting Officer at least 5 working days prior to working non-standard hours.

Work that requires inspection during accomplishment or that prevents inspection of other work after accomplishment must be coordinated with and approved in advance by the Contracting Officer. Inclement weather, operational delays, and security related delays might affect the contractor’s work periods. The Contractor must make allowances for these events, as resulting lost time will not be reimbursable.

a. The Government only recognizes the following legal holidays established by federal statute:

(1) New Year's Day, 1 January

(2) Martin Luther King Day, third Monday in January

(3) President’s Day, third Monday in February

(4) Memorial Day, last Monday in May

(5) Independence Day, 4 July

(6) Labor Day, first Monday in September

(7) Columbus Day, second Monday in October

(8) Veteran's Day, 11 November

(9) Thanksgiving Day, fourth Thursday in November

(10) Christmas Day, 25 December

b. Work Interruptions And Delays

(1) The Contractor may be required to temporarily stop work for operational requirements, special events, installation exercises, or while Distinguished Visitor

(DV) familiarization visits/tours are conducted. Official late reporting and snow calls will affect the contractor’s work periods. The Contractor must make allowances for these events and resulting lost time will not be reimbursable.

Notification to the Contractor shall be provided by the applicable Contracting

Officer.

1.5.4 Safety Requirements

1.5.4.1 See Section 01 35 29.

1.5.5 Fire Protection

1.5.5.1 The Contractor shall be responsible for furnishing adequate and proper fire protection for all phases of the contract work in accordance with UFC and National Fire

Protection Agency (NFPA) standards. See Section 01 35 29, Safety and Health

Requirements.

01 00 00-4 03/24/09

1.5.6 Request For Proposal

1.5.6.1 For each project, the Contractor will be furnished with one copy of the Statement of

Work. The Contractor will also be provided with one set of drawings and specifications, and AF Form 66, if available. The level of the design provided to the

Contractor shall be anywhere from a basic concept to a complete design package. The

Contractor may reproduce the drawings and specifications at the contractor’s own expense if additional copies are needed. The Contractor shall check all drawings and specifications immediately upon receipt for discrepancies and notify the CO immediately of any/all discrepancies found in the form of a Request for Information

(RFI). Enlarged plans and details shall govern where the same work is shown at smaller scales. The Contractor shall compare all drawings and verify the installation before laying out the work and shall be responsible for any errors which might have been avoided thereby.

1.5.7 Site Visit

1.5.7.1 Prior to negotiating any individual task order, the Government and the Contractor will conduct a pre-proposal site visit for each task order. Discussions may include, but are not limited to: scope of work, method of construction, sequence of operations, progress schedule, means of access to project site, delivery and storage of materials and equipment, work restrictions, coordination requirements, project goals, liquidated damages, and potential difficulties/problems. The Contractor shall email detailed site visit minutes to the Contracting Officer within one (1) workday following the site visit.

1.5.8 On-Site Conditions

Drawings showing the location of equipment, piping, ducts and conduit, are diagrammatic and may not show every detail required. In addition, site conditions will not always permit installation in the locations shown. Drawings showing equipment, piping, ducts, conduit, etc., to be removed, altered, or installed may require deviation from the configuration of the demolition or installation drawings due to existence of conflicting ducts, conduits, hangers, light fixtures, structural items, and temporary walls, etc. All such minor details of work which are not shown on the drawings, as well as such items not specifically mentioned in the specifications, but which are essential and necessary for the completion of the work, and to make all systems or equipment operational, shall be considered as incidental and shall be included as part of the work. When this situation occurs, the final placement of permanently installed items shall be subject to approval by the applicable

CO. The Contractor shall be responsible for inspecting to his satisfaction all areas/items of possible conflict. Failure to verify the dimensions and locations will be at the contractor's risk and shall not relieve the Contractor from accomplishing the work required by the task order.

1.5.9 Project Proposal

1.5.9.1 For every Request for Proposal (RFP) associated with a new task order (TO), the contractor shall provide a written proposal (narrative and graphic, as needed) describing his approach to the proposed project work described in the government’s

Statement of Work and project drawings, if any. The contractor shall submit the proposal within 10 working days of the site visit. If the requirement is determined to be a quick response requirement by the CO, the contractor shall submit a Task Order

Proposal to fulfill the requirement within a maximum of five (5) working days from written notification. The proposal shall include, but is not limited to, a cover page or pages, written proposal or contractor SOW, project cost estimate, design assumptions, 01 00 00-5 03/24/09 operational concerns, calculations (as needed), and drawings (as needed). The contractor’s proposals shall be complete and concise. The cover page or pages shall include project title, total project cost, list of assumptions, list of requirements, performance period, material lead times, and any special considerations such as request for winter exclusion, phasing of construction, etc.

a. Cost Estimates

(1) All task orders shall be estimated, negotiated, and awarded based upon prices in the

Unit Price Book (UPB, see Section 01 04 00). The cost estimate portion of the contractor’s proposals shall be prepared and produced using the cost estimating software described in Unit Price Book and Software Requirements (Section 01 04

00, this specification). This applies to all work done on SABER task orders, even if work is done by a subcontractor.

b. Construction Schedule

(1) A construction schedule is required in accordance with FAR 36.515 for projects with a continuous performance period of 30 days or more. Additionally, the

Contractor shall submit a construction schedule when required by the Task Order

(TO) Statement of Work (SOW). The construction schedule shall be on an AF

Form 3064 and completed according to the instructions on the reverse side of the form. In addition to the construction schedule on the AF Form 3064, the TO SOW may require a project to have a critical path or milestone schedule. The Contractor shall provide weekly construction updates on each task order on an AF Form 3065.

c. The contractor shall provide, as part of the proposal, a basic design solution showing a complete understanding of the requirement. Where required, drawings included with the proposal must be thorough enough to allow the Government and contractor to estimate prepriced and non-prepriced items. Design incidental to accomplishing the required tasks outlined in each task order will be required; the extent of these designs will depend upon the complexity of each task. Under the scope of this contract, the complexity will not necessarily require the services of a registered architect or engineer. However, the contractor shall provide sufficient design documentation to substantiate the proposed approach for the task. Also, designs shall clearly illustrate compliance with local, state, and federal building and construction codes. Where required in the SOW or otherwise needed the contractor shall include the following documentation in the task order proposal. This documentation includes, but is not limited to:

(1) Design calculations to substantiate appropriate equipment or material selection/ sizing, component assembly, and proposed layout and sizing of utilities and structural elements. The contractor shall at a minimum supply the following calculation:

(a) Mechanical: HVAC load analysis and unit sizing, pipe sizing, and duct sizing.

(b) Electrical: Electrical system capacity, conductor, conduit, protective devices, and other equipment sizing.

(c) Structural: Structural system and foundation sizing.

(d) Pavement/Site Work: Area run-off quantities, drainage capacities, and grading slopes.

(e) Energy: Provide energy savings and Return on Investment (ROI) .

01 00 00-6 03/24/09

(2) Design drawings showing basic layout and planning of work

1.5.9.2 Record Drawings

1.5.9.3 During the progress of the contract, the Contractor shall a keep record set of drawings on the job site meeting the requirements of paragraph 1.2 of Section 01 78 00 Task

Order Closeout Requirements. If the Contractor fails to maintain the record drawings as required herein, the Contracting Officer will consider that satisfactory progress has not been achieved for the period in question. Final payment will be withheld until As-Built record drawings are submitted and approved by the CO.

1.5.10 Moving Furniture And Equipment

1.5.10.1 For each task order, the Government SABER Office and the Contractor shall coordinate with occupants of the proposed work area on responsibilities of moving furniture and equipment. If the Contractor moves the furniture, associated costs may be included in his proposal. The Government shall hold the Contractor responsible for any damages when the Contractor moves the furniture.

1.5.11 Delivery Of Materials

1.5.11.1 Delivery of materials and equipment shall be made with a minimum of interference to government operations and personnel.

1.5.12 Division Of Work

1.5.12.1 The work shall, so far as practicable, be done in definite sections or divisions and confined to limited areas that shall be completed before work in other sections or divisions are begun.

1.5.13 Clean-Up

1.5.13.1 Hallways, exits, and access routes must be kept free of debris and safe at all times.

Prior to departure from the work area each day, the Contractor shall remove and properly dispose of all waste materials or rubbish generated by the project work. Daily cleanup of all job sites includes leaving the affected project area in good state of order.

Thorough daily cleanup may be required in certain high-visibility areas on a case-by-case basis as described in the statement of work (SOW) for specific Task Orders. Upon completion of the project, the Contractor shall conduct a thorough final cleaning.

1.5.14 Government-Furnished Equipment/Materials

1.5.14.1 The Contractor with his own forces shall transport all government furnished equipment

(GFE) and/or government furnished materials (GFM), if any, described on the task order. The GFE/GFM shall be transported from the government’s storage area to the work site or as indicated on the task order. The Contractor shall follow the instructions of the Contracting Officer regarding the disposition of all government furnished property not consumed in performance of a task order.

1.5.15 Equipment And Furniture On The Site

01 00 00-7 03/24/09

1.5.15.1 The Contractor shall cover equipment and furniture that is to remain in place within the contract operations area and protect it against damage or loss. Store equipment and furniture that is removed in performance of work where directed, or reuse in work as required by project statement of work (SOW), drawings, or specifications. Equipment and furniture temporarily removed shall be protected, cleaned, and replaced equal or better than its condition prior to starting work. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the Contractor.

1.5.16 Damage To Real Property

1.5.16.1 Any damage done by the Contractor to existing real property shall be repaired to prior conditions. Patch and repair any holes or damage done to walls during the removal of any items/material. Match the existing conditions and meet the requirements of these specifications. The Contracting Officer will determine if the repair work done is sufficient. All repair work will be at the Contractor’s expense.

1.5.17 Covered Chutes

1.5.17.1 All chutes used for refuse, and the like, shall be covered or of such design to fully confine the material to prevent the dissemination of dust.

1.5.18 Salvageable Items

1.5.18.1 All materials removed and not reused in the project as specified herein or as required by the project statement of work (SOW), drawings, or specifications, remain the property of the Government. The Contracting Officer will determine if these materials are salvageable or unsalvageable. Salvageable materials shall be managed as directed by the Contracting Officer with the concurrence of the Installation Environmental

Office. See Section 01 57 20.00 10 Environmental Protection for further guidance.

1.5.19 Trash Removal

1.5.19.1 Unsalvageable materials shall become the property of the Contractor and disposed of at the contractor's expense. Materials to be removed shall be removed without damage to adjacent areas. All damage resulting from the removal activity shall be repaired by the

Contractor at no cost to the Government. Repair shall be made with materials of like nature, type and construction as were damaged or exist adjacent to the areas to be repaired. See Section 01 57 20.00 10 Environmental Protection for further guidance.

1.5.20 Monthly Reporting

1.5.20.1 The Contractor must submit reports monthly showing the tons of material disposed of at a landfill and the tons of material diverted from a landfill. See Section 01 57 20.00

10 Environmental Protection, paragraph 8.6 for further guidance.

1.5.21 Permits

1.5.21.1 The Contractor is responsible for listing any and all necessary permits on each project submittal register that are required. The Contractor shall plan for and obtain any and all permits and provide two copies to the Contracting Officer. See Section 01 57 20

01 00 00-8 03/24/09

Environmental Protection for environmental permits. All environmental permits must be coordinated and approved through the Installation Environmental Office.

1.5.22 Environmental Requirements

1.5.22.1 See Section 01 57 20.00 10 Environmental Protection.

1.6 PRODUCTS AND SUBMITTALS

1.6.1 Standard Products

1.6.1.1 Materials and equipment shall be standard products of a manufacturer regularly engaged in the manufacturing of such products, which are of a similar material, design and workmanship. All products shall be new unless otherwise directed in the TO

SOW. See Section 01 57 20.00 10 Environmental Protection for affirmative procurement requirements.

1.6.2 Contract Submittal Requirements

1.6.2.1 In addition to submittals required in each task order, these specifications require various contract submittals. The Contractor shall provide these submittals in accordance with the instructions found in these specifications and on the Submittal

Register.

1.6.3 Submittal Requirements

1.6.3.1 See Section 01 33 00 Submittal Procedures.

1.7 CONCURRENT CONSTRUCTION

1.7.1 Construction work closely related to and/or located at the site of the work under this contract, including other military projects, and normal maintenance and repair work may occur. The Government reserves the right to engage in and to perform work, with its own forces or other contractor forces, of the same type as the successful offeror without breaching or violating this contract.

1.8 UTILITIY SERVICES

1.8.1 Availability Of Utility Services

1.8.1.1 All reasonably required amounts of water and electricity, where available, will be made available to the Contractor by the Government from existing system outlets and supplies. The quality, quantity, and consistency of the utilities supplied is not guaranteed. Some task orders may not allow the use of government utilities. The

Contractor shall, at his own expense, make all temporary connections and install distribution lines. All temporary lines shall be installed and maintained by the

Contractor in a safe and workmanlike manner subject to approval by the CO and shall be removed by the Contractor in like manner prior to final acceptance of the construction. Reasonable quantities of electricity and water used to make final tests of completely installed systems will be furnished by the Government as determined by the

01 00 00-9 03/24/09

Contracting Officer prior to execution.

1.8.2 Fire Hydrant Connections

1.8.2.1 Only compatible adapters shall be utilized for hydrant connections. All connections to fire hydrants shall be provided with a backflow preventor. A hydrant wrench of the correct size shall be used to control the flow. Temporary connections to fire hydrants shall be disconnected at the end of each working day. Any use of fire hydrants shall be coordinated with the Fire Department prior to work. Notification by the Contractor to the CO and Fire Department shall be made ten (10) workdays prior to any work.

1.8.3 Conservation Of Utilities

1.8.3.1 The Contractor shall be responsible for operating under conditions that preclude the waste of utilities and shall comply with energy conservation directives for each installation.

a. Supplemental lighting shall be used only in areas where and when work is actually being performed. When work areas are vacated, lighting shall be turned off.

b. Mechanical equipment for heating, ventilation, and air conditioning systems shall be adjusted by authorized craftsman only.

c. Water faucets or valves shall be turned off after the required usage has been accomplished.

1.9 UTILITY OUTAGES

1.9.1 The Contractor shall request, in writing, any utility outage necessitated by the project work at least 15 working days prior to the proposed outage unless otherwise approved in writing by the Contracting Officer. The Contractor shall not operate any valve, circuit breaker, or other utility shut-off device unless approved by the CO. The Contractor shall verify that there are no conflicts with the scheduled outage immediately before shutting off the utility. The Contractor will be responsible to implement lockout/tag out procedures, as needed.

1.9.1.1 Requests

a. The request shall be directed to the Contracting Officer. It shall reference the specific

Task Order; stipulate the specific utility system and/or circuits to be affected; the location of the work; the time, date, and duration of the requested outage for each system; and describe the contingency plans for restoring the utility to service.

1.9.1.2 Restrictions

a. Outages shall be kept to a minimum both in number and in duration. Where multiple outages are required, as many outages as can be accurately scheduled shall be submitted as a group. No outage shall exceed four (4) hours unless approved in writing by the Contracting Officer prior to outage execution.

1.10 PARKING

1.10.1 Parking of contractor vehicles shall be restricted to the project parking lot at the location

01 00 00-10 03/24/09 designated by the Contracting Officer. Under no circumstance shall the Contractor park vehicles and/or equipment, even temporarily, on the grass, unless approved in advance by the Contracting Officer. The company name shall be prominently displayed on all construction vehicles parked in the designated spaces. Parking shall not violate fire or safety regulations.

1.11 TRAFFIC CONTROL

1.11.1 The Contractor shall comply with the recommendations contained in Part 6 of the U S

Department of Transportation, Federal Highway Administration Manual on Uniform

Traffic Control Devices to ensure proper warnings to motorists and adequate traffic control. Traffic control signage should be installed in accordance with Colorado, Wyoming, and Nebraska Department of Transportation M&S Standards and Colorado

Supplement to Manual of Uniform Traffic Control Devices. All signs, warning lights, barricades, and other traffic control devices shall be provided by the Contractor. The

Contractor shall maintain the normal traffic egress to and from the installation during construction at all times. If traffic flow on any roadway is to be modified for any reason, the Contractor must notify the Contracting Officer, the Fire Department, and Security

Forces by submitting a traffic coordination plan for approval to the Contracting Officer ten (10) working days prior to commencing with construction activities. The schedule and phasing of roadway lane closure will be discussed in a pre-construction meeting.

1.12 SANITARY PROVISIONS

1.12.1 Use of government facilities may not be allowed. The Contractor shall utilize only those rest rooms designated for his use, provided such usage does not conflict with usage by installation personnel and that such usage does not result in unsanitary conditions or damage to the rest room. Should usage by the Contractor result in unsatisfactory conditions, the Contracting Officer may restrict or prohibit further usage by the

Contractor. In no instance, shall paint or other construction materials be disposed of in the rest room, nor shall fixtures be utilized for cleaning tools or construction equipment.

1.12.1.1 Temporary Sanitary Provisions

a. The Government, at its discretion, may direct the Contractor to provide temporary toilets for the contractor’s use. When the Contractor provides their own temporary toilets, they shall ensure that they satisfy state and local health requirements for the use of construction personnel. Location, type, proposed maintenance, etc., shall be approved by the Contracting Officer prior to placing toilets. Temporary toilets shall be promptly removed at the completion of construction. All costs incurred in connection with the temporary toilets shall be borne by the Contractor.

1.13 TOBACCO

1.13.1 The Contractor shall limit smoking and use of tobacco to authorized areas only. Tobacco use shall be in accordance with applicable installation and DoD policy.

1.14 ACRONYMS:

1.14.1 AF Air Force

01 00 00-11 03/24/09

1.14.2 AFI Air Force Instruction

1.14.3 CO Contracting Officer

1.14.4 COR Contracting Officers’ Representative

1.14.5 DoD Department of Defense

1.14.6 QCO Quality Control Officer

1.14.7 SOW Statement of Work

1.14.8 TO Task Order

PART 2 PRODUCTS – Not Used

PART 3 EXECUTION – Not Used

END OF SECTION 01 00 00