FINANCIAL ASSISTANCE
FUNDING OPPORTUNITY ANNOUNCEMENT (FOA)
U. S. Department of Energy
Idaho Operations Office
Silicon-Carbide Ceramic Matrix Composite
Cladding for Nuclear Fuels
Funding Opportunity Number: DE-FOA-0002308
Announcement Type: Initial
CFDA Number: 81.121
FOA Issue Date: 28 July 2020
Amendment 001 Issue Date: 14 September 2020
Letter of Intent Due Date: 28 August 2020
Application Due Date: 22 October 2020
Summary of Amendment Changes:
Amendment 001: Changes the application due date from 08 October 2020 to 22 October 2020.
Registration Requirements
There are several one-time actions an applicant must complete in order to submit an application in response to this funding opportunity announcement (FOA) (e.g., obtain a Dun and Bradstreet Data Universal Numbering System (DUNS) number, register with the System for Award Management (SAM)). Applicants, who must obtain a DUNS number and/or who are not registered with SAM, should allow at least 30 days to complete these requirements; therefore, the process should be started as soon as possible.
Note: There a few requirements each applicant must meet before submitting an application package to the U.S. Department of Energy (DOE):
• Applicants must obtain a DUNS number. DUNS website: https://www.dnb.com/duns-number/get-a-duns.html/
• Applicants must register with the SAM. SAM website: http://www.sam.gov. If an applicant had an active registration in the Central Contractor Registration (CCR) system, then the applicant should have an active registration in SAM. More information about SAM registration for applicants can be found at:
https://www.sam.gov/SAM/pages/public/loginFAQ.jsf.
• Applicants must disclose foreign government ownership interests. This disclosure shall include foreign government ownership at any level in the corporate structure. Applicants with no foreign (non-U.S.) government ownership at any level in the corporate structure shall provide a signed statement of no foreign government ownership.
FOA Questions
Prospective offerors are requested to submit written questions concerning the solicitation via the applicant’s FedConnect account (www.fedconnect.net). Since application packages are due within 72 days of FOA issuance, all proposal questions are due no later than 57 days from date of FOA issuance. DOE will furnish responses to all questions from interested Offerors via The offerors FedConnect account and posted through the FedConnect portal within a few days after question submittal. Offerors are encouraged to periodically check their FedConnect account to ascertain the status of any answers to questions. No questions will be answered by phone. Questions must clearly specify the FOA areas (section, page, etc.) to which they refer.
Any changes to this solicitation, including those resulting from submitted questions, will be incorporated into the FOA by written amendment to the solicitation to be applicable.
Application Preparation and Submission
Instructions are provided in Section IV of this FOA.
https://www.dnb.com/duns-number/get-a-duns.html/ https://www.dnb.com/duns-number/get-a-duns.html/ http://www.sam.gov/ http://www.fedconnect.net/
Review of Risk Posed and Responsibility Determination
Applicants selected for negotiation will be subject to a review of risk posed and responsibility determination in accordance with 2 CFR Part 200.205 and DOE’s Guide to Financial Assistance located at: https://www.energy.gov/management/downloads/department-energy-guide-financial-assistance.
This process may involve a review of the applicant’s and sub-recipient’s business management systems (i.e., accounting, financial, procurement, property, etc.) and financial statements. DOE may request other information to support this review and determination based on the amount of previous experience the applicant and sub-recipient have in successfully performing other federal awards.
Section I - FUNDING OPPORTUNITY DESCRIPTION
DESCRIPTION
The DOE Office of Nuclear Energy (NE) sponsors a program, called the Accident Tolerant Fuel (ATF) Program, focused on supporting commercialization activities in the United States to enhance the accident tolerance of light water reactor (LWR) fuel in severe accident situations. A goal of the ATF Program is to assist U.S. fuel vendors in initiating commercial implementation of advanced LWR fuel concepts, such as the Coated Cladding Concept, by the mid-2020-time frame. The scope of the overall ATF Program also includes the pursuit of concepts with a longer-term time horizon, such as in the 2030 and beyond time frame. The U.S. fuel vendors, along with their sub-recipients, are working with DOE as teams under three cooperative agreements. DOE- NE is issuing this FOA under the ATF Program to comply with the FY 2020 Congressional Conference Appropriation language for accident tolerant fuels, as cited below:
“The Department [DOE] shall award funding for silicon-carbide matrix composite cladding to individual participants within the industry-led teams that have demonstrated fabrication expertise in silicon-carbide ceramic matrix composites for nuclear fuels and have the expertise to scale up quantities that could support the current fleet.”
Technical Concept Description: After the 2011 Fukushima accident, in response to Congressional guidance, DOE-NE has supported an active ATF Program supporting development and commercialization of advance LWR fuel. The goal of this ATF development effort is to have one or more LWR advanced fuel concepts in commercial implementation in the United States by 2030. Toward that end several concepts are being pursued that involve either coating on existing LWR clad material or a new non-metallic type of cladding. The silicon-carbide ceramic matrix clad concept is an example of the latter.
The operational constraint on all ATF concepts is that they fit geometrically into existing LWRs, and, in comparison with standard LWR fuel, should be able to tolerate loss of active cooling in a severe accident for a considerably longer time period, and maintain or improve fuel performance during normal operations. Because of its non-metallic nature, silicon-carbide fiber, as used in the silicon-fiber ceramic matrix concept, has a potential to tolerate higher accident transient temperatures and thereby meet desired ATF safety enhancements. However, because this cladding concept is based on a woven fiber and not cast or drawn as in metal based concepts, it has significant manufacturing development hurdles that must also be addressed, such as in the joining of end cap material with tubular body in a way that does not compromise the finished fuel pin integrity.
The objectives of this FOA is to fund a project that will enhance of the chances for this concept to be successful toward meeting the ATF Program goal. Using the funds provided by the Congressional 2020 guidance, the successful applicant to this FOA, in cooperation with an existing U.S. utility, will affect an earlier near-term irradiation of its silicon-carbide ceramic matrix concept in an existing U.S. commercial reactor than would be possible under any existing program.
Applicants are invited to provide a proposed two-year project that supports the objective of achieving an introduction of the silicon-carbide ceramic matrix composite concept in commercial U.S. LWR reactors in the 2030 timeframe. The proposed project should show how the proposed work addresses major development gaps and include early involvement of potential utility users.
Funding for the cooperative agreement(s) awarded under this FOA is subject to Congressional Appropriations. The cooperative agreement(s) will be awarded in accordance with Title 2 of the Code of Federal Regulations, Chapter II Subchapter H, Part 200 (2 CFR Part 200) and Title 2 of the Code of Federal Regulations, Chapter II Subchapter H, Part 910 (2 CFR Part 910).
Section II - AWARD INFORMATION
A. TYPE OF AWARD INSTRUMENT
DOE will award one grant under this FOA. The prime recipient for this award is for an individual participant within the industry-led teams. The industry-led teams refer to the three fuel vendor teams working with DOE under existing cooperative agreements for developing light water reactor fuel with enhanced accident tolerance. The individual participant may partner with DOE National Laboratories, universities, non-profit organizations, and for-profit organizations.
B. ESTIMATED FUNDING
Contingent upon the availability of funds, appropriated by Congress, DOE expects to make available approximately $4,200,000 of federal funding over a period of two years for a new single award under this FOA.
C. MAXIMUM AND MINIMUM AWARD SIZE
The ceiling, which is the maximum amount for an individual award made under this announcement, is $5,250,000. The ceiling includes up to $4,200,000 of government funds and the awardee’s 20% cost share requirement. In the event an applicant proposes more than a 20% cost share, the maximum amount for the award may exceed the ceiling; however, the Government’s portion shall not exceed $4,200,000 for this award. (This is subject to the cost share requirements of Section III.)
There is no floor amount, which is the minimum amount for an individual award made under this announcement.
D. EXPECTED NUMBER OF AWARDS
DOE anticipates making one award under this FOA.
E. PERIOD OF PERFORMANCE
DOE anticipates making awards for an estimated project period up to two years, with an anticipated start date of 21 January 2021. Applicants may propose project periods of less than two years. Performance beyond the award base year is contingent on an additional yearly future Congressional Appropriation, an evaluation of satisfactory progress during the base year, and DOE’s approval of the yearly continuation application.
F. TYPE OF APPLICATION
DOE will accept only new applications under this announcement. Only one award will be made to the winning applicant.
Section III - ELIGIBILITY INFORMATION
A. ELIGIBLE APPLICANTS
All U.S. entities are eligible for award in accordance with 2 CFR 910.124 - Eligibility, provided they meet the Congressionally mandated criteria of being a participant in the industry-led teams under current Accident Tolerant Fuels agreements. This financial assistance award is also a “covered program” (as defined in 2 CFR 910.124(b)) and must be accomplished in the economic interest of the United States as stated in 2 CFR 910.124. Eligible entities include, but are not limited to, teams, consortia, or other partnership arrangements consisting of companies that meet the criteria of 2 CFR 910.124 (c) (1) – (2).
In accordance with 2 CFR 910.126 (b) (1) – (2), Competition, eligibility of the prime applicant for award is restricted to for-profit entities, as defined in 2 CFR 910.350(b). Institutes of higher education; non-profits; state, local and tribal government entities; federal agencies and instrumentalities (other than DOE); foreign entities; non-profit consortia (incorporated or unincorporated); and Federally Funded Research and Development Centers (FFRDCs) are not eligible to participate as a prime applicant. This restriction does not apply for these entities to become sub-recipients, sub-awardees, vendors, or team members of the prime/lead applicant.
B. OTHER ELIGIBILITY REQUIREMENTS
FFRDC/National Laboratories:
FFRDC contractors may be proposed as a team member subject to the following guidelines:
• Authorization for non-DOE/National Nuclear Security Administration (NNSA) FFRDCs. The federal agency sponsoring the FFRDC contractor must authorize in writing the use of the FFRDC contractor on the proposed project and this authorization must be submitted with the application. The use of an FFRDC contractor must be consistent with the contractor's authority under its award and must not place the FFRDC contractor in direct competition with the private sector.
• Authorization for DOE/NNSA FFRDCs. The cognizant contracting officer for the FFRDC must authorize in writing the use of a DOE/NNSA FFRDC contractor on the proposed project and this authorization must be submitted with the application. The following wording is acceptable for this authorization.
"Authorization is granted for the [Name] Laboratory to participate in the proposed project. The work proposed for the laboratory is consistent with or complimentary to the missions of the laboratory, will not adversely impact execution of the DOE/NNSA assigned programs at the laboratory, and will not place the laboratory in direct competition with the domestic private sector."
• Value/Funding. The value of, and funding for, the FFRDC contractor portion of the work will not be included in the award amount to a successful applicant. DOE/NNSA will fund a DOE/NNSA FFRDC contractor through the DOE field work proposal system and other FFRDC contractors through an interagency agreement with the sponsoring agency.
• Cost-share. The applicant's cost-share requirement will be based on the total cost of the project, this includes the applicant's and the FFRDC contractor's portions of the effort.
• Scope of Work. The scope of work to be performed by the FFRDC contractor should not be more significant than the scope of work to be performed by the applicant.
• Responsibility. The applicant, if successful, will be the responsible authority regarding the settlement and satisfaction of all contractual and administrative issues, including but not limited to, disputes and claims arising out of any agreement between the applicant and the FFRDC contractor.
C. COST SHARING
The cost share must be at least 20% of the total allowable costs for research and development projects and must come from non-federal sources unless otherwise allowed by law. See 2 CFR part 200 and 2 CFR part 910 [DOE Financial Assistance Regulations] for the applicable cost sharing requirements. See also Part VIII.F of this FOA, 2 CFR 200.306, and 2 CFR 910.130 for specific information on cost sharing requirements.
DOE will not reimburse an applicant at a higher cost share portion in the beginning budget periods of the project with the condition that the applicant catches up its proposed cost share contribution in later budget periods. Also, applicants shall provide the minimum, or higher, if proposed, cost share amount throughout the term of the award. For each invoice submitted to DOE for payment, the awardee will be required to pay at least 20% of the total submitted invoice cost.
D. QUESTIONS REGARDING ELIGIBILITY
Questions regarding eligibility should be directed to the DOE contact identified in Section VII.B.
Section IV - APPLICATION AND SUBMISSION INFORMATION
A. CONTENT AND APPLICATION FORMS
The approved OPM application forms and application package submission instructions are available online at http://www.grants.gov. To access these materials, go to http://www.grants.gov, select “FORMS” and then select “R&R Family.”
B. LETTER OF INTENT
Applicants are required to submit a letter of intent to DOE by 28 August 2020. This letter should include the name of the applicant, the title of the project, the name of the Project Director/Principal Investigator(s), estimated project cost, and a one-page abstract. The required letters of intent will be used by DOE to organize and expedite the merit review selection process.
The letter of intent should be sent by email to: silicon-carbide-project@id.doe.gov. In the subject line type: Letter of Intent for DE-FOA-0002308.
Note: The maximum file size that can be sent through the id.doe.gov web server is 45MB. This is the largest email with all attachments that can pass through the web server. This includes any attached zip files. The server will count the compressed and un-compressed zip file sizes as part of the 45MB limit. If required, send more than one email with attachments in order to submit your application package through the web server.
DOE will not accept late submissions that resulted from technical difficulties due to exceeding the 45MB e-mail limitation.
C. APPLICATION PROCESS
DOE performs an initial eligibility review of applicant submissions to determine whether they meet the eligibility requirements of Section III of the FOA. DOE will not review or consider submissions that do not meet the eligibility requirements of Section III.
Document Format Requirements
Applicants must submit an application to be considered for funding under this FOA. All submissions must conform to the following form and content requirements, including maximum page lengths (described below), and must be submitted as specifically stated. DOE will not review or consider submissions, submitted through means other than specifically stated in the FOA, and will not review or consider any incomplete submissions.
Applications must conform to the following requirements:
• Applicants must complete all mandatory forms and any applicable optional forms (e.g., SF-LLL- Disclosure of Lobbying Activities) in accordance with the instructions on the forms and the additional instructions below.
http://www.grants.gov/ http://www.grants.gov/ mailto:silicon-carbide-project@id.doe.gov http://www.id.doe.gov/ http://www.id.doe.gov/
• Document format: Each document must be submitted in Adobe Portable Document
Format (PDF), except for spreadsheets, unless otherwise specified in this announcement.
• Spreadsheet format: All spreadsheets must be created and submitted in a Microsoft Excel file format. Do NOT lock any cells in the spreadsheet.
• Language: Each document must be written in English.
• All non-budget documentation (use templates where provided) must be prepared using standard 8.5” by 11” paper with 1” margins (top, bottom, left, right), using a font size no smaller than Times New Roman 11 point.
• Page Limit: Each submission must not exceed the specified maximum page limit, including cover page, charts, graphs, maps, and photographs, when printed using the formatting requirements set forth above and single spaced. If applicants exceed the maximum page lengths, evaluators will review only the authorized number of pages and disregard any additional pages.
• DOE will not review or consider incomplete or noncompliant applications.
• Each Application shall be limited to a single concept or technology. Unrelated concepts and technologies shall not be consolidated in a single application.
• Applications must include the documentation specified in the table below (if applicable).
Detailed guidance on the content and form of each application component follows the table.
Note: Applicants must access document formats labeled as “Form” at: http://www.grants.gov, select “FORMS” and then select “R&R Family.” Applicant create documents in Word format and then save in PDF format.
Name of Document
Format Required From
1 Conflict of Interest Acknowledgement PDF Affirmed by Lead Applicant for all Participants
2 SF 424 (R&R) (Application) Form Lead Applicant 3 Research and Related Other Project Information Form Lead Applicant 3a Project Summary/Abstract (1 page limit) PDF Lead Applicant 3b Project Narrative File (40 page limit) PDF Lead Applicant 4 Project Management Plan (20 page limit) PDF Lead Applicant 5 Resume / Vitae – Technical Expertise and
Qualifications (2 page limit each) PDF Lead Applicant and
Collaborators 6 Benefit of Collaborations (4 page limit) PDF Lead Applicant 7 Capabilities (5 page limit) PDF Lead Applicant http://www.grants.gov/
Name of Document
Format Required From
8 Research & Related Budget (total Fed + Non- Fed
Form Lead Applicant and Sub-recipients
8a R&R Subaward (Total Fed + non-Fed) Attachment Form
Lead Applicant and Sub-Recipients
9 Budget for DOE National Laboratory Contractor or FFRDC/NL (if applicable) and Letter of Authorization from Cognizant Contracting Officer
PDF National Laboratory Leads and Collaborators (Including non-funded Collaborators)
10 Budget Justification Document PDF Lead Applicant and Collaborators
11 Current and Pending Support (5-page limit) PDF Lead Applicant and Collaborators
12 Project/Performance Site Location(s) Form/PDF All sites performing work
13 SF-LLL Disclosure of Lobbying Activities (if applicable)
PDF Lead Applicant
14 Waiver Requests: Performance of Work in the United States (if applicable)
PDF Lead Applicant
15 Funding Commitment Letters from Third Parties Contributing to Cost Sharing (if applicable)
PDF Lead Applicant
16 Past Performance PDF Lead Applicant and Collaborators
17 Foreign Government Ownership Disclosure (if applicable)
PDF Lead Applicant and Collaborators
18 Certifications and Assurances See #2 below for directions obtaining this form
Lead Applicant
Detailed guidance on the content and form of each application component is listed below.
1) CONFLICT OF INTREST STATEMENT
(Required for National Laboratories, DOE and NON-DOE FFRDC Applicants and Sub- Applicants).
Conflicts of interest may exist due to previous efforts performed by the Labs or assistance provided in program direction and other mission related activities. Accordingly, for each applicant or (or sub-applicant) that is a National Laboratory or DOE and/or Non-DOE FFRDCs, identify any potential conflicts of interest, fully explain the conflict, whether you feel it is significant or not, along with your rationale, and if significant, how you will avoid, neutralize, or mitigate the potential conflict.
2) SF 424 (R&R)
This is the cover page for application for federal assistance. Complete all the required fields in accordance with the pop-up instructions on the form.
3) RESEARCH AND RELATED OTHER PROJECT INFORMATION FORM
Complete questions 1 through 6 and then attach files as described below. The files must comply with the following instructions:
a. Project Summary/Abstract
The project summary/abstract must contain a summary of the proposed activity suitable for dissemination to the public. It should be a self-contained document that identifies: the name of the applicant; the project manager(s); the project title; the objectives of the project; a description of the project, including methods to be employed; the potential impact of the project (i.e., benefits, outcomes); and major participants (for collaborative projects). This document must not include any proprietary or sensitive business information as DOE may make it available to the public. The project summary must not exceed one (1) page when printed using standard 8.5” by 11” paper with 1” margins (top, bottom, left and right) single-spaced with font no smaller than 11 point. Save this information in a file named “Summary.pdf,” and click on “Add Optional Other Attachment” to attach.
b. Project Narrative File
The project narrative must include:
1) Narrative Cover Page which must indicate:
a) The name and type of organization;
b) The FOA announcement number;
c) The project title;
d) The technical and business points of contact for the applicant, denoting the names, titles, addresses, telephone and facsimile numbers, and electronic mail addresses (see Attachment C: Point of Contact Sheet);
e) Project Manager’s name, telephone number, facsimile number, e-mail address, and organization name/unit; and
f) Names of team/partnership/consortium members and funding split.
2) Project Objectives. This section should provide a clear, concise statement of the specific objectives/aims of the proposed project and a concise description on the proposed project.
3) Merit Review Criterion and Other Selection Factors Discussion: This section should be formatted to address each of the merit review criterion and sub-criterion listed in Section V.A, as well as each Other Selection Factors. In addressing the merit review criterion and sub-criterion, applicants are encouraged to reference any correlation between the responses, provided under this item, and the responses, provided for other information requests, including Technical Concept Descriptions (item 4 below) and applicable elements of the technical description as discussed below. Applicants shall provide enough information so that reviewers will be able to evaluate the application in accordance with these merit review criteria and Other Selection Factors. DOE WILL EVALUATE
AND CONSIDER ONLY THOSE APPLICATIONS THAT ADDRESS
SEPARATELY EACH OF THE MERIT REVIEW CRITERION AND SUB-
CRITERION AND OTHER SELECTION FACTORS.
4) Relevance and Outcomes/Impacts: Should explain the relevance of the near-term project plan to the objectives of the longer-term program plan and expected outcomes and/or impacts. The justification for the proposed project should include a clear statement of the importance of the project in terms of the utility of the outcomes.
5) Roles of Participants and Key Personnel: Describe the roles and the work to be performed by each organization (including estimates of percentages of total project effort to be accomplished by each participant), business agreements between the applicant and participants, and how the various efforts will be integrated and managed. This will include identification of work to be accomplished by National Laboratories and indication of which National Laboratories will be used.
6) If applicable, Multiple Principal Investigators: The applicant, whether a single organization or team/partnership/consortium, must indicate if the project will include multiple PIs. While DOE’s preference is to have only one PI specified, this decision is solely the responsibility of the applicant; having multiple PIs specified will not affect the selection for award of applications submitted in response to this FOA.
If multiple PIs will be designated, the application must identify the Contact PI/Project Coordinator and provide a “Coordination and Management Plan” (4-page limit) that describes the organization structure of the project as it pertains to the designation of multiple PIs. This plan, at a minimum, will include:
a. process for making decisions on scientific/technical direction;
b. publications;
c. intellectual property issues;
d. communication plans;
e. procedures for resolving conflicts; and
f. PIs’ roles and administrative, technical, and scientific responsibilities for the project.
7) Facilities and Other Resources: Identify the facilities (e.g., office, laboratory, computer, testing, etc.) to be used at each performance site listed and, if appropriate, indicate capacities, pertinent capabilities, relative proximity, and extent of availability to the project. Describe only those resources that are directly applicable to the proposed work.
9) Equipment: List critical items of equipment (e.g., items involved in key test programs or important long-lead procurements) required for successful completion of this project and identify whether the item of equipment is already available or proposed for acquisition, the pertinent capabilities of each, the location of available equipment and the estimated acquisition cost of equipment proposed for acquisition.
10) Statement of Project Objectives: The project narrative must contain a single, detailed Statement of Project Objectives (SOPO) that addresses how both the near-term, short-term and project objectives will be met. The SOPO must contain a clear, concise description of all activities to be completed during project performance and follow the structure discussed below. The SOPO may be released to the public by DOE in whole or in part at any time. It is therefore required that it shall not contain proprietary or confidential business information.
Applicants shall prepare the SOPO in the following format:
TITLE OF WORK TO BE PERFORMED
(Insert the title of work to be performed. Be concise and descriptive.)
A. OBJECTIVES
Include one paragraph on the overall objective(s) of the work.
B. SCOPE OF WORK
This section should not exceed one-half page and should summarize the effort and approach to achieve the objective(s) of the work.
C. TASKS TO BE PERFORMED
Tasks, concisely written, should be provided in a logical sequence and should be divided into the project phases, as appropriate. This section should provide a brief summary of the planned approach to this project.
D. DELIVERABLES
The periodic, topical, and final reports shall be submitted in accordance with the attached Appendix A, “Federal Assistance Reporting Checklist,” and the instructions accompanying the checklist.
[Note: The Recipient shall provide a list of deliverables other than those identified on the “Federal Assistance Reporting Checklist” that will be delivered, including the expected delivery dates. These reports shall also be identified within the text of the Statement of Project Objectives.] See the following examples:
1. Task 1.1 - (Report Description)
2. Task 2.2 - (Report Description)
4) PROJECT MANAGEMENT PLAN
This plan should be formatted to include the following sections, with each section to include the information as described below:
a. Executive Summary: Provide a description of the project that includes the objective, project goals, and expected results. For purposes of the application, this information is included in the Project Narrative and should be simply copied to this document for completeness, so that the Project Management Plan is a stand-alone document.
b. Risk Management: Provide a summary description of the proposed approach to identify, analyze, and respond to perceived risks associated with the proposed project. Project risk events are uncertain future events that, if realized, impact the success of the project. As a minimum, include the initial identification of significant technical, resource, and management issues that have the potential to impede project progress and strategies to minimize impacts from those issues.
c. Milestone Log: Provide milestones for each budget period (or phase) of the project.
Each milestone should include a title and planned completion date. Milestones should be quantitative and show progress toward budget period and/or project goals.
Note: During project performance, the Recipient will report the Milestone Status as part of the required quarterly Progress Report as prescribed under the Reporting Requirements Checklist. The Milestone Status will present actual performance in comparison with Milestone Log, and include:
1) the actual status and progress of the project;
2) specific progress made toward achieving the project's milestones; and
3) any proposed changes in the project's schedule required to complete milestones.
d. Funding and Costing Profile: Provide a table (the Project Funding Profile) that shows, by budget period, the amount of government funding going to each project team member. Also provide a table (the Project Costing Profile) that projects at a minimum the monthly expenditure of government funds for the first budget period.
e. Project Timeline: Provide a timeline of the project (similar to a Gantt chart) broken down by each task and subtask, as described in the Statement of Project Objectives.
The timeline should include for each task a start and end date. The timeline should show interdependencies between tasks and include the milestones that are identified in the Milestone Log (Section C).
f. Success Criteria at Decision Points: Provide success criteria for each decision point in the project, including go/no-go decision points and the conclusions of budget periods and the entire project. The success criteria should be objective and stated in terms of specific, measurable, and repeatable data. Usually, the success criteria pertain to desirable outcomes, results, and observations from the project.
Note: As the first task in the Statement of Project Objectives, successful applicants will revise the version of the Project Management Plan that is submitted with their applications by including details from the negotiation process. This Project Management Plan will be updated by the Recipient as the project progresses, and the Recipient must use this plan to report schedule and budget variances.
5) RESUME / VITAE-TECHNICAL EXPERTISE AND QUALIFICATIONS
Applicant shall name all teaming partners by name and organization, as well as their proposed roles and responsibilities. For collaborators (including senior key person) who will contribute in a substantial, measurable way to the project (including for subrecipients and consultants), the applicant shall provide a brief vita that lists the following:
• Contact information.
• Education and Training: Provide institution, major/area, degree, and year for undergraduate, graduate, and postdoctoral training.
• Research and Professional Experience: Beginning with the current position list, in chronological order, professional/academic positions with a brief description.
• Publications: Provide a list of up to 10 publications most closely related to the proposed project. For each publication, identify the names of all authors (in the same sequence in which they appear in the publication), the article title, book or journal title, volume number, page numbers, year of publication, and website address if available electronically.
• Patents, copyrights, and software systems developed may be provided in addition to or substituted for publications.
• Synergistic Activities: List no more than five professional and scholarly activities related to the effort proposed.
Technical expertise and qualifications are to be provided for individual participants, whether the participant is receiving funding or not (including consultants or national laboratory personnel). All participants making a defined, material contribution that is critical to the success of the project must be listed on the online application. A separate resume/ vita for each individual collaborator must be to the application website.
6) BENEFIT OF COLLABERATORS
The applicant shall provide a narrative that includes an explanation of the contribution that will be made by the collaborating organizations and/or facilities to be utilized. Please indicate within this section if the application has benefit or influence on other ongoing or proposed NE R&D projects.
7) CAPABILITIES
Infrastructure Requirements: The applicant shall identify the infrastructure (e.g., facilities, equipment, instrumentation, and other resources) required to execute the proposed scope of work, including its location, availability, capabilities, and how it will be used in the project. Describe the non-labor (e.g., facilities, equipment, and instrumentation) resources that are available and accessible to the applicant and are required to execute the scope of work. Describe any unique equipment and facilities that are needed, are accessible, and will be used to execute the scope of work. Discuss the adequacy of these resources and identify any gaps and how these will be addressed.
This FOA allows the applicant to propose the purchase of any needed equipment to conduct the proposed work. If equipment purchases are proposed, describe comparable equipment, if any, already available and explain why it cannot be used.
Facilities & Other Resources: Describe the capability of the organizational resources, including subrecipient resources, available to perform the effort proposed. Identify the facilities to be used (Laboratory, Animal, Computer, Office, Clinical, and Other). If appropriate, indicate capacities, pertinent capabilities, relative proximity, and extent of availability to the project. Describe only those resources that are directly applicable to the proposed work. Describe other resources available to the project (e.g., machine shop, electronic shop) and the extent to which it would be available to the project.
Equipment Appendix: If applicable provide a list of major items or equipment already available for this project and, if appropriate, identify location and pertinent capabilities.
8) RESEARCH AND RELATED BUDGET (TOTAL FED + NONFED) FORM
The name of the form on Grants.gov is Research and Related Budget (Total Fed + Non- Fed). Complete the form in accordance with the instructions on the form (Activate Help Mode to see instructions) and the following instructions. You must complete a separate budget for each year of support requested. The form will generate a cumulative budget for the total project period. You must complete all the mandatory information on the form before the NEXT PERIOD button is activated. You may request funds under any of the categories listed as long as the item and amount are necessary to perform the proposed work, meet all the criteria for allowability under the applicable federal cost principles, and are not prohibited by the funding restrictions in this announcement.
8a) R&R SUBAWARD (Total Fed + non-Fed) ATTTACHMENT(s) FORM
Provide a separate cumulative R&R budget for each sub-recipient, other than a DOE National Laboratory or FFRDC contractors, expected to perform work estimated to be more than $250,000 or 50 percent of the total work effort (whichever is less). Use the same R&R budget (total Fed + Non-Fed) form (the same form the prime applicant uses) and e-mail the form to each subrecipient that is required to submit a separate budget.
After the Sub-recipient has e-mailed its completed budget back, attach it to one of the blocks provided on the form. Use up to 10 letters of the sub-awardee’s name as the file name.
9) BUDGET FOR DOE/NNSA FFRDC CONTRACTOR.
If a DOE/NNSA FFRDC/National Laboratory contractor is applying as a collaborator, it must provide a DOE Field Work Proposal (FWP), in accordance with the requirements in DOE Order 412.1A, Administrative (Admin) Change 1, Work Authorization System, dated May 21, 2014. Include an FFRDC budget justification, to include a breakdown of the cost categories and rationale regarding the necessity of the expenditures, as well as the basis of estimate for each of the budget cost categories (e.g. labor, travel, materials, etc.).
Note: Normally no justification is required for FFRDC rates (direct costs, indirect costs, and fee) as these are already pre-established on the FFRDC contract.
FWPs will be provided by the respective National Laboratory financial administrators.
FFRDC/National Laboratories are permitted to propose costs in accordance with their established DOE contracts (e.g., overhead, fees, etc.).
Also, include a Letter of Authorization from FFRDC’s Cognizant Contracting Officer for DOE/NNSA FFRDC/National Laboratories.
10) BUDGET JUSTIFICATION DOCUMENT
Provide the required supporting information for the following costs: equipment; domestic and foreign travel; participant/trainees; material and supplies; publication; consultant services; ADP/computer services; subaward/consortium/contractual; equipment or facility rental/user fees; alterations and renovations; and indirect cost type. Provide any other information you wish to submit to justify your budget request. Attach a single budget justification document file for the entire project period in Field L. The file automatically carries over to each budget year. Therefore, only attach one budget justification document to cover all the award budget periods.
The budget is the financial plan for the proposed project. Following selection of applications for award consideration, but prior to the award being made, DOE will perform a budget review to determine whether the proposed activities are supported by adequate resources in this plan, as well as to verify cost data, including that specific elements of the proposed budget are allowable, allocable, reasonable, and are consistently treated in accordance with generally accepted accounting principles and applicable cost principles. Both the applicant’s budget, as well as all sub-recipient’s budgets (over $250,000), will be reviewed from both a technical and cost perspective.
This evaluation will provide a comparison between the budget and the project narrative. Sub-recipient budget justifications must also be submitted for sub-recipient proposed budgets over $250,000.
DOE will not conduct a budget review of sub-contractor costs. However, prime award recipients will be required to explain how they determined sub-contractor costs to be fair and reasonable. The technical review will also include reviewing sub-contractor proposals and scope-of-works to determine if the proposed scope to be performed by the sub-contractor supports the award’s overall project scope. All award amounts for sub-contracts will have a technical review of the proposed scope of work. Please ensure the scope-of-work to be performed by sub-contractors is discussed in the project narrative.
In order to permit DOE to conduct budget reviews, and to ensure that the issuance of the award will not be delayed, the applicant must provide a budget justification;
including supporting information. Provide the following for supporting information for the budget justification:
1) General
a) Applicant assessment of how the total project cost is reasonable for the effort.
b) Applicant assurance that all costs proposed are:
In accordance with any limitations, exclusions, or special conditions set forth in the
FOA;
i) In accordance with generally accepted accounting and applicable costs principles; and
ii) Allocable and allowable.
c) Specify whether your proposed indirect rates have been audited and approved;
include a copy of the audit or information on where the audit can be obtained by
DOE.
d) If the applicant is in a partnership or consortium, describe the relationships among each member and specify how this is included in the budget.
2) Personnel
a) Identify individuals or positions, describe the different levels of personnel required
(experience/skill/education, etc.), and state time commitment percentages for individuals and/or positions working on the forthcoming DOE award.
b) State rates/compensation to be paid to individuals or positions. In the budget justification document explain how each labor rate(s) are established. Also explain how the labor rates were determined to be fair and reasonable.
3) Other Direct Costs
a. Travel: If travel is proposed, provide the following data on a Microsoft Excel spreadsheet:
i. Identify the proposed trips; specify the purpose of the trip, as well as the number of people traveling on each trip, the number of days per trip, and an explanation of why the specified number of travelers is required for each trip.
ii. Specify whether the travel costs proposed are consistent with the applicant’s established travel policy; include a copy of the relevant portions of the travel policy or specify where DOE can access the travel policy.
iii. Estimated airline cost and an explanation on how airline ticket cost was estimated for each trip; if business or first-class airfares are included, provide a complete justification for the additional cost.
iv. Identify city pairs, to include cities leaving from and destination cities.
v. Federal travel regulation daily approved per diem rates for each destination city
(travel day costs can’t be higher than 75% of the destination city per diem rate).
vi. Federal travel regulation daily incidental rates for each destination city.
vii. Federal travel regulation maximum hotel rates for each destination city.
viii. If applicable, estimated car rental costs, estimated car fuel costs for each trip, estimated parking fees or other costs such as tolls.
ix. If applicable, estimated train, taxi, or other transportation costs.
b) Equipment: For proposed equipment, provide the following:
i. Explain the need for the equipment and clearly indicate the unit cost for each item to be purchased; and
ii. Explain how the cost estimates for equipment purchases are established and how the cost estimates were determined to be fair and reasonable.
c) Other direct costs: If any other direct costs are proposed, identify such costs and provide an explanation/justification for each cost, such as what is required in paragraphs 3a and 3b above.
d) Sub-recipients: See section IV number 5 above for a discussion of sub-recipient budget justifications.
e) Sub-contractors: Describe the goods or services to be acquired and justify how the costs were determined fair and reasonable in accordance with the awardee’s 2 CFR 200 Procurement Standards. Prime awardees must have a DOE approved procurement standard as outlined in 2CFR.200.317 thru 200.326. If the prime awardee does not possess an approved procurement standards document at time of award selection, the prime award recipient will be given time before the award is approved to create the procurement standard document. Award selection cannot be completed until the prime recipient’s procurement standard document is submitted to DOE (the award administrator) and then reviewed and approved by DOE.
11) CURRENT AND PENDING SUPPORT
Provide a list of all current and pending support (both federal and non-federal) for the Project Director/Project Manager (PD/PM) and senior/key persons, including sub-recipients, for ongoing projects and pending applications. For each organization providing support, show the total award amount for the entire award period (including indirect costs) and the number of person-months per year to be devoted to the project by the senior/key person. Concurrent submission of an application to other organizations for simultaneous consideration will not prejudice its review.
12) PROJECT/PERFORMANCE SITE LOCATION(S)
Indicate the primary site where the work will be performed. If a portion of the project will be performed at any other site(s), identify the site location(s) in the blocks provided.
Note: The Project/Performance Site Congressional District is entered in the format of the 2-digit state code followed by a dash and a 3-digit Congressional district code for example VA-001. Hover over this field for additional instructions.
Use the Next Site button to expand the form to add additional Project/Performance Site Locations.
13) DISCLOSURE OF LOBBYING ACTIVITIES (SF-LLL)
If applicable, complete SF-LLL. Applicability: if any funds other than Congressionally Appropriated federal funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the grant or cooperative agreement, you must complete and submit Standard Form - LLL, "Disclosure Form to Report Lobbying."
14) WAIVER REQUEST: PERFORMANCE OF WORK IN THE UNITED STTATES
All work under DOE funding agreements must be performed in the United States. This requirement does not apply to the purchase of supplies and equipment, so a waiver is not required for foreign purchases of these items. However, the Prime Recipient should make every effort to purchase supplies and equipment within the United States. There may be limited circumstances where it is in the interest of the project to perform a portion of the work outside the United States. To seek a waiver of the Performance of Work in the United States requirement, the applicant must submit an explicit waiver request in the Application. A separate waiver request must be submitted for each entity proposing performance of work outside of the United States.
Overall, a waiver request must demonstrate to the satisfaction of DOE that it would further the purposes of this FOA and is otherwise in the economic interests of the United States to perform work outside of the United States. A request to waive the Performance of Work in the United States requirement must include the following:
• The rationale for performing the work outside the U.S. (“foreign work”);
• A description of the work proposed to be performed outside the U.S.;
• An explanation as to how the foreign work is essential to the project;
• A description of the anticipated benefits to be realized by the proposed foreign work and the anticipated contributions to the US economy;
• The associated benefits to be realized and the contribution to the project from the foreign work;
• How the foreign work will benefit U.S. research, development and manufacturing, including contributions to employment in the U.S. and growth in new markets and jobs in the U.S.;
• How the foreign work will promote domestic American manufacturing of products and/or services;
• A description of the likelihood of Intellectual Property (IP) being created from the foreign work and the treatment of any such IP;
• The total estimated cost (DOE and recipient cost share) of the proposed foreign work;
• The countries in which the foreign work is proposed to be performed; and
• The name of the entity that would perform the foreign work.
DOE may require additional information before considering the waiver request.
The applicant does not have the right to appeal DOE’s decision concerning a waiver request.
15) COMMITMENT LEETTERS FORM THIRD PARTIES CONTRIBUTING TO COST
SHARE
If applicable, at the time the application is submitted it must include a letter from each third party (i.e., a party other than the organization submitting the application). The letter must state that the third party is committed to providing a specific minimum dollar amount of cost sharing. Submitting the application provides assurance that the letters of commitment have been signed.
In an appendix to the Budget Justification, the following information for each third party contribution to cost sharing must be identified: (1) the name of the organization;
(2) the proposed dollar amount to be provided; (3) the amount as a percentage of the total project cost; and (4) the proposed cost sharing – cash, services, or property; and (5) must be signed. Successful applicants must provide the signed letters of commitment.
16) PAST PERFORMANCE
Applicants must submit data on past performance that demonstrates the applicant team (not required for FFRDC/NL) has demonstrated successful experience/past performance, knowledge and understanding of the business and regulatory requirements for projects of similar size, scope and complexity in achieving project technical success within budget and on time with no significant safety and quality issues.
17) FOREIGN GOVERNMENT OWNDERSHIP DISCLOSURE
Applicants must disclose to the DOE all foreign interest in applicant’s company or corporation, as defined in this FOA.
This is the start of the file's text. The full file is on GovTribe.