Statement of Work Purchase Request #: F4D3D90043AG02 Project Title: Repair Dormitory Bathtubs Facility #: B13320, B13321, B13322, B13323
1. The scope of work for this project includes, but is not limited to, all design, material, procurement and construction to provide a complete and usable product to the Government. The contractor shall provide all labor, materials, equipment, transportation, and supervision required to repair dormitory bathtubs in the above noted facilities and as outlined in the attached spreadsheet. All work shall be accomplished in accordance with all contract specifications, common work practices, and industry standards. The detailed statement of work is as follows:
2. Statement of Work:
a. All construction materials incorporated into this project shall be recycled, reused or green products. The proposal shall list all materials used, to include the product manufacturer’s name and model, part or other distinguishing identification and numbers. The use of recycled, reused or green product substitutes is not required where the substitute is not equal in quality or overall life cycle cost compared to its virgin equivalent. Where applicable, the proposal shall state why substitute products are not being incorporated using one of these criteria.
b. The work consists of inspecting the bathtubs noted in the attached spreadsheet, determining that the proposed work as noted in the attached spreadsheet is adequate and finally executing the repair. Repairs will range from repairing chipped porcelain, removing and restoring rusted areas, to fully resurfacing the porcelain tub as well as leveling low areas adjacent to the drain. All bathtubs shall be returned, as best as possible, to a new condition with a sealed porcelain finish with no rust visible and a smooth surface throughout.
c. The facilities involved will be occupied by dorm residents during the work. All access must be scheduled through the 30th Civil Engineer Squadron Dormitory & Furnishings Management (30 CES/CEACU). Access will be granted with a Government supplied escort to accompany the contractor during the execution of work during normal duty hours, Monday through Friday.
d. The contractor shall provide an overall schedule showing an approximate time frame to complete all work not in 60 days or less. In addition to the overall schedule, contractor shall provide a two week “look ahead” schedule, forecasting the units to be scheduled over the next two weeks and an estimate on how long each bathtub will be inoperable. This will allow 30 CES/CEACU to notify the residents of the impending work to be accomplished.
e. Note that each dorm unit, or MOD, has two bathrooms with each having a separate bathtub. The contractor shall schedule work in such a manner that at no time will both tubs in an individual MOD be under renovation or unusable at the same time.
Bldg 13320 Condition; Recommended Action
101 A/B Rust; repair & resurface 101 C/D Rust; repair & resurface 201 A/B Good; resurface only 201 C/D Good; resurface only 301 A/B Rust/Hole; ; repair & resurface 301 C/D Good; resurface only 102 A/B Good; resurface only 102 C/D Good; resurface only 202 A/B Good; resurface only 202 C/D Rust; repair & resurface 302 A/B Good; resurface only 302 C/D Good; resurface only 103 A/B Good; resurface only 103 C/D Hole; repair & resurface 203 A/B Good; resurface only 203 C/D Rust; repair & resurface 303 A/B Rust/Almost Hole; repair & resurface 303 C/D Rust; repair & resurface
Bldg 13322 Condition; Recommended Action 104 A/B Rust; repair & resurface 104 C/D Good; resurface only 204 A/B Good; resurface only 204 C/D Good; resurface only 304 A/B Good; resurface only 304 C/D Good; resurface only 105 A/B Good; resurface only 105 C/D Good; resurface only 205 A/B Good; resurface only 205 C/D Good; resurface only 305 A/B Good; resurface only 305 C/D Rust; repair & resurface
Bldg 13322 Condition; Recommended Action 106 A/B Rust; repair & resurface 106 C/D Rust/Hole; repair & resurface 206 A/B Stained; repair & resurface 206 C/D Rust; repair & resurface 306 A/B Rust; repair & resurface 306 C/D Rust/Hole; repair & resurface 107 A/B Rust; repair & resurface 107 C/D Chipped; repair & resurface 207 A/B Rust; repair & resurface 207 C/D Hole; repair & resurface 307 A/B Stained; repair & resurface 307 C/D Good; resurface only 108 A/B Good; resurface only 108 C/D Rust; repair & resurface 208 A/B Good; resurface only 208 C/D Stained; repair & resurface 308 A/B Rust; repair & resurface 308 C/D Rust; repair & resurface
Bldg 13323 Condition; Recommended Action 109 A/B Stained; repair & resurface 109 C/D Stained; repair & resurface 209 A/B Rust; repair & resurface 209 C/D Good; resurface only 309 A/B Good; resurface only 309 C/D Good; resurface only 110 A/B Rust/Chipped; repair & resurface 110 C/D Chipped; repair & resurface 210 A/B Stained; repair & resurface 210 C/D Rust; repair & resurface 310 A/B Good; resurface only 310 C/D Chipped; repair & resurface