STATEMENT OF WORK
TO
FURNISH/INSTALL ABOVEGROUND AGE
6,000 GALLON FUEL TANK
AT
BUILDING 2033 ROBINS AFB
Service Request 1325732 Service Task 3902782
24 July 2018
1. SECTION 1 – DESCRIPTION OF SERVICES.
1.1. SCOPE OF WORK.
The contractor will provide a factory assembled 6,000 gallon double-wall Above-ground Storage Tank (AST) with dispensing pump at Bldg 2033 POL complex, Robins AFB, GA. This tank will be used to dispense Jet-A aircraft fuel to refuel Aerospace Ground Equipment (AGE) only. The AST is to be located on the containment pad due west of the Bldg 2033 POL complex. The contractor shall provide all labor, equipment, parts, consumables, and transportation for the AST to Bldg 2033 POL complex. The AST is to include fuel truck delivery connection system to the tank, single dispensing pump with hose to refuel AGE, electrical service connection from Bldg 2033 panel for dispensing pump motor and other electrical components, and all other component items and services necessary to provide AST AGE fuel tank to make a complete and useable system in accordance with this Statement of Work (SOW). Contract performance period will be 120 days from NTP.
2. SECTION 2 – PRODUCT DESCRIPTION.
2.1. Quantity.
2.1.1. The contractor shall provide a single double-wall 6,000 gallon AST to receive and dispense Jet-A aircraft fuel, complete. The contractor will have fuel tank/fuel systems experience and provide certification on same in the bid package to the Contract Officer for approval.
2.2. System Specifications.
2.2.1. The AST system must be composed as specified in SOW Sections 2.2., 2.3., and 2.4..
2.2.2. The AST system and electrical connections shall comply with following standards:
Unified Facilities Criteria (UFC) 3-460-01 Design: Petroleum Fuel Facilities; MIL-STD 161H; UL- 142; NFPA 70; NFPA 77; and NFPA 780. The contractor will be knowledgeable on these standards and provide certification on same in the bid package to the Contract Officer for approval.
2.3. Equipment Specifications.
2.3.1. In compliance with UFC 3-460-01, the contractor shall provide a 6,000 gallon double-wall grounded AST, standard pipe connection system to tank for fuel delivery by R-11 USAF fuel truck, single external 120 volt dispenser pump with 20-foot hose to refuel AGE from tank, electrical service connection from Bldg 2033 panel to dispensing pump motor, and any other items to make a complete and useable system. AST tank tightness testing will be required after tank is on site and prior to filling with fuel.
2.3.2. The AST fuel filling system will be a 3-inch pipe with an aircraft 3-inch single point receptacle (Cla-Val) type at the tank end that will receive Jet-A product from USAF R-11 mobile vehicle. The AST will have a clock dial-face liquid level gauge (in feet/inches, visible to a R-11 delivery operator) and a strapping chart from tank manufacturer; and an electronic automatic tank gauge (ATG) system with local read-out at the AST. The AST fuel filling system will have a local high level alarm at the AST to alert the R-11 fill pipe operator before the AST is 90% full; and an automatic shut-off to stop fuel flow into the AST before the tank level reaches 95% full. The complete fuel filling system [the single point receptacle, liquid level gauge, electronic automatic tank gauge (ATG) system, 90% high level alarm, and 95% high level shut-off] descriptions & technical specifications and the tank strapping chart will be submitted to the Contract Officer for approval. The contractor will submit schematics and drawings of AST tank and pumping system to the Contract Officer for approval. The Government will provide Jet-A fuel on site to test high level alarm/shut-off systems prior to contract acceptance. Note: Butterfly valves are not permitted on AST systems IAW UFC 3-460-1.
2.3.3. The AST and all piping and equipment will be beige color to match existing Robins AFB POL tank color: Robins 42. The AST will have tank markings IAW MIL-STD 161H and be labeled with a standard Robins AFB fuel tank placard data (“Jet-A” over three yellow vertical bars, “NO OPEN FLAME OR IGNITION SOURCE WITHIN 50 FEET FLAMMABLE”, tank number “2033-3A”, capacity “6000 GAL”). See Attachment 3 “Robins AFB Fuel Tank Placard Standardization (Jul 2015)” for requirements data and local distributor source for equivalent placard. Tank placard size will be 2 feet X 3 feet. The AST will be protected by up to three bollards (one at each corner of pavement side, one in middle equidistant from corners) IAW UFC 3-460-01, painted yellow.
2.3.4. The AST fuel dispenser will be a commercially available dispenser pump unit, 20 GPM maximum flow rate, with a self-contained electric motor and metered pumping unit (gallons unit of measure) external to the AST, 20-foot dispensing hose, in-line hose filter capable of sediment removal to 10 mg/L or less, and emergency hose shutoff valve. The end-of-hose activation flow device handle will be similar to a diesel vehicle device handle and will be rain protected in its storage position. The complete fuel dispenser system (pump, motor, meter, hose, nozzle delivery device, and so forth) description & technical specifications will be submitted to the Contract Officer for approval.
2.3.5. The electric service line from existing Bldg 2033 electric panel to the AST (see Attachments 1 &
2) will be in underground (UG) plastic conduit, conductors with ground sized per NFPA 70 for voltage drop distance to dispenser for amperage rating of dispenser electric motor. The UG conduit distance measured at about 375 feet. The conduit run from back side of Bldg 2033 will run under the north-side boundary fence concrete grade beam footer and under the existing 30-foot wide driveway that connects the Bldg 2033 POL complex to the aircraft Ramp. The driveway can be saw-cut and concrete patched, or directional bored for conduit placement. The contractor will obtain a digging permit from 78 CES for conduit route approval and utility marking after contract award and before conduit placement.
2.4. Installation & Warranty.
2.4.1. The contractor shall be responsible for AST, equipment delivery, and placement at Bldg 2033 POL Complex at Robins AFB, GA 31088. The work site abuts an aircraft taxiway/parking ramp. The contractor will take standard precautions for contract vehicles, personnel, equipment, and materials around aircraft areas and for FOD debris from work site. The contractor will have to obtain security badges for all employees accessing the aircraft taxiway/parking ramp/containment pad area that is outside the existing Bldg 2033 POL Complex fenced area. Badged employees and their vehicles will be listed on a 78 SFS Entry Authorization List (EAL). The EAL approval document from 78 SFS/S5 will to be processed after contract award via 461 ACW/CE staff.
2.4.2. The contractor will install two, six-foot swing gates (12-foot total opening width, minimum) on the existing fence that crosses the existing 30-foot concrete driveway connecting the containment pad to the southwest vehicle pavement entrance to the Bldg 2033 POL Complex at Beale Drive parking lot (see Atch 1). The two swing gates may be longer at contractor option to enable gate posts to be placed outside the concrete driveway/curb surface into the dirt. This gate access may minimize but not eliminate contractor security badge requirements for Taxiway-L access for AST site work at the containment pad/Bldg 2033 area. In addition, the contractor will have access to the existing 30-foot sliding gate/driveway to Taxiway-L on the north side of Bldg 2033 POL Complex (see Atch 1; and Atch 2, photo 6). Contractor use of this locked sliding gate will be controlled by 78 LRS/LGRF staff and 78 SFS/S5 security forces.
2.4.3. The government will provide access from Beale Drive to Bldg 2033 for the contractor to connect the AST UG electric service to the existing 120/208 volt electric panel. Contractor will furnish appropriate size circuit breaker in the panel to service the AST electric devices.
2.4.4. The installation requires contractor to run electric line in underground conduit to AST location site (see Atchs 1 & 2), crossing under the perimeter fence & the fence concrete surface beam-footer, and crossing under the concrete driveway between Bldg 2033 POL Complex and the aircraft ramp.
The contractor shall be responsible for all material and labor to connect AST to electric panel, and obtaining the digging permit for same from 78 CES after contract award. Ramp access outside the fenced area of Bldg 2033 POL Complex will be via EAL and 78 SFS/S5 daily approvals via phone coordination.
2.4.5. The contractor will provide an exterior dispensing pump on the AST for fuel delivery to Gov AGE assets.
2.4.6. The contractor shall deliver the factory assembled AST to the site and install all other necessary equipment on-site at Bldg 2033 within the installation area. The installation areas will be specified during initial walkthrough. Bldg 2033 will be accessed via the 78 LRS/LGRF occupant users.
2.4.7. The contractor shall provide a factory trained employee to supervise all work and provide labor as required, including airfare, local transportation, meals, and all other accommodations to make the AGE AST fully operational.
2.4.8. After equipment installation, the contractor shall provide system start-up, testing, and appropriate adjustments to make the AST & equipment fully operational. In coordination with the contractor site supervisor, the 116 LRS/LGRF will provide Jet-A fuel to the tank at the tank delivery connection point via R-11 USAF fuel truck.
2.4.9. After equipment installation, the contractor shall provide operator training of tank pump delivery system, equipment operation, tuning, troubleshooting, preventative maintenance awareness, and equipment servicing to increase product life.
2.4.10. The contractor shall test all equipment on-site at Robins AFB to ensure compliance with Sections 2.2., 2.3., and 2.4. of this SOW and provide certification documents to CO on same.
2.4.11. The contractor shall provide a full warranty on all equipment and workmanship for a period of no less than one (1) year from project acceptance date. All warranty issues and repairs must be handled on-site at Robins AFB.
2.5. Operating Hours. All work shall be performed during normal operating hours, 0700-1700 Monday thru Friday, except on federal holidays when the facility shall be closed. If needed, the contractor may request other work hours through the project engineer in 461 ACW/CE.
2.6. Period of Performance. All work on this contract shall be completed within 120 calendar days after contract award date.
2.7. Contractor Personnel. The contractor shall provide a point of contact (POC) and an alternate who shall act for the Contractor when the manager is absent and shall designate these individuals in writing to the Contracting Officer (CO) within two (2) working days after contract award. The Contractor shall provide telephone numbers of the Contract Manager and alternate, such that they may be contacted at any time. The Contract Manager shall have full authority to act for the Contractor on all matters relating to operation of this contract on Robins Air Force Base. Contractor’s employees shall present a neat, clean, safe, and professional work site, and appropriate dress and appearance at all times.
2.8. Re-Performance of Unacceptable Services. The contractor shall have one business day to re-perform unacceptable services, after notification by the CO that services are unacceptable. If unable to re-perform unacceptable services in one day, contractor will submit response plan to CO for determination of acceptable time. CO response to re-perform plan will be final.
2.9. Quality Control Program. The contractor is responsible for the quality of services provided under the terms of this contract, including those provided by subcontractors. To ensure the requirements of this contract are met, the contractor shall implement an effective and economical quality control program to identify, prevent, and ensure non-recurrence of defective services.
2.10. Safety Requirements. The contractor shall comply with all safety practices posted in the assigned work area and the attached Appendix A. The contractor is required to comply with the current revision of the codes, instructions, regulations, and standards specified in Appendix A. The work site is a no smoking area.
2.11. Housekeeping. The contractor shall keep work areas clean and neat in accordance with Industry Standards, Occupational Safety and Health Administration (OSHA), fire and safety standards, and this SOW.
2.12. Tool Control & Accountability. While performing contract services in or around Ramp areas, the contractor shall comply with Tool and Equipment Management procedures as directed. All tools brought into 461 ACW areas, including Ramp areas, shall be secured in a container or bag to avoid introduction of foreign objects and debris (FOD).
2.13. Foreign Object Damage (FOD) & Dropped Object Prevention (DOP). Contractor personnel who, in performance of their assigned duties on this contract, work in or travel through areas near operational and production aircraft, engines, munitions, support equipment, Aerospace Ground Equipment (AGE), trainers and the contractor personnel operating vehicles and equipment on flight lines, runways, taxiways, parking ramps, and in aircraft hangers and maintenance areas are required all posted FOD/DOP training and to comply with AFI 21-101.
2.14. Pass & ID Requirements. The contractor personnel must have a pass to access Robins AFB and coordinate with the facility to receive access to work in the Bldg 2033 contract area. All passes are obtained from 78 SFS Pass and ID office at Watson Blvd gate at Robins AFB. To obtain a pass, the contractor must be sponsored by a base employee and have a valid driver’s license, current vehicle registration, and proof of insurance. The contractor may contact Pass & ID at Bldg 767, phone
(478) 327-5666 for more information.
3. SECTION 3 – GOVERNMENT FURNISHED PROPERTY & SERVICES.
3.1. Government Furnished Property (GFP) is not applicable to the performance of this contract.
3.2. Government Furnished Services are applicable during the performance of this contract.
3.2.1. Security Forces. The Government will provide general on-base security force service. The telephone numbers for security forces are 911 for emergencies and (478) 926-2187 for non-emergency calls.
3.2.2. Fire & Emergency Services. The Government will provide general on-base fire protection services. The Contractor shall comply with fire prevention rules and regulations enforced by the Robins AFB Fire Prevention. Call 911 for emergencies. For non-emergency calls to dispatch call (478) 926- 2187.
3.2.3. Emergency Medical Service. The Government will provide 24 hour on-base state certified paramedic level emergency response and patient transport services for Contractor personnel who are injured or become seriously ill while on Robins Air Force Base. The telephone number is 911 for emergencies.
Note: Calling 911 from a cell phone will be received by off-base emergency 911 system, causing a delay in response time by Robins AFB emergency personnel. To expedite response time, request off-base 911 operator transfer your call to the Robins AFB 911 system. When possible use a base telephone to receive on-base help.
3.2.4. Utilities. The Government will provide utility services only at the nearest existing utility source.
These utilities include electricity, water, and sewer for the sole purpose of accomplishing this contract.
If the contractor requires additional utility services, it shall be the contractor’s responsibility to provide.
Contractor shall use due care and diligence in efforts to conserve utilities to reduce utility costs.
3.2.5. Custodial Services. The Government will provide custodial services limited to the extent provided in the Base Custodial Contract(s) for the Government provided facilities.
3.2.6. Workspace. The Government will provide access to the equipment and adequate workspace at the POL area.
3.3. Environmental Protection & Safety. The contractor shall be knowledgeable of and comply with all applicable federal, state and local laws, regulations, instructions and requirements regarding environmental protection and occupational safety and health. The contractor shall comply with any laws, instructions or regulation changes during the term of this contract.
3.3.1. Material Safety Data Sheet/Safety Data Sheet (MSDS/SDS). The contractor shall not transport or use any chemical, material, or substance used in the performance of this contract on Robins AFB before written coordination and approval through 116 ACW HAZMAT Control. The contractor shall submit all material safety data sheets (MSDS) and safety data sheets (SDS). The contractor shall maintain copies of manufacturer MSDSs/SDSs for all chemicals and MSDSs/SDSs shall be readily accessible at all times by contractor personnel as well as government employees.
3.3.2. Hazardous Material (HAZMAT). The contractor shall not store chemicals or hazardous material (HAZMAT) on Robins AFB.
3.3.3. Hazardous Waste. The contractor shall dispose of contaminated solid waste, spent or processed chemical solutions, used rags and hazardous waste in government furnished waste containers located at Bldg 2080, 116 ACW HAZMAT control office.
3.3.4. Discharges. Any discharges into Robins industrial waste treatment plant (IWTP) or sanitary sewer must be approved and completed IAW Robins AFB Industrial Waste Water Discharge procedure as instructed by 78 ABW/CE, Natural Infrastructure Management (Environmental Compliance).
3.3.5. Off-Site Discharges. For discharges outside of Robins AFB that may contain pollutants resulting from any contracted service, the contractor shall ensure that the waste water discharges to a state or federal permitted treatment facility, such as a municipal Publicly Owned Treatment Works (POTW). The contractor shall provide a letter ten (10) calendar days after contract award date to 461 ACW/CE, (478) 201-1408, from the POTW that states the POTW is permitted for all pollutants that the contractor may discharge during the contracted service.
3.3.6. Spills. Upon occurrence of any spill that could enter the stormwater system or cause any harmful environment effects, the contractor shall immediately call 911 to report the incident. When possible, the contractor shall use a base telephone to receive help from Robins AFB 911. If using a cell phone, the contractor shall request Robins AFB 911. The contractor shall immediately report all environmental violations to the contracting officer representative (COR) and unit environmental coordinator (UEC). The contractor shall provide five (5) copies of a typed or written spill report about the incident within four (4) hours as follows:
One (1) copy to the contracting officer (CO), two (2) copies to the COR, one (1) copy for UEC, and a copy for record. The format of the report is up to the contractor, but the report shall contain the following information:
1.) Name and contact number of person reporting the spill 2.) Date and time of incident 3.) Location and source of spill 4.) Substance or pollutant spilled 5.) Amount spilled and rate of discharge 6.) Any damages or injuries involved 7.) Extent of area impacted 8.) Potential hazards 9.) Actions taken 10.) Organizations contacted 11.) Remarks Section - addresses the cause of the spill (e.g. human error, equipment, etc.)
and whether 911 was called and which agencies responded
Within 24 hours after any spill the COR and/or the UEC (461 ACW/CE) will provide the contractor’s spill report data on a Robins AFB Spill Notification Form to 78 CEG/CEIE, attention Mr. Samuel K. Freeman, 478-926-5698.
3.4. Security Requirements.
3.4.1. All personnel employed by the contractor in the performance of this contract, or any representative of the contractor entering the governmental installation, shall abide by all security instructions and directives of Robins Air Force Base. Employees are responsible for safeguarding any government property provided for contractor use.
3.4.2. The contractor and any subcontractors, as applicable, shall not employ persons for work on this contract if such employee is identified as a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population; nor shall the contractor or subcontractor employ persons under this contract who have an outstanding criminal warrant as identified during the Criminal Background Investigation (CBI).
3.4.3. The contractor shall ensure their employees and those of their subcontracts have the proper credentials allowing them to work in the United States. Employees and subcontractors later found to be undocumented or illegal aliens will be reported to the proper authorities.
3.4.4. The contractor shall not be entitled to any compensation for delays or expenses associated with complying with the provisions of this clause. Furthermore, nothing in this clause shall excuse the contractor from proceeding with the contract as required.
3.4.5. Contact the Government Project Manager to obtain badging for access to Robins AFB.
Employee names and social security numbers will be required. Contractor needs no access to classified data nor clearance to perform, other than validating their personal data on the Entry Authorization List.
The restricted area on the aircraft ramp is due to aircraft security.
3.5. Quality Assurance. The government will evaluate the contractor’s performance under this contract. The contract monitor (CM) is a representative of the Contracting Officer (CO) and will participate in the administration of this contract. Any matters concerning a change in scope, prices, terms, or conditions of this contract shall be referred to the CO. The services to be performed by the contractor during the period of this contract shall at all times be subject to review by the CO & CM.
3.6. Emergency Evacuation Procedures. Contractor employees shall follow the direction of Government employees in regards to emergency evacuation procedures, i.e., fire, tornado, bomb threats, etc. It is the responsibility of the contractor to provide guidance and establish procedures for responding to an emergency for their employees. It is the responsibility of the contractor to account for their employees following an emergency situation.
3.7. Site Location Map, Work Area Photos, & Other Attachments. See APPENDIX B.
APPENDIX A
INDUSTRIAL SAFETY REQUIREMENTS
SECTION 1 - GENERAL REQUIREMENTS
A. Safety Program Requirements. The Contractor shall implement a safety program that ensures protection of Government personnel and property. The program shall consist of, as a minimum:
1. Mishap notification/reporting as defined in Section 1.B. below.
2. A Safety Program that addresses, as a minimum, the subjects listed in Safety Program
Elements, Section 2 and to be used during performance of the work described in the contract.
B. Mishap Notification.
1. The Contractor shall notify the procuring Safety Office or a designated Government Representative (GR) within one (1) hour of all mishaps or incidents. A written report of the mishap/incident shall be sent within three calendar days to the GR, who shall forward it to the Procuring Safety Office. For information not available at the time of initial written report, the Contractor shall provide the remaining information no later than 20 calendar days after the mishap, unless extended by the Safety Office.
2. Mishap notifications shall contain, as a minimum, the following information:
a. Contract, Contract Number, Name and Title of Person(s) Reporting
b. Date, Time and exact location of accident/incident
c. Brief Narrative of accident/incident (Events leading to accident/incident)
d. Cause of accident/incident, if known
e. Estimated cost of accident/incident (material and labor to repair/replace)
f. Nomenclature of equipment and personnel involved in accident/incident
g. Corrective actions (taken or proposed)
h. Other pertinent information
3. If requested by the designated government representative, the Contractor shall immediately secure the mishap scene/damaged property and impound pertinent maintenance and training records, until released by the Procuring Safety Office.
C. The safety provisions of this contract, shall apply to any subcontracts/subcontractors.
Safety requirements listed herein that do not concern Contractor’s operations or services shall be considered self-deleting as mutually agreed by the Contractor and the procuring office.
SECTION 2 - SAFETY PROGRAM ELEMENTS
The Contractor’s Safety Program shall clearly define procedures, personnel qualifications, facilities and required equipment necessary to fulfill the following elements.
Element/Requirement Referenced Benchmark
Mishap Notification/Reporting
Housekeeping
Material Handling Equipment (MHE)
Handling & Storage of Flammable/Combustible Liquid
Vehicle Operations
Tool Control
Foreign Object Damage (FOD)
Tobacco Use in the Air Force
AFI 91-204
AFI 91-203
AFI 91-207
IAW facility rqmts
IAW local policies/procedures
AFI 40-102
APPENDIX B
ATTACHMENTS
ATTACHMENT 1: Bldg 2033 POL Complex Aerial Site Location Map [one page]
ATTACHMENT 2: Bldg 2033 Work Area Photos [two pages]
ATTACHMENT 3: Robins AFB Fuel Tank Placard Standardization (Jul 2015) [two pages]
ATTACHMENT 1
ATTACHMENT 2
Bldg 2033 Work Area Photos
1. B2033 South Side Wall, window view of electric panels.
2. B2033 Inside, electric panels on east wall for electric source to AST.
3. B2033 Inside, 120/208V panel, space for adding circuit breaker for electric feed to AST.
4. B2033 East Side Wall, area for conduit penetration.
5. B2033 North Side Exterior Area, area for UG conduit going to AST. The digging permit from 78
CES will determine exact location for UG conduit to avoid other existing UG structures/piping.
6. B2033 North Side Exterior Area, fence gate on right with driveway to taxiway, area for UG conduit going to AST. Concrete driveway is 30-feet wide, unknown thickness.
ATTACHMENT 2
Bldg 2033 Work Area Photos
7. B2033 Wide View, showing OWS & containment pad area for AST (near light pole), and area for UG conduit feed to AST. Storm drain and UG manhole seen just north of OWS. The UG electric conduit distance from B2033 to AST location area measures about 375 feet.
8. B2033 OWS & UG manhole, area for UG electric conduit feed to AST.
9. Same as Photo 8, looking west, with containment pad in background.
10. Containment Pad Northeast Corner, white line for taxiway clearance & drain to OWS.
ATTACHMENT 3
ROBINS AFB Fuel Tank Placard Standardization (Jul 2015)
New placards for fuel storage tanks at Robins AFB shall conform to the following (or equivalent):
1. Sign placards for fuel tanks need to have the following properties:
a. Scratch Resistance; UV protection from damage and fading; Graffiti Resistance (cleans with 80% alcohol and a rag); Chemical Resistance (test data attached); Water and Mold Resistance
b. Specialized polymer coating cured and bonded to the sign substrate using UV light. The coating covers the entire sign from edge to edge locking in and protecting the ink and the substrate against environmental damage.
2. For fuel identification labels: line width, black box, and letter height depends on the size of the tank (Ref. MIL-STD-161H, Pg 6, Table 2)
a. Product Group Bands will be yellow
b. Letters will be white
c. A black box background for letters will extend at least ¾ inches beyond lettering
d. If tank capacity is below 420,000 gal:
i. Width of bands= 3”
ii. Space between bands= 3”
iii. Length of bands= 33”
iv. Letter Height= 6”
v. The above can be adjusted to the size of the sign. Currently on the 2’ x 3’ and the 2’ x 2’, the Width of the bands=13/16”
vi. Space between band=13/16”
vii. Length of bands=9 ¾”
viii. Letter Height=1 ¾”
e. If tank capacity is above 420,000 gal:
i. Width of bands= 4”
ii. Space between bands= 3”
iii. Length of bands= 33”
iv. Letter Height= 12”
3. If the tank is in a fenced enclosure or building, a sign must be posted on the fence as follows: NO OPEN FLAME OR IGNITION SOURCE BEYOND THIS POINT (Ref. T.O. 37-1-1, Pg 2-1, 2.2. a)
4. NO OPEN FLAME OR IGNITION SOURCE WITHIN 50 FEET (Ref. T.O. 37-1-1, Pg 2-1, 2.2. b)
5. Fire protection labels will use black lettering with a white background
6. Center fire protection label directly under fuels identification label
7. Tank ID is to be placed in the upper right corner
8. Tank capacity is to be placed in the lower right corner
9. Local distributor for equivalent placards is: ADA Supplies Inc., Bonaire GA, 478-329-8896, or http://www.adasupplies.us/ http://www.adasupplies.us/
| 1. SECTION 1 – DESCRIPTION OF SERVICES. |
| 2. SECTION 2 – PRODUCT DESCRIPTION. |
| 2.2. System Specifications. |
| 2.3. Equipment Specifications. |
| 2.4. Installation & Warranty. |
| 3. SECTION 3 – GOVERNMENT FURNISHED PROPERTY & SERVICES. |
| 3.4. Security Requirements. |
| APPENDIX A |
| SECTION 1 - GENERAL REQUIREMENTS |
| SECTION 2 - SAFETY PROGRAM ELEMENTS |
| ATTACHMENT 3 |
| v. The above can be adjusted to the size of the sign. Currently on the 2’ x 3’ and the 2’ x 2’, the Width of the bands=13/16” |