PERFORMANCE WORK STATEMENT_UPS_8 Apr 2026.docx

DOCX document 29 KB Posted

Attached to
Replace and Installation of New Uninterruptible Power Supply (UPS) for 51 FW/CS at Osan AB
Solicitation number
F3J0CP6126A001
Issued by

About this file

This is a Performance Work Statement (PWS) for the replacement and installation of an Uninterruptible Power Supply (UPS) system at Building 946, Osan Air Base, Republic of Korea. The contractor shall remove the existing EATON 9395 UPS (installed November 2012 and at end-of-life), procure a replacement UPS unit, perform any necessary building or power modifications, install the new system, and conduct full system testing and integration. The new UPS must maintain the current power demand and safeguard requirements, provide uninterrupted power to information technology and security systems during the 3-10 second interval before the facility's backup generator activates, utilize the existing 120 battery units (C&D Technologies 12V 109AH VRLA), and fit within the existing room space. The facility houses the 7th Air Force A8/9 (1st and 2nd floors) and the 694th Intelligence, Reconnaissance, Surveillance Group (3rd floor), with the 7 AF/A8/9 facility manager serving as the contracting officer representative.

Key contractor responsibilities include conducting a site survey to assess feasibility and identify required modifications, procuring UPS parts and services with an estimated timeline, safely removing and disposing of the current UPS while maintaining base commercial power, installing the replacement UPS with all necessary labor and materials, and testing and validating new UPS operation. Work shall be performed Monday through Friday, 0800-1600 Korea Standard Time, excluding holidays. Deliverables include the installed and integrated UPS system, operating and maintenance manuals with technical data sheets and wiring diagrams, service tickets documenting all work performed, operator training for the facility manager, and a one-year warranty on all materials and workmanship. The contractor must have unescorted access to Osan Air Base and will be escorted by facility management when accessing restricted floors.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

PERFORMANCE WORK STATEMENT (PWS)

Replace Uninterruptible Power Supply (UPS)

Building 946, 7 AF/A8A9, Osan AB ROK

POC: Mr. David Signorini (Building 946 Facility Manger) CAO: 8 April 2026

Table of Contents

Contents

1. General Information

2. Detailed Contractor Tasks

3. Logistics and Security

4. Deliverables

Part 1

General Information

1. GENERAL: The work to be performed by the contractor is to remove and dispose of the current Uninterruptible Power Supply (UPS) and replace it with a new UPS that will use existing UPS batteries and room space. Such contract service providers shall be accountable solely to the Contractor who, in turn, is responsible to the Government.

1.1. Description of Services/Introduction: The contractor shall have a service organization, trained and experienced in removing the current UPS, making required building or power modifications prior to installation of new UPS, possibly removing, bypassing, or modifying two transformers within the room, procure parts for new UPS, install and test the new UPS.

1.2. Current Uninterpretable Power Supply (Current UPS):

1.2.1. The current UPS model is EATON 9395 (“current UPS”), installed in November 2012 and is at end of life and showing faults, requiring a replacement to prevent outages affecting mission requirements.

1.2.2. The current UPS is located at Building 946 (“facility”) at Osan Air Base, South Korea within the Pyeongtaek City limits. The building is frequently mentioned as Pacific Air Simulation Center (PASC) building.

1.2.3. The batteries currently in and use and to be used with the new UPS are 120x C&D Technologies 12V 109AH VRLA (Part Number UPS12-400MRX)

1.2.4. The current UPS is connected to the facility’s power generator that will provide

1.2.5. The unit tenants of the facility are 7th Air Force A8/9 occupying the 1st and 2nd floor and 694th Intelligence, Reconnaissance, Surveillance Group occupying the 3rd floor.

1.2.6. The 7 AF/A8/9 facility manager (“facility manager”) is represent the tenants listed above and will be the U.S. government lead and contracting officer representative (COR) for this effort.

1.3. New Uninterruptable Power Supply Requirements (New UPS):

1.3.1. The new UPS shall at least support the current power demand and safeguard requirements already provided by the current UPS. This includes no loss of power to connected information technology and security systems while on battery power and integrated with the facility power generator.

1.3.2. The facility’s power generator typically takes 3 – 10 seconds to provide power to the facility in the event commercial power is lost. During this time, the new UPS must provide uninterrupted power to these systems. Once power generator provides power, the new UPS batteries are no longer used.

1.3.3. The new UPS shall use the existing batteries that are used by the current UPS.

1.3.4. The new UPS shall use the existing room and space that houses the current UPS.

1.4. Objectives: Replace current UPS system to ensure continuous 24/7 power for critical infrastructure at a cost that is mutually agreeable to the facility manager and contractor.

1.5. Scope. Effort shall occur within Building 946 and 20 meters from the surrounding area. Removal and disposal of current UPS hardware, procurement of new UPS unit, installation, and system testing. Annual and follow-on maintenance contract or agreement will be managed by a separate contract.

Part 2

Detailed Contractor Tasks

2.1. All tasks listed below shall be coordinated in English with the building’s facility manager who is the on-site U.S. government point of contact for this work.

2.2. Site Survey: The contractor shall visit the building and walkthrough with the building’s facility manager to survey the current UPS and determine the feasibility of replacing the UPS and any required building or power modifications such as possibly removing or modifying transformers.

2.3. UPS Parts and Service Procurement and Estimated Timeline: Based on the site survey and obligated funding, the contractor shall procure or source the replacement UPS parts and required services. The contractor shall provide the facility with an estimated schedule for current UPS removal, replacement UPS installation, and replacement UPS full operation.

2.4. Current UPS removal and disposal: The contractor shall schedule with the facility manager on removing the current UPS and making any required building or power modifications prior to the installation of the new UPS. With approval of the facility manager, the contractor shall execute removal of current UPS and make the required building or power modifications. The contractor MUST ensure the facility continues to receive base commercial power prior to shutdown of the current UPS. The contractor shall safely transport, dispose, and/or recycle the current UPS.

2.5. New UPS installation: Contractor provides all necessary labor, tools, materials, and services to install the replacement UPS and use existing batteries.

2.6. New UPS integration: The contractor will be responsible for testing, configuring, and validating the new UPS operation to ensure that it supports specified load capacity, to ensure that the building tenants can maintain their mission.

Part 3

Logistics and Security

3.1. Hours of Performance: Standard work typically occurs between 0800 to 1600 Korea Standard Time, Monday through Friday, excluding holidays, unless otherwise approved by the Contracting Officer Representative (COR).

3.2. Site Access and Clearance Requirements: The contractor must have access into Osan Air Base without being escorted in. The contractor shall be given access to the building’s facility power systems by the facility manager. While the contractor does not require a U.S. security clearance, they shall be escorted by the facility manager, unit security manager, or an assigned member for 7 AF/A8/9 when on the 2nd floor and 3rd floor of Building 946.

Part 4

Deliverables

4.1. Installation of the new UPS and integration with the facility’s power system

4.2. Manuals and Diagrams: The contractor must provide operating and maintenance manuals, technical data sheets, and detailed wiring diagrams of the new UPS.

4.3. Service Tickets: Paper or electronic reports detailing all work being performed.

4.4. Training: Instructions for facility manager on how to properly operate the UPS, including bypass switchboard and emergency power off buttons.

4.5. Warranty: Standard requirement of a one-year warranty of all materials and workmanship from the date of acceptance.

CUI