DRAFT - Bldg 941 Replace Air Handler Unit Specifications.pdf
PDF 1 MB Posted
- Attached to
- Bldg 941 Replace Air Handling Unit 1 Federal contract opportunity
- Solicitation number
- F2X3CE4115A001
About this file
This document is a draft Statement of Work (SOW) and specifications for the PNQS 24-3075 Replace AHU-1 Building 941 project at Maxwell Air Force Base, Alabama. The key details are:
The project involves replacing the inoperable air handling unit-1 (AHU-1) located in Building 941 at Maxwell AFB. The work includes demolition of the existing AHU-1, providing and installing a new AHU, connecting ductwork, piping, instrumentation, controls, and electrical components. The contractor will have 21 days to complete the AHU-1 demolition and installation once all equipment is on site. The contractor must comply with all applicable environmental laws and regulations, and obtain necessary federal, state, and local permits. Contractor responsibilities include site disturbance and erosion control measures, hazardous materials management, waste disposal, protection of cultural/historical resources, and restoration of any damaged landscaping. The government estimates a 310 calendar day period of performance for the project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sources Sought - B941 Replace AHU.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPLACE AHU-1
BLDG 941
MAXWELL AFB, AL
PNQS 24-3075
SECTION 00002 TABLE OF CONTENTS
SECTION 00002
TABLE OF CONTENTS
DIVISION DESCRIPTION PAGES
SECTION 00002 TABLE OF CONTENTS PAGE 1
SECTION 00005 BID SCHEDULE PAGE 1
DIVISION 0 – CONDITIONS OF THE CONTRACT
SECTION 01000 GENERAL REQUIREMENTS PAGES 1 - 16
SECTION 01001A EXHIBIT L, ENVIRONMENTAL PROTECTION PAGES 1 - 10
DIVISION 1 - GENERAL
SECTION 01305 SUBMITTAL PROCEDURES PAGES 1 - 3
AF FORM 3000 MATERIAL APPROVAL
AF FORM 66 SUBMITTAL REGISTER
SECTION 01670 RECYCLED / RECOVERED MATERIALS PAGES 1 - 3
RECYCLING & LANDFILL REPORT
CONTRACTOR’S ENVIRONMENTAL ENTRY FORM
CONTRACTOR’S HAZ MAT QUESTIONNAIRE
PAGES 1 - 19
PAGES 1 – 6
PAGES 1 – 20
PAGES 1 - 24
PAGES 1 – 23
PAGES 1 – 16
DIVISION 23 – MECHANICAL
SECTION 23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION AND EXHAUST SYSTEMS
SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING
SECTION 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
SECTION 23 09 00 Instrumentation and Control for HVAC
SECTION 23 09 13 Instrumentation and Control devices for HVAC
SECTION 23 09 23 BACnet Direct Digital Control for HVAC
SECTION 23 64 26 CHILLED AND HOT WATER PIPING SYSTEMS PAGES 1 – 22
REPLACE AHU-1
MAXWELL AFB, AL
PNQS 24-3075
SECTION 00002 TABLE OF CONTENTS
DIVISION 26 – ELECTRICAL
SECTION 26 20 00 INTERIOR DISTRIBUTION SYSTEM PAGES 1 - 26
SECTION 26 29 23 VARIABLE SPEED CONTROLLERS PAGES 1 – 10
END OF SECTION
Section 00005
REPLACE AHU-1
BLDG 941
MAXWELL AFB, AL
PNQS 24-3075
SECTION 00005
SCHEDULE OF BID ITEMS
Furnish all plant, labor, materials, and equipment necessary to perform all work in connection with Project Number PNQS 24-3075, REPLACE AHU- 1, at BLDG 941, MAXWELL AFB in accordance with the attached Statement of Work (SOW), specifications, and drawings.
Item No. Description Unit of Issue
Total Amount
REPLACE AHU- 1
BUILDING 941
MAXWELL AFB, AL
LS $______________
TOTAL FOR ITEM: 0001 Lump Sum $ _________________
COMPANY NAME: ___________________________________
PRINTED NAME: _____________________________________
SIGNATURE: _________________________________________
DATE: ________________________________________________
REPLACE AHU-1 PNQS 24-3075
MAXWELL AFB, ALABAMA
Section 01000 Page 1 of 16
1.0 DIVISION 1: SECTION 01000: GENERAL REQUIREMENTS
1.01 SUMMARY OF WORK
The work covered by these specifications consists of furnishing all plant, labor, equipment, and materials and performing all operations in connection with the PNQS 24-3075, REPLACE AHU-1 at Building 941, MAXWELL AFB to include all areas as indicated on drawings and in strict accordance with these specifications and applicable drawings and subject to terms and conditions of the contract.
The work generally consists of the following:
1. Maxwell AFB Bldg. 941 AHU-1 (air handling unit-1) located in mechanical room 44 is currently inoperable. Since existing inoperable air handler will act as the supply and return points for temporary ductwork from temporary air handler supplied, installed, and maintained under separate contract, demolition of existing air handler -1 cannot take place until contractor is ready to install new air handler. At such time that all equipment including new air handler is onsite, at agreed upon time, once contractor starts demolition of existing air handler-1, contractor shall have no more than 21 days to complete the demolition of the existing air handler and have new air handler in service supplying conditioned air to all parts of the building that was served by the existing air handler.
2. New air handler shall be as per attached drawings and specifications. Provide and install all connecting ductwork, airflow control dampers, CHW (chilled water) and HW (hot water) coil connecting piping, 2-way characterized ball modulating control valves, shut off valves, check valves, circuit setters, and hydronic specialties, ductwork and piping insulation, instrumentation, sensors, BAS (building automation system), BACnet protocol controller(s), AHU supply fan VFD (variable frequency drive), and required electrical wiring, conduit, switches per attached drawings.
3. Tie-in new AHU duct work at OA, RA and SA points shown on attached drawings.
4. Reinstall existing AHU smoke detectors in new mechanical room duct work. Install per NFPA-99 and NFPA-72. Re-certify portion of fire alarm system modified after duct detectors have been reinstalled.
5. Reuse existing fire dampers at duct entrance to mechanical rooms.
6. Provide and install externally located VFD for AHU fan operation.
7. Provide and install OA (outside air), RA (return air), and relief air galvanized airfoil blade air dampers with 24 volt operated modulating actuators controlled through new AHU-1 BAS controller.
8. Replace chilled water and hot water piping within both mechanical rooms as necessary for transitioning to new AHU chilled water and hot water coils.
9. The existing BAS controller for air handling unit shall be replaced with Schneider Electric or Distech direct digital controller(s). New controller(s) shall communicate through BACnet protocol.
All new equipment shall be able to communicate to BAS building through BACnet communications protocol. All new controls shall seamlessly communicate with Base-wide Schneider front end EMCS. Contractor’s DDC contractor shall integrate current building floor plan into new controller(s). Provide and install emergency shut-off switch in room 44 that will shut down all building ventilation units including both existing air handler -2 and new air handler-1.
MAXWELL AFB, ALABAMA
Section 01000 Page 2 of 16
10. Control cable inside mechanical rooms shall be installed in conduit except for final actuator and device connections. Provide EMT-type conduit with NEC compliant junction boxes.
11. Provide NEMA rated junction boxes, control wiring, low voltage or 120-volt required for a complete and operable system.
12. Reuse existing Air handling unit electrical circuit for new unit. Circuit shall be intercepted, and new variable speed drive installed. Provide controllers for motors rated one 1 horsepower and larger with electronic phase-voltage monitors designed to protect motors from phase-loss, undervoltage, and overvoltage. Provide protection from immediate restart by a time adjustable restart relay for motors. The service voltage to the building is existing. Installation shall comply with National Electric Code, and manufacturer’s recommendations. Maintain all clearances for electrical equipment per NEC.
2.01 BUILDING OCCUPANCY
2.01.1 The building will be occupied.
3.01 SCHEDULE OF WORK
The Contractor shall be responsible for establishing a schedule to meet construction time. See item 1 under 1.01- SUMMARY OF WORK. Contractor shall prepare a work schedule on forms provided by Contracting Officer (CO)/Contract Administrator for schedule of work. Contractor shall have 310 calendar days to complete the work.
3.01.1 PHASING OF WORK: See the plans.
4.01 GENERAL
4.01.1 The contractor shall coordinate work with the Technical Manager (TM)/Contract Administrator to avoid interference with necessary activities within and adjacent to the construction site. The Contractor shall coordinate the work of all trades to prevent any conflicts. The Contractor, before proceeding with the construction, shall resolve any conflicts of components.
4.01.2 The Contractor will perform all work during work hours between 6:00 A. M. and 5:00 P.M (normal working hours). The Contractor will not normally be permitted to work on weekends or on the following legal holidays (or the day the federal government observes these holidays) unless the work has coordinated such work with the TM/Contract Administrator at least 72 hours in advance:
a. New Year's Day g. Labor Day
b. Martin Luther King, Jr.'s Birthday h. Columbus Day
c. Washington’s Birthday i. Veteran's Day
d. Memorial Day
e. Juneteenth j. Thanksgiving Day
f. Independence Day k. Christmas Day
5.01 SITE VISIT
MAXWELL AFB, ALABAMA
Section 01000 Page 3 of 16
Contractor is responsible for site investigation in accordance with contract clause entitled "Site Investigation and Conditions Affecting the Work" (FAR 52.236-3).
6.01 CONTRACT DRAWINGS AND SPECIFICATIONS
The Contractor must comply with the contract clause entitled "Specifications and Drawings for Construction" (FAR 52.236-21). See paragraph 19.01 entitled "INTENT OF DRAWINGS".
7.01 MATERIAL AND EQUIPMENT SUBMITTALS AND REQUIRED REAL ESTATE SUBMITTAL
DATA
7.01.1 SUBMITTAL REGISTER
Within ten (10) calendar days after receipt of "Notice to Proceed," of the contract, the Contractor shall furnish the Government a Submittal Register to indicate the Contractor's scheduled submittal dates. The Register shall contain all items (shop drawings, manufacturer's literature, certificates of compliance, material samples, guarantees, etc.) that the Contractor shall submit for review and approval action during the life of the contract. The Register will be furnished as one (1) original plus two (2) copies. The Contractor shall take special care to timely schedule the submittal data required for long lead-time items.
The Contractor will submit three (3) copies of all required submittals unless otherwise specifically indicated.
7.02 DESCRIPTIVE DATA
The Contractor shall submit three (3) copies of AF Form 3000, Material Submittal Approval, to the Contracting Officer (CO) for approval. Included shall be manufacturer's descriptive data for materials, fixtures, and equipment the Contractor proposes to incorporate in the work. The submittal shall include catalog numbers, diagrams, drawings, and such additional descriptive data and samples required to properly evaluate all items. When specifications require materials to conform to Federal, Military, Commercial, American Society for Testing Materials (ASTM), or other specifications and standards, the Contractor shall submit supplier's or manufacturer's Certification of Conformance in addition to other descriptive data. Catalog numbers and trade names specified indicate examples of a standard product.
Other manufacturers' products may be substituted contingent upon approval. Approval of all items must be obtained prior to fabrication or purchase. Payment for work incorporating these materials will not be made if required material submittals have not been approved. Approval of materials, fixtures, and equipment will be based on manufacturer's published ratings and conformance with specifications.
7.02.1 The Material Descriptive Data Submittal shall include the information indicated in each specification section.
7.02.2 The Shop Drawing Submittal shall include the information indicated in the each specification section.
7.02.3 The Samples Submittal shall include the information indicated in each specification section.
7.03 CONTRACTOR DEVIATION
When data is submitted for approval, the Contracting Officer approval of such data shall not relieve the Contractor from responsibility for errors or deviation from contract drawings and specifications. In the case of a deviation, the Contractor shall inform the Contracting Officer in writing of the request for deviation with all the specific data related to the change.
8.01 REAL PROPERTY SUBMITTAL DATA:
PNQS 24-3075 REPLACE AHU-1
MAXWELL AFB, ALABAMA
Provide data as requested by the Government to complete real property records.
8.01.2 REMOVED EQUIPMENT AND REFRIGERANT: N/A.
8.01.3 SALVAGED EQUIPMENT: N/A
8.02 REMOVAL PROCEDURES:
No removed items will be reused in this contract unless specifically listed in these specifications and/or on the drawings. All removed equipment becomes the property of the Contractor unless noted otherwise.
The Contractor will be required to furnish lifting equipment as necessary to remove the equipment, and shall provide all equipment to transport the removed items off base. All unused material or debris will be removed from Government-controlled property. Use of Government-contracted dumpsters is prohibited.
Unused materials, debris and rubbish shall be disposed of off base in a permitted landfill. The Contractor shall comply with Alabama Department of Environmental Management (ADEM) Code, Division 13, Solid Waste Program, and Chapter 335-13-1, through 335-13-8; Adopted November 18, 1981; Amended July 26, 1996.
REFER TO SPECIFICATION SECTION 01001A – GENERAL REQUIREMENTS
ENVIRONMENTAL PROTECTION
8.03 REFRIGERANTS
All refrigerants must remain the possession of the Air Force. Refrigerants from any refrigeration systems removed must be turned over to the Refrigerant Manager, 42CES/CEOH, 400 Cannon Street, Maxwell
AFB.
REFER TO SPECIFICATION SECTION 01001A – GENERAL REQUIREMENTS
ENVIRONMENTAL PROTECTION
9.01 GOVERNMENT-FURNISHED ITEMS: N/A
10.01 REFERENCED PUBLICATIONS
All publications referenced in this specification, but not shown in each part under paragraph entitled "APPLICABLE PUBLICATIONS", also form a part of these specifications to the extent referenced.
11.01 HEALTH STANDARDS
The following specified guidance is essential to maintaining compliance with the health standards on this base. This contract must adhere to all of the following:
11.01 Radioactive Materials (RAM): Air Force requirements for the management are listed in AFI 40- 201, Management Radioactive Materials in the USAF. All contractors who intend to bring RAM (such as the materials in the soil density gauges, X-ray fluorescence meters, etc.) onto Maxwell AFB must first obtain written approval from the Base Radiation Safety Officer (RSO), in the Bioenvironmental Engineering (BEE) Flight 334-953-5848. To provide this approval, the RSO needs a written request no later than 30 days prior to initiating any work requiring radioactive material. The request must include the following information:
11.01.1 A copy of your NRC license (or State license with a current NRC FonD 241) that authorizes your use of radioactive material on this installation.
11.01.2 Training certificate(s) for individual(s) who will use the instrument on base.
Section 01000 Page 4 of 16
MAXWELL AFB, ALABAMA
11.01.3 The most recent leak/wipe test for the instrument(s) that will be used on base.
11.01.4 A signed document on company letterhead paper that includes:
a. A brief description of your proposed activities including: instruments to be used and their purpose, the contract number and title under which you will work, location of the work (closest building number, annotated map, or similar identification), and anticipated start and end dates (with the understanding that actual days of use are difficult to specify in advance).
b. The name, local address, and telephone number of both the responsible local representative and the RSO.
c. Name and phone number of the Maxwell AFB inspector overseeing the project.
d. An acknowledgement that the Maxwell AFB RSO can make periodic Checks to ensure contractor personnel follow radiation safety practices to prevent exposure to Air Force personnel and avoid contamination of government property as well as an understanding that the Maxwell AFB RSO has the authority to suspend any contractor operation believed to be unsafe.
11.02 Asbestos/Lead-Based Paint
Contractors who will perform asbestos and or lead-based paint abatement work must comply with all OSHA regulations and be certified by Safe State of Alabama. In particular, after all visible debris has been removed and the abatement area has been appropriately decontaminated, the contractor must perform clearance sampling verifying the area is clean before re-occupancy can be allowed. BEE must review all clearance sample results prior to government acceptance of abatement areas as clean.
Contractors can expedite this process by faxing copies of clearance results directly to the BEE for review.
REFER TO SPECIFICATION SECTION 01001A – GENERAL REQUIREMENTS
ENVIRONMENTAL PROTECTION
11.03 Drinking Water:
11.03.1 If a facility is to be constructed in which sources of drinking water are provided (sinks, water fountains, showers, etc.), the water lines must be flushed thoroughly prior to occupancy. BEE approval is required before the water is declared potable. If the contractor is required to test the interior water lines, provide BEE the documentation at two weeks prior to occupancy of the facility .If the contractor is not required to do bacteriological testing of the interior water lines, the BEE office should be contacted at least two weeks prior to occupancy so that we may schedule our testing of the system.
11.03.2 If water mains are constructed or repaired, disinfection of the lines must be conducted as stated in ANSI/AWWA C651-92, American Water Works Association for Disinfecting Water Mains prior to putting into service. Provide our office with a copy of the documentation that demonstrates compliance with the above requirements. We recommend coordination of the plan to disinfect water mains prior to construction to ensure that we agree with the disinfection and testing method.
11.04 HAZARDOUS MATERIALS:
All hazardous chemicals (including paint, cleaning solutions, solvents and so on) used by the contractor must be registered with the Maxwell AFB Hazardous Material Manager, which can be contacted at (334) 953-5260.
Section 01000 Page 5 of 16
MAXWELL AFB, ALABAMA
REFER TO SPECIFICATION SECTION 01001A – GENERAL REQUIREMENTS
ENVIRONMENTAL PROTECTION
12.01 EXCAVATION:
Prior to excavating for any purpose, the Contractor shall obtain an approved Construction Permit, AF Form 103 (dated July 1982), from the MSD/CE, 400 Cannon Street, Maxwell Air Force Base. The purpose of this form is to give the Contractor clearance to excavate a given area, to protect the underground facilities, and to protect personnel from injury. The Government will determine what facilities are beneath the surfaces and discuss their locations with the Contractor prior to issuing the AF Form 103.
The Contractor is required to determine the exact location to be excavated in relation to the underground facilities prior to excavating. The AF Form 103 may note cable, pipe, etc., in the area; if this occurs, Contractor will be responsible for digging in such a manner so as not to damage the hidden facility.
Contractor will place particular emphasis on the site inspection prior to proposing to determine which facilities are obviously in the area. After receipt of the approved AF Form 103, the Contractor will not perform any excavation work without specific approval by the Contracting Officer.
13.01 GROUND FAULT CIRCUIT INTERRUPTERS
Whenever the Contractor uses portable electrical tools or equipment in an outside location or in an interior wet location where floor is conductive such as concrete, the Contractor shall provide and use a portable ground fault circuit interrupter (GFCI). This shall apply wherever electric power is supplied through Government-controlled facilities. The Contractor shall be responsible for maintaining the GFCI in operating condition and testing it before each use.
14.01 EQUIPMENT MAINTENANCE AND OPERATING INFORMATION
15.01 EQUIPMENT OPERATING, MAINTENANCE, AND REPAIR MANUALS:
15.01.1 Data Required. Three (3) copies of each manual shall be submitted for approval to the Contracting Officer. The submittal schedule shall be as shown on the submittal register. Each manual shall include the following:
15.02.1 The manuals shall be bound in a 3-ring binder with a hard cover, or 3-hole portfolio for small projects. The following identification shall be inscribed on the cover: "EQUIPMENT OPERATING, MAINTENANCE, AND REPAIR MANUAL" and the building name and number, location, and indication of utility or system covered. Manuals shall be approximately 8 1/2 by 11 inches with large sheets folded in and capable of being easily pulled out for reference.
15.02.2 A warning page shall be provided to warn of potential dangers (it they exist), such as high voltage, toxic chemicals, flammable liquids, explosive materials, carcinogens, or high pressures. The warning page shall be placed inside the front cover, in front of the title page.
15.02.3 The title page shall show the name, address and phone number of the Contractor, the contract number and the date of publication.
15.02.4 Provide a table of contents in accordance with standard commercial practice.
15.02.5 Separate Sections and manuals. Manuals shall include, in separate sections, the following information for each item of equipment and system:
15.02.6 Performance sheets and graphs showing capacity data, efficiencies, electrical characteristics, pressure drops, and flow rates. Marked-up catalogs or catalog pages do not satisfy this requirement.
Performance information shall be presented as concisely as possible and contain only data pertaining to
Section 01000 Page 6 of 16
MAXWELL AFB, ALABAMA
Section 01000 Page 7 of 16 equipment actually installed.
15.02.7 Catalog cuts showing application information
15.02.8 Installation information showing minimum acceptable requirements.
15.02.9 Operation and maintenance requirements. Include adequate illustrative material to identify and locate operating controls, indicating devices and locations of areas or items requiring maintenance.
Describe, in detail, starting and stopping procedures for components, adjustments required to obtain optimum equipment performance, and corrective actions for malfunctions. Maintenance instructions describing the nature and frequency of routine maintenance and procedures to be followed. Indicate any special tools, materials, and test equipment that may be required.
15.03 Repair information including diagrams and schematics, guidance for diagnosing problems, and detailed instructions for making repairs. Provide trouble-shooting information that includes a statement of the indication or symptom of trouble and the sequential instructions necessary. Include test hookups to determine the cause, special tools, and test equipment, and methods for returning the equipment to operating conditions. Information may be in chart form or in tabular format with appropriate headings.
15.03.2 Parts list, names and addresses of the two closest parts supply agencies.
15.03.3 Names and addresses of the local manufacturer representatives and the parent company.
16.01 OTHER EQUIPMENT
The Contractor will be required to furnish a brochure, catalog cut sheet, parts list, manufacturer's spec sheet, and/or other printed information that shows detailed parts data, and the manufacturer's name, address, and telephone number, for all other equipment (such as hardware, lighting fixtures, etc.) subject to repair or maintenance procedures. The data shall be furnished in three (3) copies (for each building) to the CO at the final inspection. This requirement is in addition to the requirements for material submittals specified elsewhere in this contract. Information submitted as a part of "Equipment Operating, Maintenance, and Repair Manuals" will be considered a part of this requirement.
17.01 FIRE REGULATIONS
The Contractor shall comply with all aspects of the National Fire Protection Association (NFPA) publication 241, "Safeguarding Building Construction, Alteration and Demolition Operations; EM 385-1-1, Safety and Health Requirements Manual; and Maxwell AFB Instruction 32-2005, Fire Prevention and Protection During Construction, Alteration, Demolition, and Repair Operations.
18.01 ASBESTOS
No friable asbestos containing materials will be installed as a part of this contract. Spray application of asbestos or asbestos-containing materials to exposed walls, ceilings, ducts, columns, etc. is prohibited.
In the event friable asbestos containing materials are encountered during "rip out" and demolition operations, the Contractor shall stop work immediately and notify the TM/Contract Administrator who will take appropriate action.
REFER TO SPECIFICATION SECTION 01001A – GENERAL REQUIREMENTS
ENVIRONMENTAL PROTECTION
19.01 INTENT OF DRAWINGS
All drawings are diagrammatic and are intended to qualify the materials specified and indicate their intended relationship to each other. The drawings are not to be scaled, rather field conditions should
MAXWELL AFB, ALABAMA
Section 01000 Page 8 of 16 dictate placement. The various scales used on the drawings may not allow the indications of all fittings, offsets, and accessories that may be required. The Contractor is to carefully investigate the conditions that would affect the work to be performed and shall arrange such work accordingly.
20.01 AS-BUILT DRAWINGS
The Contractor shall provide to the Government marked drawings commonly referred to as "as-builts" indicating conditions that differ from that shown on the contract plans. The Contractor will review with the CO the "as-builts" as needed to ensure an accurate up-to-date set of documents is being kept. Changes are to be noted as the work progresses. The Contractor will utilize a Government-furnished copy of the contract drawings with the changes neatly indicated in red using the drafting standards and legends indicated in the contract drawings. One copy is required and will be submitted to the CO at the final inspection. If there are no changes, a title sheet (from the contract drawings) will only be required with the note "NO CHANGES" marked appropriately.
21.01 TRAFFIC CONTROL
The Contractor shall be responsible for the orderly handling of traffic through the work at all times during the life of the construction contract. This shall be accomplished in conformity with Sub article (d).
"HANDLING OF TRAFFIC," of Article 104.04, "Sequence of Construction for Handling Traffic Through the Work and Construction and Maintenance of Detours," of Section 104, "SCOPE OF WORK," of the Alabama Highway Department "Standard Specifications for Highway Construction," 1992 Edition. In this specification, the word "Engineer" Shall be replaced with the words CO.
22.01 CONTRACTOR MAINTENANCE
At the end of each working day the Contractor shall clean up the work site which includes the construction area(s), construction office area(s), material storage area(s), parking and eating area(s), and any other area(s) affected by the construction process. Stacked material shall not be within 8m (25-feet) of an active roadway. Tracking of soil, mud or other construction debris or substance on any Base street, parking area, sidewalk, patio, driveway, turf, or other area shall not be permitted. The Contractor shall keep all turfed areas mowed and clean within the construction limits, and shrubs and other elements in the landscape shall be maintained.
23.01 ENVIRONMENTAL PROTECTION
REFER TO SPECIFICATION SECTION 01001A – GENERAL REQUIREMENTS
ENVIRONMENTAL PROTECTION
23.01.3 MAXWELL & GUNTER STORMWATER BMP FOR LATEX PAINT:
REFER TO SPECIFICATION SECTION 01001A – GENERAL REQUIREMENTS
ENVIRONMENTAL PROTECTION
23.01.4 MAXWELL & GUNTER STORMWATER BMP FOR OIL BASE PAINT, POLYURETHANE &
CLEANING SOLUTIONS:
REFER TO SPECIFICATION SECTION 01001A – GENERAL REQUIREMENTS
ENVIRONMENTAL PROTECTION
MAXWELL AFB, ALABAMA
23.01.5 CONTRACT REQUIREMENTS FOR BUILDINGS WITH LEAD-BASED PAINT
REFER TO SPECIFICATION SECTION 01001A – GENERAL REQUIREMENTS
ENVIRONMENTAL PROTECTION
24.01 ENVIRONMENTAL RELEASE REPORTING
An environmental release report shall be completed for all environmental releases that are caused by an Air Force activity or which occur on an Air Force installation or facility. Examples of environmental releases are listed as follows but not limited to: oil releases to navigable waters, hazardous substance release above the reportable quantity, vinyl chloride releases, excessive emissions over amount allowed in permits, hazardous material incidents occurring during transportation, underground storage tank spills and releases, and any emergency incidents of environmental contamination. The Contractor shall immediately notify the TM in the event of any environmental release. The following information shall be documented; the time, type, amount, and cause of release.
25.01 PROTECTION OF EXISTING LANDSCAPE DURING CONSTRUCTION:
REFER TO SPECIFICATION SECTION 01001A – GENERAL REQUIREMENTS
ENVIRONMENTAL PROTECTION
25.01.1 REPAIR OR REPLACEMENT OF DAMAGED LANDSCAPE
If any failure to comply with these General Requirements Section or any other Contract Specification or provision or term of this contract occurs during installation, maintenance, or warranty, the Contractor shall be held responsible. Any damage occurring to Government property during the execution of this contract shall be repaired to the Government standards as defined in "The Maxwell Landscape Management Operational Instruction Manual" by the Contractor at no additional cost to the Government. The repair work shall be inspected and accepted by the Government. Any discrepancies shall be fixed before acceptance.
25.02.2 REQUIREMENTS
25.02.2.1 The following requirements shall be observed by the Contractor in order to protect existing landscape (to include trees, shrubs, flowers, turf, flower beds, sidewalks, patios, fences, etc.) during construction operations.
No vehicle parking is allowed under canopies or within the drip-line root zone of protected trees. All trees are to be protected unless they are shown to be removed on the plans.
No storage of materials will be allowed under protected tree canopies or beside existing shrub plantings.
25.02.2.2 No storage of materials on turf areas shall be allowed unless the TM/Contract Administrator has given the Contractor approval. If any lawn damage occurs (even with special permission), the Contractor shall restore the lawn per par. 25.02.2.3.05 below.
25.02.2.3 No driving across, parking, or other equipment operations on existing turf shall be permitted unless prior approval has been obtained from the TM/Contract Administrator. If any lawn damage occurs (even with special permission), the Contractor shall restore the lawn per par. 25.02.2.3.05 below.
25.02.2.3.01 No pruning or breaking off existing trees or shrubs shall be permitted unless prior approval has been obtained from the TM/Contract Administrator. If prior approval is not obtained, the Contractor is liable for the repair/replacement of any damaged landscape items.
Section 01000 Page 9 of 16
MAXWELL AFB, ALABAMA
25.02.2.3.02 No work shall damage the health of any tree whose roots extend into the construction area.
No fences, ropes, cables, signs, or devices of any kind shall be attached to any tree.
25.02.2.3.03 The TM shall be notified immediately of any damage occurring to a tree in the construction site, or any tree damaged by Contractor personnel. The TM/Contract Administrator shall direct measures, if any, to treat the injury. The Government shall incur no cost for any corrective measures, including, but not limited to, removal and replacement of the tree.
25.02.2.3.04 If the Contractor causes the death or 60% decline to any protected tree(s) within a 24 month period, the Contractor shall remove and replace the damaged tree(s) with size and species of tree(s) directed by the TM. The size of the new tree(s) shall equal caliper size of removed tree(s).
25.02.2.3.05 Damaged turf areas shall be replaced with sod per “The Maxwell Landscape Management Operational Instruction Manual.” The use of grass seed to repair turf damage at Maxwell AFB or Gunter Annex is not permitted.
26.01 STAGING AREA
The Contractor will be provided space as indicated for an office trailer and a 6’ wood fence with lockable gates around the staging of materials in support of this project and must provide protection and security for it in that area.
27.01 TESTING
Where specific tests are required by this contract, the Contractor shall notify the TM/Contract Administrator at least 24 hours prior to testing. The Contractor shall turn in a test report, if required, to the TM/Contract Administrator as soon as possible. The Contractor shall not proceed with any work that would cover up the work being tested until the TM/Contract Administrator has approved the work being tested.
28.01 WARRANTIES
All workmanship, materials, and equipment shall be under warranty for at least one year as set forth in the contract clause entitled "Warranty of Construction" (FAR 52.246-21). See specs for warranties extending beyond the one year period.
29.01 PROTECTION OF GOVERNMENT PROPERTY AND PERSONNEL
29.01.1 WORK AREAS INCLUDED
29.01.2 Construction site.
Area or areas in which the work of the contract is accomplished or performed.
29.01.3 Storage areas.
Area or areas used for the storage of materials, devices, appliances, and equipment to be used in the work.
Section 01000 Page 10 of 16
MAXWELL AFB, ALABAMA
Section 01000 Page 11 of 16
29.01.4 Office and shed areas.
Area or areas for placing or setting of temporary field office, tool sheds, or storage sheds.
29.01.5 Transportation areas.
Area or areas that are defined as streets, roads, driveways, parking areas, etc., paved, treated, and unpaved; area or areas not paved, such as grass plots or grass areas used for transportation purposes.
29.02 CONDUCT OF WORK
The Contractor shall conduct work so the Government property and personnel, other personnel, and work areas shall be protected at all times from inconvenience, damage of any nature, or injury caused by this work until completion of the contract.
29.03 REPAIR OR REPLACEMENT OF DAMAGED PROPERTY
29.03.01 In the event of damages of any nature caused by this work (including maintenance and warranty operations) due to improper protection, precaution, or safety measures, such damages shall be repaired or such property shall be replaced by the Contractor at no expense, cost, or charge to the Government.
In the event the Contractor does not satisfactorily repair or replace such damage caused by the work of the contract, the Government reserves the right to make the necessary corrections and deduct from the contract price the cost to the Government for inconveniences, labor material, etc. involved. Reference contract clause "Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements"
(FAR 52.236-9).
29.03.2 Contractor shall protect all communications cabling while working and if damage is caused by the contractor, then the contractor shall replace the damaged communications cabling with same, or for internal cable, base standard CAT 6 cable. All CAT 6 cable must be home run to the communications room. Copper tie cables must be replaced with same. Fiber optic cables must be a continuous strand with no splices. All communication cabling must be wired to T568B standard.
29.04 BARRICADES
The Contractor shall furnish, place and maintain all required barricades as directed by the Safety Office and the TM/Contract Administrator, and access driveways and doors will remain clear at all times.
30.01 FINAL CLEANING
30.01.1 CLEANING SCHEDULE
Execute final cleaning prior to the final inspection.
30.01.2 PROCEDURES
30.01.3 Clean surfaces exposed to view.
30.01.3.1 Remove temporary labels, stains, and foreign substances; polish transparent and glossy surfaces; wet mop tile or sealed concrete floors, vacuum carpeted floors, broom clean other floors.
30.01.3.2 Clean equipment and fixtures to a sanitary condition.
30.01.3.3 Clean or replace filters of mechanical equipment.
MAXWELL AFB, ALABAMA
Section 01000 Page 12 of 16
30.01.3.4 Any additional cleaning as specified in other sections.
30.01.3.5 Clean sites of all construction related and project related debris.
30.01.3.6 Remove waste and surplus materials, rubbish, and construction facilities from the work areas and the site.
31.01 CLOSEOUT PROCEDURES
When the Contractor is ready for final inspection, the Contractor shall notify the CO (in writing) within two
(2) working days of the desired inspection date. During the inspection, the Contractor and the CO shall document all deficiencies on a "punchlist." The CO will provide a formal copy of the punchlist to the Contractor. The Contractor shall be responsible for correcting all punchlist items prior to the end of the contract completion date and notify the CO (in writing) when the contractor is ready for re-inspection.
32.01 SECURITY REQUIREMENTS FOR UNCLASSIFIED CONTRACTS
32.01.1 NOTIFICATION
The Contractor shall notify 42 SFS/SPAI, Maxwell AFB AL, no later than 10 days after contract award.
The notification shall include:
a. Name, address, and telephone number of each company representative.
b. The contract number and contracting agency (e.g., 42 CONS/PKC).
c. The description of the work to be performed/construction project number.
d. The location(s) of the construction work (i.e., street address or other description of the construction site).
e. The date contract performance begins.
f. Any updates to information previously provided under this paragraph.
42 CONS/PKC will brief specific instructions during the Preconstruction Conference
32.02 LIST OF EMPLOYEES
The Contractor shall maintain a current listing of employees. The list shall include employee's name, social security number, and level of security clearance (if contract work involves unescorted entry to Air Force restricted or other sensitive areas designated by the installation commander). The list shall be validated and signed by the company Facility Security Officer (FSO) and provided to the TM/Contract Administrator, Maxwell AFB, AL, prior to the contract start date. Updated listing shall be provided when an employee's status or information changes. 42 CONS/PKC will brief specific instructions during the Preconstruction Conference
32.03 PASS AND IDENTIFICATION
32.03.1 The Contractor shall obtain the following pass and identification items:
32.03.1.1 DD Form 1172, "Application for Uniformed Services Identification Card" (AFI 36-3001 and AETCR 30-1). Forms shall be supplied by the Contracting Office Customer Service Station. The Contractor shall fill out the forms and take them to Pass and Identification, Building 502, 10 North Pine Street, Maxwell AFB.
32.03.1.2 AETC Form 58, "Civilian Identification Card" (AETCR 30-1). Pass and Identification will issue this to each Contractor employee.
32.03.1.3 AF Form 2219 (series), "Registered Vehicle Expiration Tab", (AFI 31-204), "Motor Vehicle Traffic Supervision" and DD Form 2220, "DOD Registered Vehicle and Installation Tab" (AFI 31-204).
The Security Forces, Pass and Registration Section, Building 502, 10 North Pine Street (at the Bell Street entrance) will issue vehicle registration decals, upon proof of employment, insurance, ownership of
MAXWELL AFB, ALABAMA
Section 01000 Page 13 of 16 vehicle, and a valid driver's license. A temporary decal will be issued if employment is for six months or less.
32.03.1.4 AF Form 1199, USAF Restricted Area Badge, or a locally developed badge (if applicable).
32.03.1.5 AF Form 75, Visitor/Vehicle Pass (AFI 31-204)
32.03.1.6 The Contractor shall retrieve all identification media, including vehicle decals from employees who depart for any reason before the contract expires (e.g., terminated for cause, retirement, etc.)
32.04 PHYSICAL SECURITY; KEY CONTROL; LOCK COMBINATIONS &
CONTROLLED/RESTRICTED AREAS
32.04.1 Physical security. The Contractor shall be responsible for safeguarding all Government property and controlled forms provided for the Contractor's use. At the end of each work period, all Government facilities, equipment, and materials shall be secured. The Contractor shall be also responsible for the security of his own facilities, equipment, and material.
32.04.2 Key control.
The Contractor shall establish and implement methods of making sure all keys issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. The following shall apply:
32.04.2.1.01 The Contractor shall not duplicate any keys issued by the Government
32.04.2.1.02 The Contractor shall immediately report any occurrences of lost or duplicated keys to the Government.
32.04.2.1.03 In the event of lost or duplicated keys, the Contractor may be required, upon written direction of the Government, to re-key or replace the affected lock or locks without cost to the Government. The Government may, however, at its option, replace the affected lock or locks or perform re-keying and deduct the cost of such from payment due the Contractor. In the event a master key is lost or duplicated, the Government shall replace all locks and keys for that system and the total cost deducted from payment due the Contractor.
32.04.2.1.04 The Contractor shall prohibit the use of Government issued keys by any persons other than the Contractor's employees and the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in performance of contract work requirements in those areas.
32.04.3 Controlled/Restricted Areas.
The Contractor shall implement local Base procedures for entry to Air Force control/restricted areas where Contractor personnel will work.
32.04.4 Lock combinations.
The Contractor shall control access to all Government-provided lock combinations to preclude unauthorized entry.
32.05 OPERATING INSTRUCTION (OI)
If applicable, the Contractor shall develop an OI for internal circulation control, protection of resources, MAXWELL AFB, ALABAMA
Section 01000 Page 14 of 16 and regulated entry into Air Force controlled areas during normal, simulated, and actual emergency operations. The OI shall be coordinated through 42 SFS/SPAIR located at 130 W. Selfridge Street, Maxwell AFB, and shall be written in accordance with AFI 31-209 ("Air Force Resource Protection Program"), the local Base Operations Plan, and AFI 31-210 ("Anti-Terrorism Program").
32.06 REPORTING THREATS TO SECURITY
The Contractor shall comply with the requirements of AFI 71-101V1, "Counterintelligence Awareness and Briefing Program." Contractor personnel shall report to an appropriate authority any information or circumstances of which they are aware that may pose a threat to the security of DOD or Contractor personnel, resources, and classified or unclassified defense information. Contractor employees shall be briefed by their immediate supervisor upon initial on-base assignment.
32.07 WEAPONS, FIREARMS, AND AMMUNITION
Contractor employees are prohibited from possessing weapons, firearms, or ammunition on themselves or within Contractor-owned or privately owned vehicles while on Maxwell AFB or Gunter Annex.
32.08 TRAFFIC LAWS
All Contractor personnel shall comply with Base traffic regulations.
32.09 SUITABILITY INVESTIGATIONS
Contractor personnel shall successfully complete, as a minimum, National Agency Check (NAC), before operating government furnished workstations that have access to Air Force e-mail systems. These investigations shall be submitted by the government at no additional cost to the contractor. The contractor shall comply with the DOD 5200.2-R, Personnel Security Program, and AFI 33-119, Electronic Mail (E-Mail) Management and Use, requirements.
33.01 REQUIRED INSURANCE
33.01 Reference FAR clause 52.228-5 entitled “Insurance...” the Contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract.
a. Workmen’s Compensation and Employers Liability Insurance as required by law except that if this contract is to be performed in a State which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such State will be satisfactory. The required Workmen’s Compensation insurance shall extend to cover employer’s liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.
b. General Liability Insurance. Bodily injury liability insurance, in the minimum limits of $500,000 per occurrence shall be required on the comprehensive form of the policy.
c. Automobile Liability Insurance. The insurance shall be required on the comprehensive form of policy and shall provide bodily and property damage liability covering the operation of all automobiles used in connection with the performance of the contract. At least the minimum limits of $200,000 per person and $500,000, per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required. This insurance shall cover the operation of automobiles by Contractor employees and authorized Government employees and third parties.
34.01 CLAUSES AND PROVISIONS (SEP 2000)
MAXWELL AFB, ALABAMA
Section 01000 Page 15 of 16
34.01 Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.
34.02 Even though most of the clauses and provisions are incorporated by reference, some clauses and provisions are required to be completed and submitted by the offeror with offer. The full text of the clauses and provisions may be seen at https://www.acquisition.gov/
34.03 Clauses and provisions in this document will be numbered in sequence.
34.04 Sections K, L and M will be physically removed from any resultant award, but will be deemed to be incorporated, by reference, in that award.
35.01 SMOKING IN AETC FACILITIES
Contractors are advised that the Commander has placed restrictions on the smoking of tobacco products in AETC facilities. AFI 40-102, Tobacco Use in the Air Force, and its AETC supplement 1, outline the procedures used by the commander to control smoking in our facilities. Contractor employees and visitors are subject to the same restrictions as government personnel. Smoking is permitted only in designated smoking areas.
36.01 INSPECTION AND ACCEPTANCE
36.01 42 CES/CEN is designated as the office responsible for inspecting the work while the Contracting Officer is responsible for final acceptance of the work.
37.01 REQUIRED POSTERS
37.1 Please utilize the following website to access and download as appropriate EEO posters, Service Contract posters, and disability posters required in accordance with 52.222-26, 52.222-41, and 52.222-36 respectively.
http://www.dol.gov/osbp/sbrefa/poster/main.htm
END OF SECTION
https://www.acquisition.gov/ http://www.dol.gov/osbp/sbrefa/poster/main.htm
ENVIRONMENTAL PROTECTION 01001 Page 1 of 16
SECTION 01001A
EXHIBIT L
ENVIRONMENTAL PROTECTION
July 7, 2022
PART 1 GENERAL
1.0 DESCRIPTION
The work covered by this section consists of furnishing all labor, materials, and equipment and performing all work required for the prevention of environmental degradation during and as a result of construction operations under this contract. These requirements are in addition to any environmental protection requirements elsewhere in these specifications.
For the purpose of this specification, environmental pollution is defined as the presence of chemical, physical, or biological elements or agents, not naturally occurring at the site, which adversely affect human health or welfare; unfavorably alter ecological balances;
negatively affect plant or animal species; or degrade the utility of the environment for aesthetic and recreational purposes. The control of environmental pollution by the contractor requires consideration of air, water, and land, and involves noise control, solid waste management and management of radiant energy and radioactive materials, as well as other pollutants. This section also requires the protection of natural, cultural and historic resources.
1.1 ACRONYMS AND DEFINITIONS
ADEM – Alabama Department of Environmental Management CAA – Clean Air Act CO – Contracting Officer CERCLA – Comprehensive Environmental Response, Compensation and Liability Act CWA – Clean Water Act EPA – Environmental Protection Agency MAFB – Maxwell Air Force Base and Gunter Annex. Throughout this environmental protection section, MAFB (including Gunter Annex) may commonly be referred to as the base or installation.
Media – Any soil, water, or air that is moved, disturbed, or released from a site OSHA – Occupational Safety and Health Administration TM – Technical Manager RCRA – Resource Conservation and Recovery Act SDWA – Safe Drinking Water Act
TSCA – Toxic Substances Control Act 42 CES/CEIE – Maxwell Air Force Base Civil Engineering Squadron, Environmental Section.
Throughout this environmental protection section, this office will commonly be referred to as the “installation environmental office.”
The terms hazardous, waste, pollutant, contaminant, and substance have the same meanings and usage here as they commonly do in the CAA, CERCLA, RCRA, SDWA, and TSCA.
ENVIRONMENTAL PROTECTION 01001 Page 2 of 16
1.2 CONTRACTOR’S GENERAL ENVIRONMENTAL COMPLIANCE OBLIGATIONS
1.2.1. Work under this contract is to be performed on a government facility. All environmental rules applying to contractor operations elsewhere shall also apply on the government facility. Contractor (and any of their additional contractors, agents or representatives) shall comply with all applicable Federal, State, and local laws and regulations providing for environmental protection and pollution control and abatement. These include but are not limited to: the Clean Air Act, Clean Water Act, Resource Conservation and Recovery Act, Comprehensive Environmental Response, Compensation and Liability Act, Toxic Substances Control Act, Federal Insecticide Fungicide and Rodenticide Act, Coastal Zone Management Act, Endangered Species Act, Migratory Bird Treaty Act, National Historic Preservation Act, Archeological Resources Protection Act, Safe Drinking Water Act, Emergency Planning and Community Right-to-Know Act, Oil Pollution Act, and Pollution Prevention Act. Contractor has the duty to determine for himself/herself where such laws and regulations apply. Although the contractor may request assistance from the TM/Contract Administrator or the installation environmental office in delineating applicable environmental laws and regulations, contractor has an independent responsibility to make its own determination and to do so in a timely fashion. Environmental Management System (EMS) significant aspect is Hazardous Waste Compliance. Please ensure all personnel are aware of applicable RCRA requirements and have reviewed the Commander’s Policy at the end of this section.
1.2.2. Contractors are responsible to implement their own environmental compliance programs, to ensure…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .