STATEMENT OF WORK
Industrial Washer/Dryer Equipment for Laundry Facility B346
23 Jun 2016
I. Summary
Contractor shall perform the work necessary to deliver/install the new industrial, commercial washer/dryer equipment for B346.
(a) Contractor shall provide all labor, materials, equipment, transportation and services required to accomplish all work related to installing equipment to manufactures specifications.
II. Project Description
The contractor shall provide and install each industrial washer/dryer equipment for B346, Hill Air Force Base for laundry facility.
a. Work schedule:
o Contractor will schedule work with the dorm management office 30 days prior to start of installing equipment.
o Contractor shall use all precautions in installing equipment in facility as to not damaging door jambs, walls, flooring, electrical panels/outlets or any other equipment.
o Contractor will remove all packing material from washer/dryer equipment including support boards underneath, any taping and dispose of all materials into a disposal container provided by contractor on site with prior approval from Procurement Contracting office (PK).
o Contractor will make sure all equipment is set up, balance, and operational while ensuring each washer and dryer meets specs provided/listed in Quantities, item IV.
o Contractor will only use visitor’s restroom located in B341 on first floor dayroom and no other location around campus.
o Contractor will check in and out with dorm management personnel in addition to providing a daily progress report on finished installation of machine(s).
o Contractor shall perform work during 0730-1530, Mon - Fri.
(with exception of holidays) o All clean up of grounds and bldg areas to be completed by o 1530 hrs each work day.
o Contractor will be prohibited from using dayroom/kitchen areas of dorm campus facilities.
III. Site Walk
A site walk of the building is highly encouraged for all bidders. The exact date and time shall be announced.
IV. Standard Equipment Descriptions
The contractor shall prepare their bid based on the following quantities in the base bid items as given below:
Bid items for New Equipment
a. Standard for Industrial Washer shall consist of: Two o 30lb (or comparable) industrial/commercial grade washers o 35”x49”x58” o Hard-wired electricity o Floor bolted/secured
b. Standard for Dryer shall consist of: Two o 50lb (or comparable) industrial/commercial grade dryers o 35”x50”x72” o Hard-wired electricity o Floor bolted/secured o Gas powered
V. Period of Performance
The contractor shall perform the installation of equipment within 90 calendar days after delivery of contract. Contractor will be responsible to store equipment not subject to outside elements/in secured trailer at contractor expense during work performance if necessary. All work shall be coordinated with Hill Air Force Base POC: Merry Stowell or MSgt Krizek, 777-3029, before actual work begins or deliveries are made to the site.
VI. Warranty
Provide a minimum 3/5 year warranty for parts & service on each product furnished.