STATEMENT OF WORK

FOR

BOILER SAFETIES (6) EA.

AT

EIELSON AIR FORCE BASE, ALASKA

Project:

Provide Six Boiler Safety Relief Valves Preset to Specified Settings

At Eielson AFB Central Heat and Power Plant

3 Nov. 2011

1.0 INTRODUCTION

Eielson AFB (EAFB) operates five turbine generators capable of generating twenty five mega watts of electricity at its Central Heat and Power Plant (CH&PP) facility.

This statement of work (SOW) defines the work to provide Six Boiler Safety Relief Valves Preset to Specified Settings.

2.0 LOCATION

EAFB is located approximately 23 miles southeast of Fairbanks, Alaska. The Central Heat and Power Plant is located in Building 6203. This facility is accessible from Arctic Avenue and is contained within the secured portion of the base.

3.0 INSTRUCTIONS TO THE CONTRACTOR – Provide six Boiler Safety Relief Valves as specified below.

4.0 PROJECT OBJECTIVES- The objective of this work is to manufacture to OEM specifications and provide six safety relief valves. The valves are to include (2) Crosby HAS-36 ser.# 28945 code V set at 425 psig. Size and orfice 2H3, capacity 13,910 pph. and (2) Crosby HS-35 ser# 28381 code V set at 450 psig. Size and orfice 3K4, capacity 39,565 pph. and (2) Crosby HS-35 ser# 28381 code V set at 455 psig. Size and orfice 3K4, capacity 39,958 pph.

5.0 DESCRIPTION OF WORK- Provide above named safety relief valves and ship to CH&PP 2676 Indrustrial Ave., Eielson AFB, Alaska. 99702