The document provided is a Performance Work Statement (PWS) for a contract to provide propane to Building 1348 at Eielson AFB, Alaska.
The key details are:
- This is a non-personal service contract to acquire and deliver up to 10,000 gallons of propane to support the Maintenance Squadron (MXS) at Eielson AFB.
- The objective is to provide propane and fill propane tanks located on Eielson AFB at Building 1348 and the Fire Training Ground.
- The work will be performed at Eielson AFB, with performance evaluated under a Quality Assurance Surveillance Plan.
- The government will award a contract to meet this requirement, as indicated by the related pre-solicitation for "MXS Propane" issued by the 354th Contracting Squadron at Eielson AFB.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AUG 22
Performance Work Statement (Includes associated Performance Requirements Summary (PRS)
PERFORMANCE WORK STATEMENT (PWS)
MXS Propane
11/14/2024
Part 1 General Information
1. General: This is a non-personal service(s) contract under which the personnel rendering the service(s) are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees.
1.1 Description of Services/Introduction: This is a non-personal service(s) contract to provide propane to Building 1348 Eielson AFB 99702
1.2 Background: The purchase of propane in the product description is to support the continued operation of the Maintenance Squadron (MXS). Previously, similar requirements have been purchased via Blanket Purchase Agreement (BPA). Previous BPA has reached the end of its life cycle.
1.3 Scope: The Contractor shall provide non-personal service(s). The contractor shall acquire and deliver Propane to Eielson AFB as required up to 10k gallons..
1.4 Objectives: The objective of this contract is to provide propane and fill propane tanks located on Eielson AFB. The contractor will source propane, provide transport and fill storage tanks on Eielson AFB at Building 1348 for a total of 10k Gallons.
1.5 General Information:
1.5.1 Reserved
1.5.2 Quality Assurance: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).
1.5.3 Recognized Holidays: The following provides information on recognized holidays for the purpose of the PWS. If submittal of any documentation (e.g. deliverables, submittals, etc.)
deadlines fall on a holiday, the closest work day prior to the holiday will apply as the deadline for submittal.
WAYFIELD, LAURA J CIV USAF PACAF 354 CONS/PKB
Title�
WAYFIELD, LAURA J CIV USAF PACAF 354 CONS/PKB
These are two locations maybe we should add other locations could shall be stated on the Blanket Purchase Agreement Call�
1.5.3.1 U.S. Holidays: Work shall be performed on U.S. federally recognized holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer.
When a U.S. holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively.
New Year’s Day January 1st M. L. King Memorial Day 3rd Monday in Jan Presidents Day 3rd Monday in February Memorial Day last Monday in May Juneteenth June 19th Independence Day July 4th Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veteran’s Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th
1.5.4 Operating Hours: The Government facility office hours, facility operating hours, and the Contractor support hour requirements often coincide, however, they may differ. Please refer to the following.
1.5.4.1 Government Facility Office Hours: The Government facility office hours are 0700 to 2300, and days Monday through Friday 0730-1630 except U.S. Holidays identified in paragraph 1.5.3.1 above or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.
1.5.4.2 Government Facility Operating Hours: The Government facility operating hours occur between the hours of 0700 to 2300, and days Monday through Friday (Insert the hours (e.g. 0600 to 1800), days (e.g. Monday through Saturday)). The Government facility is closed for operations during the recognized U.S. Holidays identified in paragraph 1.6.3.1 above. The Government facility may close due to local or national emergencies, administrative closings, or similar Government directed facility closings and will be communicated by the Contracting Officer to the Contractor.
1.5.5 Reserved
1.5.6 Place of Performance: The work to be performed under this contract will be performed at Eielson AFB, BLDG 1348 Corrosion Control and 4324 Fire Training Ground.
1.6 Security Requirements: The following information is provided on security related matters.
1.6.3 Installation Access: Access to U.S. installations, buildings and controlled areas is limited to personnel who meet security criteria and are authorized Failure to submit required information/data and obtain required documentation or clearances will be grounds for denying access to U.S. installations, buildings and controlled areas. The Contractor shall ensure that any subcontractors used in performance of this contract complies with these requirements and that all employees, of both the Contractor and any subcontractor utilized by the Contractor, are made aware of and comply with these requirements.
The Contractor shall be aware of and comply with the requirements associated with Installation Access Control. The Government is not liable for any costs associated with performance delays due solely to a firm’s failure to comply with Installation Access Control System (IACS) processing requirements.
The Contractor shall return installation passes to the issuing IACS office when the contract is completed or when a Contractor employee no longer requires access.
1.6.6 Operations Security (OPSEC) Requirements: Contractor personnel shall adhere to facility security policies and restrictions. The Contractor shall immediately report suspicious activities to security personnel.
1.7 Reserved
1.8 Reserved
1.9 Reserved
1.10 Reserved
1.11 Reserved
1.12 Reserved
1.13 Reserved
1.14 Reserved
1.15 Reserved
1.16 Reserved
1.17 Reserved
1.18 Reserved
1.19 Reserved
1.20 Reserved
1.21 Reserved
1.22 Reserved
1.23 Reserved
1.24 Reserved
1.25 Reserved
1.26 Reserved
1.27 Reserved
1.28 Reserved
Part 2 Reserved Part 3 Reserved Part 4 Reserved
PART 5
SPECIFIC TASKS
5.1 Basic Services: The Contractor shall provide propane for Bldg 1348 Corrosion prevention and Bldg 4324 Fire Training Ground upon request.The contractor shall acquire and deliver requested amount of propane in Gallons.
PART 6
APPLICABLE PUBLICATIONS
6. Applicable Publications (Current Editions): The following publications, manuals, regulations, etc. are mentioned in this PWS and are listed below.
6.1.1 Department Of Defense Contract Security Classification Specification (DD Form 254)
6.1.2 Department of Defense Security Agreement (DD Form 441)
6.1.3 National Industrial Security Program Operating Manual (DoD 5220.22-M)
6.1.4 Installation Access Control (AE Reg 190-16)
6.1.5 The Army Physical Security Program (AR 190-13)
6.1.6 Contractor Identification (AE Reg 27-715)
6.1.7 U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1)
6.1.8 Information Assurance Workforce Improvement Program (DoD 8570-M)
6.1.9 Information Assurance Training Certification and Workforce Management Directive (DoDD 8570.01)
6.1.10 Information Assurance (AR 25-2)
6.1.11 Electromagnetic Compatibility Directive (2004/108/EC)
6.1.12 Policies and Procedures for Property Accountability (AR 735-5)