Question_Answers_Soil_Limerock.docx
DOCX document 17 KB Posted
- Attached to
- Soil/Limerock Sub Base
- Solicitation number
- F1T2AH4155A002
About this file
Questions and Answers 20 Aug 14
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Material_Analysis.pdf | ||
| 1_-_PKO_Memorandum_Letter_rev.doc | DOC document | |
| Bid_Schedule_(Soil-Limerock).xlsx | XLSX spreadsheet | |
| 2_-_Affidavit_9_Jul_2013.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions/Answers to Solicitation F1T2AH4155A002
1. In section 15 of the statement of work it states: "All material delivered must meet specifications provided, and will be inspected by 796 personnel." What are the specifications for the soil/limerock?
Answer: See attachment 4, Material Analysis Sheet
2. In the "Delivery Schedule" section it states: "Same-day delivery is required." Does this mean within 24 hours or the same working day that the call is received?
Answer: Delivery of materials will be required the same working day the request is made.
3. Under section 5 of the statement of work it states: The contractor shall provide physical security for the materials and work under his control. Does material and work return to government control for physical security once it is delivered?
Answer: Once the material is delivered to the specified site, the Government will assume ownership of the material.
4. Is this a follow-on contract opportunity? No
5. If so, A. What is the current contract number and what is the previous solicitation number?
Answer: N/A
B. What was the base award amount?
Answer: N/A
6. How did you come up with the estimated quantity? Is this base on a monthly past allocation 12,000 plus tons or a past year daily requirement of 600 plus tons or how?
Answer: Customer will have a kick-off meeting with awardee to discuss delivery requirements.
7. If this is not a follow-on requirement, can you cite the last time you purchased this product (including delivery) and what that contract number and solicitation number were?
Answer: N/A
8. Can you please plot all 4 locations on a map OR provide GPS coordinates for each location OR provide distance from each point to the entry gate?
Answer:
a. Duke Field - RR-213 West (start point) Lat 30.636/ Lon -86.561 . (end point) Lat 30.550 / Lon -86.901
b. RR-234 (Start point) Lat 30.553 / Lon -86.758. (End Point ) Lat 30.487 / Lon -86.624
c. Duke Field - RR 213 East (Starting Point) Lat 30.640 / -86.546 (End point) Lat 30.662 / Lon -86.389
d. RR-211 West (Starting point) Lat 30.677 / Lon -86.644 (End point) Lat 30.631 / Lon -86.735
9. If/when submitting a bid via SF1449, other than the information required on the SF1449 for Offeror, what does your agency require to be completed (i.e.: solicitation number, offer due date/time, solicitation contact information, issuing contractor, etc..)
Answer: Per combined Synopsis/Solicitation
1. DUNS/Cage Code
2. Description off delivery Terms and any charges for shipping
3. Representation and Certification
4. Bid Schedule
5. Responses should include POC, name, position, telephone , and email
6. If applicable, request base access memo and affidavit
10. If awarded the contract, who decides terms of payment? How often is invoicing allowed?
Answer: A. Contracting Officer’s discretion B. Monthly invoicing is preferred.
11. If subcontracting, is a company automatically qualified for Fast Pay? If not, how would one become qualified?
Answer: No, the awardee may not automatically qualify. As prescribed, IAW FAR subpart 13.4.