RECOVERY ACT - AIB Phase I Demolition & Hazmat Removal
Solicitation number
F09SOL00035
Issued by

About this file

Questions and Responses

View the file

Other files

File Type Posted
F09SOL00035, Amendment No. One.pdf PDF
F09SOL00035,AIB HAZMAT.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

F09SOL00035

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

OCON

Washington DC 20013-7012

MRC 1200

P.O. BOX 37012

SMITHSONIAN INSTITUTION

OFEO# 091510305/28/2009000002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/07/2009

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The Solicitation Number cited in block 9A above, for the Phase 1 Demolition and HazMat

Removal at the Smithsonian Instituiton's Arts and Industries Building, located in

Washington, DC, is amended as follows:

A.1. Provided herein are responses to questions posed by the prospective offerors.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Robert Fraga

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

1. Question: Sheet G101.0 provided for “reference only” indicated that all remaining terrazzo is to be repaired & refinished, is this work to be included in this contract scope?

Answer: Repairs to the terrazzo flooring are not required.

2. Question: Verify that reimbursement to SI for off hours work does not apply to off hours work proposed in contractor’s baseline schedule.

Answer: Any off-hours work proposed in General Contractor’s bid schedule will not require SI reimbursement.

3. Question: Can the entire project be scheduled for off hours? If so, would there be any reimbursement to SI required for security & inspection services?

Answer: Yes, the entire project can be done on off-hours. The Contractor is required to show this in their bid schedule and provide an explanation why this is the best course of action to complete this project. This should be included in the Plan of Accomplishment required in the Solicitation.

4. Question: Clarify the extent of demolition required; what is the extent of the demolition work at the building perimeter walls & windows. These items are drawn using the legend symbol for “existing elements and partitions to be removed”.

Answer: Remove all wall finishes adjacent to or applied to historic finishes as identified in documents. Exterior windows are not to be removed.

5. Question: How is the demolition of the walls abutting “historic masonry construction” to be performed without damage to these features?

Answer: Any materials to be removed that are adjacent to or attached to existing ‘historic masonry walls’ or other ‘historic fabric’ shall be removed so as to do the least amount of damage possible to the historic fabric.

6. Question: Clarify the extent of demolition required at the East & West Towers. These items are drawn using the legend symbol for “existing elements and partitions to be removed”. Key Note #1 indicates that temporary doors are to be installed, does this included construction of temporary walls similar to those required by Key Note #7?

Answer: There is no demolition scheduled for the East and West Towers. The temporary doorway designated in the East Tower is the only exception. The guidelines for the temporary door are as follows:

• Temporary doors and walls to be wood products per the specifications. Width and height of doors shall be sized to accommodate demolition equipment but the pair shall not be less than 6 feet wide and 8 feet high.

• WALL: ½” FRT plywood (interior side of wall), FRT wood studs, R-19 batt insulation and 5/8” FRT T&G plywood on the exterior face. Seal all joints and paint all surfaces.

• DOORS: Assembly similar to wall. Provide exterior lockset and deadbolt (thumb turn on interior) on the active leaf with ADA compliant lever. Include flush bolts at the top and bottom edges of the inactive leaf. Key per SI standards.

7. Question: Is there any fire rating requirement for the EPS insulation? Provide ASTM specification & density requirement for this material.

Answer: The EPS insulation cannot be left exposed after installation, it must be covered 100% by FRT plywood. Refer to Volume 1 of 2 Specification Section 01760 2.1 A. 1. for ASTM information as it relates to the EPS insulation.

8. Question: What is the contractor’s extent & responsibility for pest control?

Answer: Contractor’s extent shall be to enforce construction management techniques to deter pests.

9. Question: Can we obtain a copy of the Hazardous Materials Report referenced in specification Section 01732 – Selective Demolition, paragraph 1.1B?

Answer: Refer to the Volume 2 of 2 drawings and specifications for Hazardous Materials Report.

10. Question: Verify that all heat, light & power to be provided by SI at no cost to the contractor including off hours work indicated in their original schedule & for any additional off hours requested thereafter.

Answer: SI will provide heat, light and power at no additional cost to contractor.

11. Question: Is all the protection to be removed or to remain after completion of demolition & hazmat removal?

Answer: Protection to remain in place after completion of project.

12. Question: Is all the protection Type E indicated as “temporary” to be removed after completion of demolition & hazmat removal?

Answer: Protection to remain in place after completion of project.

13. Question: Provide specification for temporary doors, frames & hardware.

Answer: Provide a 1 ¾ inch thick, solid core flush wood door with 1 ½ pair heavy duty hinges and a privacy set in a 16 gauge knock down metal frame. Provide ADA compliant lever handle and key to SI standards. Paint door and wall. Refer to question #6 for additional information.

14. Question: Sheet AD501.0 indicates a height of 4’-0” & 610 mm, which is correct?

Answer: 4’-0”/1220 mm is the correct dimension.

15. Question: Confirm height of protection Type C, on the elevations they appear to be the same height as Type D.

Answer: 1220 mm is the dimension to use.

16. Question: Can you provide the heights required for protection Type E at the columns where the protection is shown partial height?

Answer: The height of Type E protection is intended to be at least 18 inches above the height of adjacent equipment/construction being removed. The minimum height shall be 8’-0”.

17. Question: Demolition options 4 & 5 and 6 & 7 have areas of overlap both of which appear to include removal of the same walls. How are we to account for this in our option pricing?

Answer: These areas do not overlap. The limits of the option areas are defined by the structural walls that outline these areas. For example, the NW court’s four walls are on column lines 6, 11, K and F. Price the side of the wall facing the space. The pricing for the opposite face of the wall is to be included in the adjacent area/option.

18. Question: Is there any requirement for restoration of adjacent finishes after demolition of abutting elements?

Answer: No.

19. Question: Sheet AD 101.0 Key Note #7 indicates a partition is to be installed adjacent to Room 1282A Office/SMAG. Why is this partition necessary since this area is to be demolished under Option #5?

Answer: Provide door/partition in base bid and credit for door/partition in Option 5.

20. Question: Does the General Requirements paragraph 14.7 pertain to this project since all the work is confined to unoccupied space?

Answer: Paragraph 14.7 in the General Requirements does not stipulate whether or not the building is occupied. The temporary protection plan has taken into consideration pathways in and out of the building. If the Contractor’s plan will require an unidentified area containing exposed historic flooring to be accessed, this specification section would be applicable.

21. Question: Is Section 01524 paragraph 1.3A regarding the salvage/recycling percentage relevant to this contract?

Answer: This project and all its phases in their entirety will seek LEED certification for this building.

All items salvaged or recycled will need to be recorded for LEED credits. Contractor should salvage and recycle as much non-hazardous materials as possible.

22. Question: Since the subcontractor’s walk through is not scheduled until after the deadline given for questions will additional time be given to ask additional questions?

Answer: No additional time will be given since two walk-throughs have been held prior to the question deadline.

23. Question: Specification Volume 2 of 2 has pages 1-163, but there is no page 155. Please confirm that Page 155 is not used.

Answer: There was a printing error and Page 155 was not used.

24. Question: Drawing G101.0, flag notes indicate repair and refinish existing terrazzo floor. The drawing also has a footnote that “This Drawing is Provided for Contractor’s Reference Only.” Please confirm that there is no terrazzo repairs or refinishing for this solicitation.

Answer: Repairs for the terrazzo are not required for this project.

25. Question: Specification volume 2 of 2, spec. 01000-1, part 12.1.2 states that removal of demolition and construction debris is from 6:30 pm to 9:30 am. Spec. sec. 01000-1, part 27.3 and others states that the hours are from 6:30 pm to 6:30 am. Please confirm that the hours for removal of hazmat or construction debris is from 6:30 pm to 6:30 am and not till 9:30 am.

Answer: The timeframe will be from 6 p.m. to 6 a.m. for the removal of all debris types as noted in Volume 1 of 2, specification section 12.1.

26. Question: Drawings AD 101 thru 104 and AD 301-302, note 6 ask for a per fixture cost for temporary lighting. Are we to provide only a per fixture price or provide temporary lighting per the parameters noted in note 6 and also provide a Unit Price for additional fixtures and would this be considered Unit Price #10.

Answer: Provide only a unit cost. All Contractors shall provide an Item J. unit price either typed or hand written and submitted with bid along with items A through I.

27. Question: Because of the obnoxious fumes and hazardous sewer gases we were unable to view the existing toilet rooms to get a fixture count. Could the SI please issue a count of water closets, lavatories and urinals that require demolition and or removal for the base bid?

Answer: There are no fixtures being removed in the base bid. Included are the counts for the fixtures in the Options.

• Southwest Annex:

a. Men’s Restrooms First Floor: 5 Toilets, 5 Urinals and 4 Sinks

b. Women’s Restroom First Floor: 7 Toilets and 6 Sinks

c. Men’s Restrooms Second Floor: 5 Toilets, 5 Urinals and 4 Sinks

d. Women’s Restroom Second Floor: 7 Toilets and 6 Sinks

• Southeast Pavilion:

e. Men’s Restrooms First Floor: 6 Toilets, 4 Urinals and 4 Sinks

f. Women’s Restroom First Floor: 6 Toilets and 5 Sinks

28. Question: Please clarify the note on Plan G101.0 “Original Galleries That Remain Are Terrazzo (40% Verified at This Time). Repair and Refinish All. This Area is indicated by the Diagonal Hatch.

1. There are two different types of diagonal hatch marks. Which diagonal hatch mark is applicable, the single line or the double line diagonal hatch marks.

2. Please identify the limits of the terrazzo work and a more detailed scope of work required.

3. If the single diagonal hatch marks applies, which is the four tower entrances foyers, the floor are cover with carpet and the condition of the terrazzo cannot be observed.

Answer: There is no terrazzo repair or re-finishing in the Phase I Demolition and HazMat Removal project.

29. Question: Please identify on the plans where the SE Annex toilet rooms are located and how manyfixtures are in the toilet rooms. Note: This area was not identified at either walk through survey.

Answer: Southeast Annex toilet rooms are shown on drawing DA 1.00.0 and are tagged #1.

Additionally, the area where the restrooms are located is labeled in the Southeast Pavilion. Refer to question # 27 for fixture counts.

30. Question: On Drawing DA1.00.0 Demolition Options Scope of Work, refer to specific items to be removed such as Drywall from existing partitions. Is all the drywall to be removed and is it considered to be hazardous materials. The problem is that the Volume #2 drawings do not match Volume #1 drawings.

1. Shall we assume that all partitions with drywall contain Asbestos and remove all drywall from all partitions?

2. There appears to be more partitions shown on Volume #1 drawings than there are on Volume #2 drawings. Which Drawing should we use?

Answer: Demolition Options Scope of Work: Refer to volume 2 for hazmat quantities and volume 1 for demolition quantities.

1. Material composition should be based on the Volume 2 of 2 Drawing’s Hazardous Material Inventory Table.

2. Refer to Volume 1 of 2 drawings for partition layouts.

31. Question: Is it the intent of the scope of work to remove and haul away all condensing water piping from the chillers, condensing water pumps and cooling tower? Also is it the intent to remove the refrigerant purge line in its entirety.

Answer: Yes.

32. Question: Note #13 on drawing #MD 4- 01.0 states “Relocate Chill Water Flow Meter”. Where do we relocate the flow meter too?

Answer: Regarding the Note 13 on drawing MD 4-01.1, the existing sensor is located on the exterior of the south wall of room 1435A, which is designated for demolition. The sensor should be relocated and mounted at the wall location where the keynote tag is shown on the drawings. The new wall location is along column line 10, and column line I. This location should be coordinated in field with the COTR.

33. Question: Are there any high-lighted drawings indicating the exact areas of Hazardous Material abatement for Base Bid & Options 1 through 7?

Answer: Volume 2 of 2 drawings indicates location of hazardous materials.

34. Question: Is there a detailed scope of work for the Asbestos Abatement that outlines where ceilings areto remain and were walls are only to be removed up to the drop ceilings?

Answer: No ceilings are being removed. All drywall should be removed to underside of drop ceiling.

35. Question: In regards to Questions #1 & #2: Should me utilize the Hazardous Material Inventory Table dated May 2009 as the outline for the scope of work with the assigned locations, material types and quantities? At least 2 full days of site investigation would be required to determine, if the quantities are accurate.

Answer: Yes, the documents provided should be used. The quantities have been verified in field and documented in the materials provided. Refer to question #30 for additional information.

Except as provided herein, all other terms, provisions and conditions of the Solicitation remain unchanged.

END OF AMENDMENT NO. TWO