This document consists of Contract Data Requirements Lists (CDRLs) related to a federal contract opportunity for Performance Oriented Packaging (POP) Boxes for the Guided Multiple Launch Rocket System (GMLRS) and Low-Cost Reduced Range Practice Rocket (LCRRPR).
The key details are:
- The contract opportunity is solicitation W31P4Q-24-R-0025 for manufacturing two configurations of POP Boxes, with a total maximum quantity of 6,004 boxes over one year.
- Required deliverables include a POP Box Qualification Test Plan, POP Box Test Report, and Quality Program Plan (QPP). First Article Inspection (FAI) and Production Line Validation (PLV) with government participation will be required.
- Delivery location is Letterkenny Munitions Center in Camden, Arkansas, with anticipated weekly deliveries up to 288 boxes per week.
- The acquisition will be a Firm-Fixed-Price contract awarded to a Small Business or Service-Disabled Veteran-Owned Small Business on a Lowest Price Technically Acceptable basis.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A NDTI
Performance Oriented Packaging Boxes W31P4Q-24-R-0025
A001 Test Plan POP Box Test Plan
DI-NDTI-80566 A SOW Para 3.5 SFAE-MSL-STE
LT
A See 16 See BLK 16
N/A
See BLK 16
See BLK 16
SFAE-MSL-STE 0 1 0
Block 9:
(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by
STORM CM.
Date of determination shall be determined by the contractor.
Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.
(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:
WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.
Blocks 8, 10, 12 and 13: The contractor shall submit 30 days prior to the start of the M26 Performance Oriented Packaging (POP) Testing. The Government will provide approval/disapproval 10 days after receipt. If disapproved, the contractor shall resubmit 5 days after receipt of Government disapproval. Subsequent submissions as required.
Block 14: Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.storm-pdm@army.mil. The data item shall be delivered in one or more of the MS Office document or searchable PDF format.
0 1 0
1 4 14 Feb 202414 Feb 2024
A SESS
A002 Request for Variance (RFV)
DI-SESS-80640 E SOW Para 3.9 SFAE-MSL-STE
LT
A
See 16 See BLK 16
N/A
See BLK 16
See BLK 16
SFAE-MSL-STE 0 1 0
Block 9:
(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM
CM.
Date of determination shall be determined by the contractor.
Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.
(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:
WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.
Blocks 8, 10, 12 and 13: The contractor shall submit RFV as generated for approval. The Government will provide approval/disapproval 15 days after receipt. If disapproved, the contractor shall resubmit 5 days after receipt of Government disapproval. Subsequent submissions as required.
Block 14: Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.storm-pdm@army.mil. The data item shall be delivered in one or more of the MS Office document or searchable PDF format.
2 4
A PACK
A003 Performance Oriented Packaging (POP) Test Report
DI-PACK-81059 C SOW Paras 3.6; 3.7 SFAE-MSL-STL
LT
A
See 16 See BLK 16
N/A
See BLK 16
See BLK 16
SFAE-MSL-STE 0 1 0
Block 9:
(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM
CM.
Date of determination shall be determined by the contractor.
Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.
(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:
WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.
Block 8: Government will provide approval/disapproval within 45 days after receipt. Approval shall be dependent upon evaluation that requirements cited in the DID and SOW have been met; and document is complete. SPIs created within the Test Report will be approved/signed by the Government; and incorporated into the final delivery of the POP Test Report. If disapproved, the contractor shall provide required information; and resubmit NLT 15 days after receipt of Government disapproval. The same approval cycle applies.
Blocks 10, 12 and 13: The contractor shall deliver NLT 14 days after completion of POP Certification Testing.
Block 14: Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.storm-pdm@army.mil. The data item shall be delivered in one or more of the MS Office document or searchable PDF format.
3 4
A QCIC
A004 Quality Program Plan (QPP)
DI-QCIC-81722 SOW Para 3.3 SFAE-MSL-STE
LT
N/A
See 16
ASREQ
N/A
30 DAC
ASREQ
SFAE-MSL-STE 0 1 0
Block 9:
(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM
CM.
Date of determination shall be determined by the contractor.
Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.
(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:
WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.
Block 10 and 13: The contractor shall resubmit plan if revisions are made by the contractor.
Block 14: Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.storm-pdm@army.mil. The data item shall be delivered in one or more of the MS Office document or searchable PDF format.
4 4
CDRL CONTINUATION SHEET
1.0 Data Item Delivery Instructions
1.1 Data Item Delivery. Delivery of electronic documents shall be accomplished by uploading the required data items and Meta Data into STORM Net, https://mis.msl.army.mil/storm/. If STORM Net is unavailable the contractor shall submit required data items on a CD-ROM and notifying the STORM Data Manager via email (usarmy.redstone.peo-ms.mbx.pf-pdm@army.mil) that the document has been submitted per the contract requirements (CDRL). A data item shall be considered delivered as of the date that the document is received and/or the Transmittal of Delivery (TOD) is signed by the requiring office. Incomplete or incorrect data items shall be corrected by the contractor and resubmitted. The date received of the corrected data item will be recorded as the final date of delivery.
1.2 Alternative Data Item Delivery Methods. When a CDRL data item is due, the contractor shall notify the Government STORM Data Manager via email if there is a delivery problem. A mutually agreed to, or Government selected, alternative method of delivery to satisfy the delivery requirement will be established.
1.2.1 The use of alternative delivery methods IAW the above paragraphs shall not constitute a change to the contract and shall not be the basis of any equitable adjustment.
1.3 Meta Data Requirements. Meta data shall accompany all electronic documents delivered to the Government. The minimum required meta data include: Contract Name, Sequence Number, Contractor Name, Notice of Availability (NOA) Number, NOA Date, Return to Contractor Date, Approval Required, Draft, Document Title, Document Number, Document Revision, and Document Date.
2.0 STORM Net Access. The contractor shall request access to STORM Net through https://accountrequest.msl.army.mil/. The contractor shall have an Army Knowledge Online (AKO) email account, Public Key Infrastructure (PKI) Certificate and Visit Authorization Request on file with the STORM Security Office.
3.0 Classified Data. The contractor shall deliver classified data IAW DoD 5220.22-M on Compact Disk to:
OUTER PACKAGE:
Strategic and Operational Rockets and Missiles Attn: SFAE-MSL-STS 100 Secured Gateway Huntsville, AL 35808
INNER PACKAGE:
Strategic and Operational Rockets and Missiles Attn: SFAE-MSL-STS (POC'S NAME) 100 Secured Gateway Huntsville, AL 35808
The Transmittal of Data (TOD) shall be delivered electronically through STORM Net for all classified documentation.
https://accountrequest.msl.army.mil/
| CDRL Continuation Sheet 23 November 2021 STORM Net.pdf |
| CDRL CONTINUATION SHEET |
| 1.2.1 The use of alternative delivery methods IAW the above paragraphs shall not constitute a change to the contract and shall not be the basis of any equitable adjustment. |
| 2024-02-14T13:10:36-0600 | |
| LANIER-PARKER.ANDREA.DELENE.1230677570 |
| 2024-02-14T13:16:05-0600 | |
| SANDERS.HEATHER.MARIE.1272930933 |
File details come from the government source that posted it. Updated .