Exhibits A_B_C_ Knox DAGIR CDRLs.pdf

PDF 781 KB Posted

Attached to
Fort Knox, KY Digital Air-Ground Integration Range (DAGIR) Fielding
Solicitation number
W900KK-22-R-0018-02
Issued by

About this file

This draft request for proposal from the U.S. Army seeks to install an additional Digital Air Ground Integration Range at Fort Knox, Kentucky. Key features to be provided include IT equipment utilizing the Digital Range Training System Live Training Transformation software, an After Action Review system, vehicle and dismounted player units, and a radio communication system. The anticipated award date is the fourth quarter of fiscal year 2022. Questions regarding the draft RFP are due by May 6, 2022.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SFAE-STRI-PMST-LTS

6. REQUIRING OFFICE

SOW PARA 3.2

5. CONTRACT REFERENCE

DI-MGMT-81928

4. AUTHORITY (Data Acquisition Document No.)

3. SUBTITLE

CPSMR

CONTRACTORS PROGRESS AND STATUS REPORT

2. TITLE OF THE DATA ITEM

A001

1. DATA ITEM NO.

F. CONTRACTOR

W900KK-22-D-XXXX Knox

E. CONTRACT/PR NO.

DRTS

D. SYSTEM/ITEM

TDP

C. CATEGORY

TM OTHER MGMT

B. EXHIBIT

A. CONTRACT LINE ITEM NO.

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Form Approved OMB No. 0704-0188

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

N/A

8. APP CODE

DD

7. DD 250 REQ

D

9. DIST STATEMENT

REQUIRED

13. DATE OF SUBSEQUENT

SUBMISSION

See block 16

11. AS OF DATE

12. DATE OF FIRST

MNTHLY

10. FREQUENCY

Repro Reg

Final

Draft

b. COPIES

a. ADDRESSEE

14. DISTRIBUTION

08-DEC-2021

J. DATE

Todd, James

I. APPROVED BY

29-SEP-2021

H. DATE

G. PREPARED BY

Steib, Nicole

1. BLOCK 7: THE CONTRACTOR SHALL INITIATE A ZERO COST RECEIVING

REPORT IN WIDE AREA WORKFLOW (WAWF) TO THE TECHNICAL OFFICE

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

3. BLOCK 12: SHALL BE DUE 15 CALENDAR DAYS AFTER THE END OF THE

CONTRACTORS SECOND FULL ACCOUNTING MONTH FOLLOWING AWARD.

4. BLOCK 13: SHALL BE DUE 15 CALENDAR DAYS AFTER THE END OF THE

CONTRACTOR'S ACCOUNTING MONTH THROUGH THE LIFE OF THE CONTRACT.

5. THE GOVERNMENT WILL HAVE 10 CALENDAR DAYS TO ACCEPT/REJECT EACH

SUBMISSION.

6. THE CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO RESPOND TO THE

GOVERNMENT'S COMMENTS AND RESUBMIT.

16. REMARKS

1 DRTS APM

1 0 0 15. TOTAL

18. ESTIMATED

TOTAL PRICE

17. PRICE GROUP

Page 1 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.2.3

DI-MGMT-81861A

Integrated Program Management Report (IPMR)

A002

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

MNTHLY

01-OCT-2021

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

3. BLOCK 12: SHALL BE DUE 15 CALENDAR DAYS AFTER THE END OF THE

CONTRACTORS SECOND FULL ACCOUNTING MONTH FOLLOWING AWARD.

4. BLOCK 13: SHALL BE DUE 15 CALENDAR DAYS AFTER THE END OF THE

CONTRACTOR'S ACCOUNTING MONTH THROUGH THE LIFE OF THE CONTRACT.

5. THE GOVERNMENT SHALL HAVE 10 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION OF THE SUBMISSION.

6. THE CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

7. CONTRACTOR FORMAT IS ACCEPTABLE.

8. THE SCHEDULE SHALL INCLUDE, AT A MINIMUM, THE FOLLOWING MILESTONES:

- COMPLETION OF MATERIAL ORDERING

- MATERIALS RECEIVED

- START OF IN-HOUSE ASSEMBLY

- START OF ON-SITE INTEGRATION

- COMPLETION OF INSTALLATION

- TEST READINESS REVIEW

- START OF SYSTEM OPERATIONAL TEST

- NEW EQUIPMENT TRAINING

- COMPLETION OF TRANSITION PERIOD

- COMPLETION OF DOCUMENTATION

- PERIOD OF PERFORMANCE

9. TAILOR DI-MGMT-81861A AS FOLLOWS: CONTENT SHALL BE IN ACCORDANCE

WITH FORMAT 6.

1 0 0 15. TOTAL

Page 2 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.2.4

DI-FACR-80966

Site Survey Report

Trainer Facilities Report (TFR)

A003

TM OTHER FACR

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

SEE BLOCK 16

1TIME/R

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D. DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 13 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

3. BLOCK 12: SHALL BE DUE 15 CALENDAR DAYS AFTER THE COMPLETION OF

EACH SITE SURVEY.

4. BLOCK 13: REVISIONS, AS REQUIRED, THROUGH THE LIFE OF THE CONTRACT.

5. THE GOVERNMENT SHALL HAVE 14 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION OF EACH TFR SUBMISSION.

6. THE CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

7. CONTRACTOR FORMAT IS ACCEPTABLE.

8. TAILOR DID TO INCLUDE THE FOLLOWING CONTENT:

A. Title page. The title page shall contain the following information:

I) Title.

II) Contract data requirements list (CDRL) data item number.

III) Site name.

IV) Identification of project.

V) Contract number.

VI) Date.

B. Table of Contents. The Table of Contents shall identify all paragraphs and the corresponding page number.

C. Introduction. The Introduction shall contain the following information:

I) Purpose.

II) Location.

III) Dates of survey.

IV) Personnel in attendance.

D. Results. The Results section shall be the main body of the report. It shall

1 DRTS LOG

1 DRTS LEAD ENG

3 0 0 15. TOTAL See continuation sheet...

Page 3 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

16. REMARKS (Continued) include a summary of all anticipated minor construction required, document any required changes to the system baseline, and document any findings with regards to cabling, power connections, target pit preparations, and any other tasks required to support the transition of the range into the final configuration. This section shall fully document and explain any other findings concerning on-site conditions.

E. Conclusions and recommendations. This section shall summarize the results of the survey and present conclusions. The conclusion shall also identify any discrepancies between the contract and survey results. This section shall contain any recommendations that contractor has based on the survey. Any actions required from the Government by the contractor shall be noted here.

TM OTHER FACR

Page 4 of 35 Pages DD FORM 1423-1, FEB 2001

SOW PARA 3.2.8

DI-SESS-80640D

Request for Variance (RFV)

A004

TM OTHER SESS

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

A

ASREQ

REPORT IN WIDE AREA WORKFLOW (WAWF) IMMEDIATELY AFTER SUBMITTING

THE DATA IN ACCORDANCE WITH BLOCK 14. A WAWF RECEIVING REPORT IS

REQUIRED FOR EVERY DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT

SUBMISSIONS) TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES

USED TO CREATE FIGURES, TABLES AND CHARTS SHALL READABLE USING

MICROSOFT OFFICE 2013. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY MAILED OR

DELIVERED VIA DOD SAFE (URL: SAFE.APPS.MIL) TO THE APM.

2. BLOCK 8: GOVERNMENT APPROVAL IS REQUIRED VIA CONFIGURATION

CONTROL BOARD (CCB) PRIOR TO ANY VARIATION BEING IMPLEMENTED.

3. BLOCK 9: DISTRIBUTION STATEMENT D. DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 13 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

4. BLOCK 12: SHALL BE DUE SUBMITTED WITHIN 14 CALENDAR DAYS OF

DETERMINATION OF NEED.

5. BLOCK 13: SUBSEQUENT SUBMISSIONS, AS REQUIRED, THROUGH THE LIFE

OF THE CONTRACT.

6. THE GOVERNMENT SHALL HAVE 60 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION OF EACH SUBMISSION.

7. THE CONTRACTOR SHALL HAVE 14 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

8. CONTRACTOR FORMAT IS ACCEPTABLE. THE RFV SHALL CONTAIN ALL THE

INFORMATION IN DD FORM 1694.

3 0 0 15. TOTAL

Page 5 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SFAE-STRI-ST-LTS

SOW PARA 3.3.1

DI-MGMT-81024

SYSTEM ENGINEERING MANAGEMENT PLAN (SEMP)

A005

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

30-SEP-2021

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

3. BLOCK 12: SHALL BE DUE 60 CALENDAR DAYS AFTER CONTRACT AWARD.

4. BLOCK 13: REVISIONS AS REQUIRED THROUGH LIFE OF THE CONTRACT.

5. THE GOVERNMENT WILL HAVE 10 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION OF EACH SUBMISSION.

6. THE CONTRACTOR SHALL HAVE 5 CALENDAR DAYS TO INCORPORATE GOVERNMENT

COMMENTS.

7. CONTRACTOR FORMAT IS ACCEPTABLE.

2 0 0 15. TOTAL

Page 6 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.3.1

DI-MGMT-82133

See Block 16

A006

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

2TIME/R

Block 2: REQUIREMENTS TRACEABILITY VERIFICATION MATRIX (RTVM)

REPORT IN WIDE AREA WORKFLOW (WAWF) TO THE TECHNICAL OFFICE

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

3. BLOCK 12: SHALL BE DUE 60 CALENDAR DAYS AFTER CONTRACT AWARD.

4. BLOCK 13: SECOND SUBMISSION SHALL BE DUE 30 CALENDAR DAYS PRIOR

TO THE START OF IN-PLANT TESTING. REVISIONS, AS REQUIRED,

THROUGHOUT THE LIFE OF THE CONTRACT.

5. THE GOVERNMENT WILL HAVE 20 CALENDAR DAYS TO REVIEW AND ACCEPT OR

REJECT EACH SUBMISSION.

6. THE CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

Page 7 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.3.3

DI-IPSC-81432A

System/Subsystem Design Description (SSDD)

A007

TM OTHER IPSC

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

1TIME

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

3. BLOCK 12: SHALL BE DUE 14 CALENDAR DAYS PRIOR TO TECHNICAL DESIGN

REVIEW (TDR).

4. THE GOVERNMENT SHALL HAVE 20 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION OF THE SUBMISSION.

5. THE CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

6. CONTRACTOR FORMAT IS ACCEPTABLE.

Page 8 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.3.4

DI-IPSC-81442A

Software Version Description (SVD)

A008

TM OTHER IPSC

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

3. BLOCK 12: SHALL BE DUE 14 CALENDAR DAYS AFTER SYSTEM OPERATIONAL

TEST. FINAL SVD SHALL REPRESENT THE "SITE FIELDING" SW

CONFIGURATION OF THE SYSTEM.

4. THE GOVERNMENT SHALL HAVE 20 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION OF THE SUBMISSION.

5. THE CONTRACTOR SHALL HAVE 14 CALENDAR DAYS TO INCORPORATE COMMENTS.

Page 9 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.3.4

DI-MCCR-80700

Computer Software Product End Items

A009

TM OTHER MCCR

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

3. BLOCK 12: SHALL BE DUE 14 CALENDAR DAYS AFTER SYSTEM OPERATIONAL

TEST. FINAL COMPUTER SOFTWARE PRODUCT END ITEMS SHALL REPRESENT

THE "SITE FIELDING" SW CONFIGURATION.

4. THE COMPUTER SOFTWARE PRODUCT END ITEMS SHALL CONSIST OF ALL

DOCUMENTATION, SOURCE CODE, OBJECT, SITE SPECIFIC DATA AND

EXECUTABLE PRODUCTS AND AFFILIATED SOFTWARE MODULES.

ANY COTS SOFTWARE SHALL BE DELIVERED IN ITS NATIVE MEDIA.

5. THE GOVERNMENT SHALL HAVE 20 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION OF THE SUBMISSION.

6. THE CONTRACTOR SHALL HAVE 14 CALENDAR DAYS TO INCORPORATE COMMENTS.

Page 10 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.3.6.1

DI-MISC-80711A

RF Coverage

Scientific and Technical Reports

A010

TM OTHER MISC

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-TRADE, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

3. BLOCK 12: SHALL BE DUE 15 CALENDAR DAYS PRIOR TO THE TECHNICAL DESIGN

REVIEW.

4. THE GOVERNMENT WILL HAVE 10 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION OF EACH SUBMISSION.

5. THE CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

Page 11 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.3.8

DI-QCIC-81794

QUALITY ASSURANCE PROGRAM PLAN

A011

TM OTHER QCIC

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-TRADE, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

3. BLOCK 12: SHALL BE DUE 60 CALENDAR DAYS AFTER CONTRACT AWARD.

4. BLOCK 13: REVISIONS SHALL BE DUE, AS REQUIRED, THROUGH THE LIFE

OF THE CONTRACT.

5. THE GOVERNMENT WILL HAVE 20 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION OF EACH SUBMISSION.

6. THE CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

Page 12 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.3.9

DI-SESS-80639D

Engineering Change Proposal (ECP)

A012

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

ASREQ

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

3. BLOCK 12: SHALL BE DUE 20 CALENDAR DAYS AFTER IDENTIFYING A

CHANGE TO ANY ESTABLISHED BASELINE.

4. BLOCK 13: SUBSEQUENT SUBMISSIONS SHALL BE DUE, AS REQUIRED,

THROUGH THE LIFE OF THE CONTRACT.

5. THE GOVERNMENT SHALL HAVE 30 CALENDAR DAYS FOR REVIEW AND

APPROVAL OR REJECTION OF EACH SUBMISSION.

6. THE CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

Page 13 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.3.10

DI-SAFT-80102C

SAFETY ASSESSMENT REPORT

A013

TM OTHER SAFT

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 8: GOVERNMENT APPROVAL WILL BE REQUIRED PRIOR TO THE START

OF ANY TESTING. GOVERNMENT RE-APPROVAL WILL BE REQUIRED PRIOR TO

THE START OF ANY TESTING FOLLOWING ANY CHANGE TO THE TECHNICAL BASELINE.

3. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

4. BLOCK 12: SHALL BE DUE 14 CALENDAR DAYS AFTER COMPLETION OF THE

TECHNICAL DESIGN REVIEW.

5. BLOCK 13: REVISIONS AS REQUIRED THROUGH THE LIFE OF THE CONTRACT.

7. THE SAFETY ASSESSMENT REPORT SHALL HAVE A COMPREHENSIVE SAFETY

ASSESSMENT, RISK HAZARDS ANALYSIS AND RISK MITIGATION DUE TO

ENVIRONMENTAL HEALTH HAZARDS, HUMAN FACTORS ENGINEERING, AND

SYSTEM SAFETY DESIGN.

6. THE GOVERNMENT WILL HAVE 20 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION OF EACH SUBMISSION.

7. THE CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

8. CONTRACTOR FORMAT IS ACCEPTABLE.

Page 14 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.3.10

DI-SAFT-80106C

HEALTH HAZARD ASSESSMENT REPORT (HHAR)

A014

TM OTHER SAFT

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 8: GOVERNMENT APPROVAL WILL BE REQUIRED PRIOR TO THE

START OF ANY TESTING.

3. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

4. BLOCK 12: SHALL BE DUE 14 CALENDAR DAYS AFTER COMPLETION OF THE

TECHNICAL DESIGN REVIEW.

5. THE GOVERNMENT WILL HAVE 20 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION.

6. THE CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

Page 15 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.3.11

Technical Design Review (TDR)

A015

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

3. BLOCK 12: SUBMISSION SHALL BE DUE 15 CALENDAR DAYS PRIOR TO THE

TECHNICAL DESIGN REVIEW.

4. THE GOVERNMENT WILL HAVE 5 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION OF EACH SUBMISSION.

5. THE CONTRACTOR WILL HAVE 5 CALENDAR DAYS TO INCORPORATE GOVERNMENT

COMMENTS.

Page 16 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.4

DI-NDTI-80566A

Test Plan

A016

TM OTHER NDTI

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 8: GOVERNMENT APPROVAL IS REQUIRED 30 CALENDAR DAYS PRIOR

TO THE START OF IN-PLANT TESTING.

3. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

4. BLOCK 12: SUBMISSION DUE 20 CALENDAR DAYS AFTER COMPLETION OF THE

TECHNICAL DESIGN REVIEW.

5. BLOCK 13: REVISIONS AS REQUIRED THROUH THE LIFE OF THE CONTRACT.

6. THE GOVERNMENT WILL HAVE 20 CALENDAR DAYS TO REVIEW AND ACCEPT OR

REJECT EACH SUBMISSION.

7. THE CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

8. CONTRACTOR FORMAT IS ACCEPTABLE.

Page 17 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.4.4 & 3.4.5

DI-NDTI-80603A

Test Procedure

A017

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

3TIME/R

30-NOV-2021

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 8: GOVERNMENT APPROVAL WILL BE REQUIRED PRIOR TO THE

START OF TESTING.

3. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON 11 MAY 2020.

OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO U.S. ARMY

PROGRAM EXECUTIVE OFFICE, SIMULATION, TRAINING, AND

INSTRUMENTATION, (PEO STRI), ATTN: PEO-SFAE-STRI-PMST-LTS, 12211

SCIENCE DR., ORLANDO, FL 32826-3224.

4. BLOCK 12: COMPREHENSIVE TEST PRODCEDURE DRAFT DUE 45 CALENDAR

DAYS PRIOR TO TRR FOR IN-PLANT TESTING.

5. BLOCK 13: SECOND SUBMISSION DUE 30 CALENDAR DAYS PRIOR TO TRR FOR

SYSTEM TECHNICAL TEST. FINAL SUBMISSION DUE 30 CALENDAR DAYS PRIOR

TO TRR FOR SYSTEM OPERATIONAL TEST. REVISIONS, AS REQUIRED,

THROUGH THE LIFE OF THE CONTRACT.

6. CONTRACTOR FORMAT IS NOT ACCEPTABLE. THE CONTRACTOR SHALL USE

THE GOVERNMENT PROVIDED TEST PROCEDURE TEMPLATE IN LIEU OF THE DID FORMAT.

7. THE GOVERNMENT WILL HAVE 20 CALENDAR DAYS FOR REVIEW AND

ACCEPTANCE OR REJECTION OF EACH SUBMISSION.

8. THE CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO INCORPORATE GOVERMENT

COMMENTS.

Page 18 of 35 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARA 3.4.4 & 3.4.5

DI-NDTI-80809B

Test/Inspection Report

A018

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

2TIME/R

30-NOV-2021

RESPONSIBLE FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6,

AND AS DELINEATED BY BLOCK 14. A WAWF RECEIVING REPORT IS REQUIRED

FOR EACH DATA ITEM SUBMISSION (INITIAL AND SUBSEQUENT SUBMISSIONS)

TO THE GOVERNMENT. ALL DOCUMENTS AND GRAPHIC PACKAGES USED TO

CREATE FIGURES, TABLES AND CHARTS SHALL BE READABLE USING

MICROSOFT OFFICE 2016. IF, DUE TO FILE SIZE, THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF, A COVER PAGE SHALL BE SUBMITTED VIA

WAWF AND THE DELIVERABLE SHALL BE ELECTRONICALLY DELIVERED VIA DOD

SAFE (HTTPS://SAFE.APPS.MIL) TO THE TECHNICAL OFFICE RESPONSIBLE

FOR THE REVIEW/APPROVAL OF THE DATA ITEM PER BLOCK 6, AND AS

DELINEATED BY BLOCK 14. THE CONTRACTOR WILL NEED TO REQUEST A

DROP-OFF VIA DOD SAFE FOR EACH DELIVERABLE THAT THE CONTRACTOR IS

UNABLE TO SUBMIT VIA WAWF.

2. BLOCK 9: DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO

THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY. DUE TO

ADMINISTRATIVE USE, THIS DETERMINATION WAS MADE ON…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .