Exhibit4_Specifications.pdf

PDF 1 MB Posted

Attached to
Lakeside Ranger District Concrete and Asphalt Road Repairs
Solicitation number
12837120Q0226
Issued by

View the file

Other files

File Type Posted
Sol_12837120Q0226.pdf PDF
Exhibit 2 - BioPreferred.pdf PDF
Exhibit3_Drawings_20200204.pdf PDF
Exhibit 1_WD_AZ20200008.pdf PDF
SectionsBCDFGJM.pdf PDF
Exhibit6_FoolHollowMap.pdf PDF
Exhibit5_Pictures.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Apache-Sitgreaves

Specifications Package

Project: Fool Hollow Road and Site Repairs District: Lakeside Ranger District Region: Southwest Region 03

Contracting Office: TBD Contracting Officer: TBD

Contracting Address: TBD

Civil Engineer: Richard Polanco Date: 01/22/2020

Fool Hollow Road and Site Repairs

2 | P a g e

Table of Contents

SUBMITTAL REGISTER

SECTION 00 01 15 – LIST OF DRAWINGS AND SPECIFICATIONS

SECTION 00 50 00 – CONTRACTING FORMS AND SUPPLEMENTS

SECTION 01 11 00 – SUMMARY OF WORK

SECTION 01 14 00 – WORK RESTRICTIONS

SECTION 01 42 13 – ABBREVIATIONS AND ACRONYMS

SECTION 03 11 00 – CONCRETE FORMING AND ACCESSORIES

SECTION 03 15 16 – CONCRETE JOINTS

SECTION 03 20 00 – CONCRETE REINFORCING

SECTION 03 30 00 – CAST-IN-PLACE CONCRETE

3 | P a g e

SUBMITTAL REGISTER

Contract Document

Reference

Description Item Submitted Pa ra gr ap h

Submittal Type (1)

For (2) No

. o f C op ies

Contractor Government Action Sp ec ifi ca tio n Se ct io n Nu m be r

Dr aw in g

Sh ee t Nu m be r

Va ria nc e (

Y/ N)

Da te

S ub m itt ed

Da te

R et ur ne d

Ac tio n Co de (3

Re vie we d

By

03 30 00 Concrete Mix Design 2.2.A SD-05 GA 2 03 30 00 Concrete Test Results 3.5 SD-06 FIO 2

(1) Submittal Type:

SD-01 – Preconstruction SD-02 – Shop Drawings SD-07 – Certificates SD-03 – Product Data SD-08 – Manufacturer’s Instructions SD-04 – Samples SD-09 – Manufacturer’s Field Reports SD-05 – Design Data SD-10 – O&M Data SD-06 – Test Reports SD-11 – Closeout

(2) For:

FIO – For Information Only GA – Government Approval

(3) Action Codes:

A – Approved B – Approved, except at noted (no resubmission) C – Approved, except as noted (resubmission req’d) D – Will be returned by separate correspondence E – Disapproved (resubmission req’d) F – Receipt Acknowledged (no resubmission) X – Receipt Acknowledged, does not comply with contract requirements, as noted (resubmission req’d)

4 | P a g e

SECTION 00 01 15 – LIST OF DRAWINGS AND SPECIFICATIONS

PART 1 - GENERAL

1.1 LIST OF DRAWINGS

A. FOOL HOLLOW ROAD AND SITE REPAIRS, Dated 01/22/2020

1. C-01 Concrete Details

1.2 LIST OF SPECIFICATIONS

A. DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

1. Section 00 01 15 LIST OF DRAWINGS AND SPECIFICATIONS

2. Section 00 50 00 CONTRACTING FORMS AND SUPPLEMENTS

B. DIVISION 01 – GENERAL REQUIREMENTS

1. Section 01 11 00 SUMMARY OF WORK

2. Section 01 14 00 WORK RESTRICTIONS

3. Section 01 42 13 ABBREVIATIONS AND ACRONYMS

C. DIVISION 03 – CONCRETE

1. Section 03 11 00 CONCRETE FORMING AND ACCESSORIES

2. Section 03 15 16 CONCRETE JOINTS

3. Section 03 20 00 CONCRETE REINFORCEMENT

4. Section 03 30 00 CAST-IN-PLACE CONCRETE

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 00 01 15

5 | P a g e

SECTION 00 50 00 – CONTRACTING FORMS AND SUPPLEMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This section consists of standard forms required during the course of the project. It is not intended to be a full and complete list of forms, but typical forms used during a project.

B. All forms are attached to this specification section. Electronic copies available upon request.

1.2 PRE-CONSTRUCTION FORMS

A. Standard Form (SF) 1413 – STATEMENT AND ACKNOWLEDGMENT

1. Required for each individual subcontractor for the project.

2. Must be submitted prior to the subcontractor(s) starting a feature of work, and approved in writing by the Contracting Officer.

1.3 PROGRESS AND FINAL PAYMENT FORMS

A. FAR 52-232-5 – PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTACTS

1. Required with submission of all progress and final payments.

B. WH-347 – CERTIFIED PAYROLL

1. Required weekly and submitted with all payment requests.

2. Contractor-developed forms may be used in lieu of, but must contain, at minimum, all information as required on WH-347.

1.4 CLOSEOUT FORMS

A. All those required under Section 1.3.

B. FSH 6309.11 – CONTRACT RELEASE FORM

1. Required at the time of final payment submission for all contracts.

PART 2 - PRODUCTS (NOT USED)

END OF SECTION 00 50 00

STATEMENT AND ACKNOWLEDGMENT OMB No.: 9000-0014 Expires: 6/30/2014

Public reporting burden for this collection of information is estimated to average 30 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the FAR Secretariat, (VIR), Regulatory and Federal Assistance Division, GSA, Washington, DC 20405; and to the Office of Management and Budget, Paperwork Reduction Project (9000-0014), Washington, DC 20503.

PART I - STATEMENT OF PRIME CONTRACTOR

1. PRIME CONTRACT NO. 2. DATE SUBCONTRACT

AWARDED

3. SUBCONTRACT NUMBER

15b. TITLE OF PERSON SIGNING

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1413 (REV. 7/2005)

Prescribed by GSA/FAR (48 CFR) 53.222(e)

4. PRIME CONTRACTOR 5. SUBCONTRACTOR

a. NAME a. NAME

b. STREET ADDRESS b. STREET ADDRESS

c. CITY d. STATE e. ZIP CODE c. CITY d. STATE e. ZIP CODE

6. The prime contract does, does not contain the clause entitled "Contract Work Hours and Safety Standards Act -- Overtime Compensation."

7. The prime contractor states that under the contract shown in Item 1, a subcontract was awarded on the date shown in Item 2 to the subcontractor identified in item 5 by the following firm:

a. NAME OF AWARDING FIRM

b. DESCRIPTION OF WORK BY SUBCONTRACTOR

8. PROJECT 9. LOCATION

10a. NAME OF PERSON SIGNING 11. BY (Signature) 12. DATE SIGNED

10b. TITLE OF PERSON SIGNING

PART II - ACKNOWLEDGMENT OF SUBCONTRACTOR

13. The subcontractor acknowledges that the following clauses of the contract shown in Item 1 are included in this subcontract:

Contract Work Hours and Safety Standards Act - Overtime Compensation - (If included in prime contract see Block 6) Payrolls and Basic Records Withholding of Funds Disputes Concerning Labor Standards Compliance with Davis-Bacon and Related Act Regulations

Davis-Bacon Act Apprentices and Trainees Compliance with Copeland Act Requirements Subcontracts (Labor Standards) Contract Termination - Debarment Certification of Eligibility

14. NAME(S) OF ANY INTERMEDIATE SUBCONTRACTORS, IF ANY

A C

B D

15a. NAME OF PERSON SIGNING 16. BY (Signature) 17. DATE SIGNED

FAR 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (SEP 2002)

(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.

(1) The Contractor’s request for progress payments shall include the following substantiation:

(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.

(ii) A listing of the amount included for work performed by each subcontractor under the contract.

(iii) A listing of the total amount of each subcontract under the contract.

(iv) A listing of the amounts previously paid to each such subcontractor under the contract.

(v) Additional supporting data in a form and detail required by the Contracting Officer.

(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if—

(i) Consideration is specifically authorized by this contract; and

(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.

(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)

I hereby certify, to the best of my knowledge and belief, that—

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor’s performance.

(Name)

(Title)

(Date)

U.S. Department of Labor PAYROLL (For Contractor's Optional Use; See Instructions at www.dol.gov/whd/forms/wh347instr.htm) Wage and Hour Division

Persons are not required to respond to the collection of information unless it displays a currently valid OMB control number.

NAME OF CONTRACTOR OR SUBCONTRACTOR ADDRESS OMB No.: 1235-0008 Expires: 02/28/2018

PAYROLL NO. FOR WEEK ENDING PROJECT AND LOCATION PROJECT OR CONTRACT NO.

(1) (2) (3) (4) DAY AND DATE (5) (6) (7) (9)

(8)

DEDUCTIONS

O

O

O

O

O

O

O

O

NAME AND INDIVIDUAL IDENTIFYING NUMBER

(e.g., LAST FOUR DIGITS OF SOCIAL SECURITY

NUMBER) OF WORKER N

O

. O F

W

IT

H H

O

LD

iN G

E

XE

M

P

TI

O N

S

WORK

CLASSIFICATION

O T.

O R

S T.

HOURS WORKED EACH DAY

TOTAL

HOURS

RATE

OF PAY

GROSS

AMOUNT

EARNED FICA

WITH-

HOLDING

TAX OTHER

TOTAL

DEDUCTIONS

NET

WAGES

PAID

FOR WEEK

S

S

S

S

S

S

S

S

Rev. Dec. 2008

Rev. Dec. 2008

While completion of Form WH-347 is optional, it is mandatory for covered contractors and subcontractors performing work on Federally financed or assisted construction contracts to respond to the information collection contained in 29 C.F.R. §§ 3.3, 5.5(a). The Copeland Act (40 U.S.C. § 3145) contractors and subcontractors performing work on Federally financed or assisted construction contracts to "furnish weekly a statement with respect to the wages paid each employee during the preceding week." U.S. Department of Labor (DOL) regulations at 29 C.F.R. § 5.5(a)(3)(ii) require contractors to submit weekly a copy of all payrolls to the Federal agency contracting for or financing the construction project, accompanied by a signed "Statement of Compliance" indicating that the payrolls are correct and complete and that each laborer or mechanic has been paid not less than the proper Davis-Bacon prevailing wage rate for the work performed. DOL and federal contracting agencies receiving this information review the information to determine that employees have received legally required wages and fringe benefits.

Public Burden Statement

We estimate that is will take an average of 55 minutes to complete this collection, including time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. If you have any comments regarding these estimates or any other aspect of this collection, including suggestions for reducing this burden, send them to the Administrator, Wage and Hour Division, U.S. Department of Labor, Room S3502, 200 Constitution Avenue, N.W.

Washington, D.C. 20210

(over) nthai nthai nthai

Date

I, (Name of Signatory Party) (Title) do hereby state:

(1) That I pay or supervise the payment of the persons employed by on the (Contractor or Subcontractor)

; that during the payroll period commencing on the (Building or Work) day of , , and ending the day of , , all persons employed on said project have been paid the full weekly wages earned, that no rebates have been or will be made either directly or indirectly to or on behalf of said from the full (Contractor or Subcontractor) weekly wages earned by any person and that no deductions have been made either directly or indirectly from the full wages earned by any person, other than permissible deductions as defined in Regulations, Part 3 (29 C.F.R. Subtitle A), issued by the Secretary of Labor under the Copeland Act, as amended (48 Stat. 948, 63 Stat. 108, 72 Stat. 967; 76 Stat. 357; 40 U.S.C. § 3145), and described below:

(2) That any payrolls otherwise under this contract required to be submitted for the above period are correct and complete; that the wage rates for laborers or mechanics contained therein are not less than the applicable wage rates contained in any wage determination incorporated into the contract; that the classifications set forth therein for each laborer or mechanic conform with the work he performed.

(3) That any apprentices employed in the above period are duly registered in a bona fide apprenticeship program registered with a State apprenticeship agency recognized by the Bureau of Apprenticeship and Training, United States Department of Labor, or if no such recognized agency exists in a State, are registered with the Bureau of Apprenticeship and Training, United States Department of Labor.

(4) That:

(a) WHERE FRINGE BENEFITS ARE PAID TO APPROVED PLANS, FUNDS, OR PROGRAMS

− in addition to the basic hourly wage rates paid to each laborer or mechanic listed in the above referenced payroll, payments of fringe benefits as listed in the contract have been or will be made to appropriate programs for the benefit of such employees, except as noted in section 4(c) below.

(b) WHERE FRINGE BENEFITS ARE PAID IN CASH

− Each laborer or mechanic listed in the above referenced payroll has been paid, as indicated on the payroll, an amount not less than the sum of the applicable basic hourly wage rate plus the amount of the required fringe benefits as listed in the contract, except as noted in section 4(c) below.

(c) EXCEPTIONS

REMARKS:

EXCEPTION (CRAFT)

EXPLANATION

NAME AND TITLE SIGNATURE

THE WILLFUL FALSIFICATION OF ANY OF THE ABOVE STATEMENTS MAY SUBJECT THE CONTRACTOR OR SUBCONTRACTOR TO CIVIL OR CRIMINAL PROSECUTION. SEE SECTION 1001 OF TITLE 18 AND SECTION 231 OF TITLE

31 OF THE UNITED STATES CODE.

nthai nthai

FSH 6309.11 - CONTRACT ADMINISTRATION HANDBOOK

RELEASE FORM

Based on FS-6300-16

USDA - Forest Service CONTRACT NUMBER

UNIT

CONTRACT RELEASE

(Reference FSH 6309.11)

TO:

In consideration of ___________ the undersigned hereby releases the United States of America from any and all obligations arising under this contract and any modifications thereof except as reserved below:

Reservations:

Date:_____________________ ____ Contractor

By ___

Title _

NAME AND ADDRESS OF CONTRACTOR

PROJECT

richardrpolanco Sticky Note Marked set by richardrpolanco richardrpolanco Sticky Note Marked set by richardrpolanco richardrpolanco Sticky Note Marked set by richardrpolanco

11 | P a g e

SECTION 01 11 00 – SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Work for this project consists of the demolition, removal, and replacement of 6-inch concrete in roadways and camp sites at the Fool Hollow Lake Recreation Area.

1.2 LOCATION

A. The project work is located Fool Hollow Lake Recreation Area, 1500 North Fool Hollow Lake Road, Show Low, AZ, 85901.

1.3 GENERAL SITE CONDITIONS AND WEATHER

A. The area sits at an elevation of approximately 6,300 feet above sea level. Fall and winter months see high temperatures in the 40s and 50s, with nighttime temperatures dropping to 20 degrees and colder. Snowfall can be expected starting in November and running through March; but tends to melt quickly.

1.4 FIELD VERIFICATION

A. Field verify all new and existing dimensions and project conditions affecting the work of the project prior to starting the work. If there are any discrepancies from the contract drawings and specifications, notify the Contracting Officer before proceeding with the work.

PART 2 - PRODUCTS (NOT USED)

END OF SECTION 01 11 00

12 | P a g e

SECTION 01 14 00 – WORK RESTRICTIONS

PART 1 - GENERAL

1.1 SUMMARY

A. This section covers general and specific work restrictions at the project site.

1.2 USE OF PREMISES

A. Contractor’s use of premises is limited by the Government’s right to perform work or to retain other contractors for other projects. Coordinate work activities with other contractors, if applicable, on site to avoid conflict causing construction delays.

B. Conduct operations to ensure the least inconvenience to the public, government employees, and other contractors onsite.

C. Limit use of premises to work in within the construction limits. Do not disturb portions of the project site beyond where the construction limits are indicated.

D. Keep roadways and entrances clear and available to Government employees and vehicles, emergency vehicles, and the public at all times. Do not use these areas for parking or storage of materials.

E. Use of Government’s existing toilet facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to the Government.

F. Provide adequate signing and barricades, and take necessary safety measures to protect the public during all construction operations, per MUTCD and OSHA. Minimize disturbance of all undisturbed areas.

G. Overnight camping may be available on the project where there is little to no available accommodations within a reasonable distance to the construction site. Coordinate with the Contracting Officer if for overnight stays at designated areas in and around the project site.

1.3 WORK SCHEDULING

A. Normal working hours for construction activities are from 8:00 AM to 6:00 PM, Monday through Thursday.

B. Request for additional work hours requires written approval from the Contracting Officer 7 days in advance of the proposed work period.

C. Depending on conditions, normal fire restrictions may apply to activities associated with this project. Refer to the fire plan for mandatory requirements for different fire restrictions.

13 | P a g e

1.4 UTILITIES

A. WATER

1. Water is available at the site(s). Contact AZSP manager at 928-537-3680.

B. ELECTRIC

1. Electric is available at the site(s). Contact AZSP manager at 928-537-3680.

C. SANITATION

1. Flush-toilet facilities are available to the Contractor, so long as the facilities are kept in the same condition before use.

1.5 PRESERVATION OF NATURAL FEATURES

A. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damages trees and plants, at no additional cost to the Government.

B. Do not remove, injure, or destroy trees or other plants without prior approval, or as indicated in the contract.

C. Carefully supervise excavating, grading, backfilling, and other construction operations near trees to prevent damage.

PART 2 - PRODUCTS (NOT USED)

END OF SECTION 01 14 00

14 | P a g e

SECTION 01 42 13 – ABBREVIATIONS AND ACRONYMS

PART 1 - GENERAL

1.1 CONTRACTING

A. CO – Contracting Officer

B. COR – Contracting Officer’s Representative

C. FAR – Federal Acquisition Regulation

D. FIO – For Information Only

E. GA – Government Approval

F. SF – Standard Form

1.2 OTHER

A. MUTCD – Manual on Uniform Traffic Control Devices

1.3 TECHNICAL AND PROFESSIONAL GROUPS

A. AASHTO – American Association of State Highway and Transportation Officials

B. ACI – American Concrete Institute

C. ANSI – American National Standards Institute

D. APA – American Plywood Association

E. ASTM – American Society for Testing and Materials

F. CCRL – Cement and Concrete Reference Laboratory

G. CRSI – Concrete Reinforcing Steel Institute

H. NIST – National Institute of Standards and Technology

PART 2 - PRODUCTS (NOT USED)

END OF SECTION 01 42 13

15 | P a g e

SECTION 03 11 00 – CONCRETE FORMING AND ACCESSORIES

PART 1 - GENERAL

1.1 SUMMARY

A. This section covers requirements for concrete forming and accessories, for replacing and new concrete applications.

PART 2 - PRODUCTS

2.1 MATERIALS FOR FORMS

A. General

1. Use wood, metal, or other suitable material for forms.

B. Wood Forms.

1. Provide lumber that is square edges or tongue-and-groove boards, free of raised grain, knotholes, or other surface defects.

2. Provide plywood that complies with NIST PS 1, B-B concrete form panels or better or

APA A135.4, hardboard for smooth form lining.

C. Plastic Forms.

1. Provide plastic forms that contain a minimum of 50 percent post-consumer recycled content, or a minimum of 50 percent post-industrial recycled content.

D. Steel Forms.

1. Provide steel form surfaces that to not contain irregularities, dents, or sags.

PART 3 - EXECUTION

3.1 FORMS

A. Design and construct forms that are free of bulge and warp and allow for removal without injuring the concrete. When concrete contains a retarding admixture, fly ash, or other pozzolan replacement for cement, design the forms for a lateral pressure equal to that exerted by a fluid weighing 150 pounds per cubic foot.

B. Set forms mortar-tight and true to line and grade.

C. Before concrete placement, coat the contact surfaces of forms with a form release agent.

D. Use forms that extend the full depth of the concrete.

16 | P a g e

E. Construct formwork to ensure that after removal of forms and prior to patching and finishing of formed surfaces; provide concrete surfaces in accordance with tolerances specified in ACI 301 Section 5 and ACI 117.

F. Reuse forms providing the structural integrity of concrete and the aesthetics of exposed concrete are not compromised. Wood forms must not be clogged with paste and must be capable of absorbing high water-cementitious material ratio paste.

G. Provide form ties in accordance with ACI 301 Section 2.

H. After placing concrete, removal of forms must be in accordance with ACI 301 Section 2.

END OF SECTION 03 11 00

17 | P a g e

SECTION 03 15 16 – CONCRETE JOINTS

PART 1 - GENERAL

1.1 SUMMARY

A. This section includes requirements for control, isolation, and construction joints in concrete, both for replacing and new concrete activities.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Bond Breaker: Non-staining type which provides positive bond prevention.

1. White opaque polyethylene film under ASTM C 171 except the minimum thickness must be 6 mils.

2. White curing paper under ASTM C 171.

3. Geosynthetic bond breaker.

PART 3 - EXECUTION

3.1 GENERAL

A. Do not vary longitudinal joints more than ½ inch and transverse joints more than ¼ inch from the true alignment.

B. Methods

1. Dry-cut saw method.

a. Install joints as soon as sawing equipment can be supported, and before uncontrolled cracking occurs.

b. Do not ravel the joints while sawing.

c. Do not saw a joint if a crack occurs at or near the joint location before sawing.

d. Discontinue sawing when a crack develops ahead of the saw.

2. Tooled.

C. Remove and place newly placed concrete where uncontrolled cracking occurs.

1. Do not saw a joint if a crack occurs at or near the joint location before sawing.

2. Discontinue sawing when a crack develops ahead of the saw.

3.2 CONTROL (CONTRACTION) JOINTS

A. Install control joints as shown and detailed in the drawings.

18 | P a g e

3.3 COLD JOINTS

A. In lieu of isolation joints and where indicated on the drawings, install base bond breaker. Install bond breaker per the manufacturer’s instructions.

B. Clean groove of foreign matter and loose particles after surface has dried.

END OF SECTION 03 15 16

19 | P a g e

SECTION 03 20 00 – CONCRETE REINFORCING

PART 1 - GENERAL

1.1 SUMMARY

A. This section includes required concrete reinforcement product standards and installation of various types of concrete reinforcement.

1.2 SECTION REQUIREMENTS

A. Delivery, Storage, and Handling

1. Store reinforcement and accessories off the ground on platforms, skids, or other supports.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Reinforcing Bars.

1. Deformed, ASTM A615/A615M grade 60 bars and sizes as indicated

B. Dowel Bars.

1. Conform to AASHTO M 254, type A or B.

PART 3 - EXECUTION

3.1 DOWEL INSTALLATION

A. Use plain round bars, free from burring or other deformation restricting free movement in the concrete.

B. Dowel with lengths as indicated on the drawings. Immediately prior to placing the dowel, clean hole of dust and other deleterious material with a high pressure air hose. Fill hole halfway with epoxy or non-shrink grout, and insert dowel by rotating it at least one complete turn while tapping it down. Add more epoxy or non-shrink grout to completely fill hole, if necessary.

C. Install dowels in slabs on grade at locations indicated and at right angles to joint being doweled.

D. Accurately position and align dowels parallel to the finished concrete surface before concrete placement.

E. Rigidly support dowels during concrete placement.

END OF SECTION 03 20 00

20 | P a g e

SECTION 03 30 00 – CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 SUMMARY

A. This section includes requirements for cast-in-place concrete for various placement applications.

1.2 SECTION REQUIREMENTS

A. Reference Sections:

1. 03 11 00 – CONCRETE FORMING AND ACCESSORIES

2. 03 15 16 – CONCRETE JOINTS

B. Submittals:

1. Concrete mix design (SD-05, Design Data), GA

2. Concrete testing results (SD-06, Test Reports), GA

C. Weather Limitations:

1. When air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes.

2. When air temperature is less than 40 deg F, use ACI 306 A Guide to Cold Weather

Concreting. Submit a detailed plan for the producing, transporting, placing, protecting, curing, and temperature monitoring of concrete.

3. When rain is threatening during paving operations, stop paving operations and protect the concrete pavement from rain with plastic sheeting or other methods approved by the Contracting Officer. Remove, replace, or repair pavement damaged by rain or hail as directed by the Contracting Officer at no cost to the Government.

D. Ready-Mixed Concrete Producer Qualifications: ASTM C 94/C 94M.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Portland Cement: ASTM C 150, Type I or II.

B. Aggregates: ASTM C 33, Class 3S coarse aggregate or better.

1. Maximum Coarse-Aggregate Size: 1-1/2 inches nominal.

2. Maximum Aggregate Size for Concrete in Insulating Concrete Forms: 3/4 inch.

C. Air-Entraining Admixture: ASTM C 260.

D. Chemical Admixtures: ASTM C 494, water reducing, high-range water reducing, water reducing and accelerating, and water reducing and retarding. Do not use calcium chloride or admixtures containing calcium chloride.

21 | P a g e

E. Synthetic Fiber: ASTM C 1116/C 1116M, Type III, polypropylene fibers, 1/2 to 1-1/2 inches long.

F. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

2.2 CONCRETE MIXTURES

A. Normal-Weight Concrete:

1. Minimum Compressive Strength: 4000 psi at 28 days.

2. Maximum Water-Cementitious Materials Ratio: 0.45.

3. Slump Limit: 4 inches for concrete with verified slump of 3 to 5 inches before adding high-range water-reducing admixture or plasticizing admixture, plus or minus 1 inch.

4. Air Content: 4-6 percent.

5. Synthetic Fiber: 1.5 lb/CY.

B. Measure, batch, mix, and deliver concrete according to ASTM C 94.

1. Maintain temperature of the concrete mixture just before placement between 50 and 90 deg F.

2. Complete concrete discharge operations within 1-1/2 hours after the introduction of the mixing water to the cement and aggregates.

3. Adding water to the mix not permitted beyond the batching and mixing operations.

PART 3 - EXECUTION

3.1 CONCRETING

A. Compact subgrade and subbase to firm and stable surface.

B. Provide 24-hour notice of any concrete placement operations that will be occurring.

C. Place concrete in a continuous operation and consolidate using mechanical vibrating equipment.

1. Place concrete to avoid segregation of material.

2. Do not exceed 30 minutes between deliveries of batches for a single pour.

D. Protect concrete from physical damage, premature drying, and reduced strength due to hot or cold weather during mixing, placing, and curing. Repair and patch defective areas. Methods for protecting concrete, and repairing and patching defective areas to be approved by the Contracting Officer.

E. Being curing concrete slabs after finishing.

1. Cure concrete at least 7 days.

2. If high early strength cement is used, cure concrete at least 3 days.

22 | P a g e

3.2 FINISHES

A. Slab Finishes: Comply with ACI 302.1R for screeding, re-straightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces. Provide the following finishes:

1. Non-slip (medium-broom) finish to exterior concrete roadways.

3.3 CONCRETE JOINTS

A. Install control, isolation, and construction joints where indicated, and per 03 15 16 –

CONCRETE JOINTS.

3.4 CONCRETE REPLACEMENT

A. Furnish concrete saws, drop hammers, hydro-hammers, and jack jammers to break concrete.

Saws shall have sufficient power to saw full depth and complete the work with water-cooled, diamond-edged blades or abrasive wheels. Equip saws with blade guards and guides or devices to control alignment and depth. Ball-drop breakers are not permitted.

B. Furnish equipment that will not damage the subgrade, subbase, base, or existing concrete slabs designated to remain.

C. If new or existing slabs not scheduled for replacement are chipped, spalled, or damaged during the removal operations, replace the damaged slabs at no cost to the Government.

D. Dowel into the sides of existing concrete, such as foundations, curb and gutter, and sidewalk.

3.5 FIELD QUALITY CONTROL

A. Provide independent certified testing agency, minimum Grade I ACI Concrete Field Testing Technician.

B. Concrete testing laboratory must have the necessary equipment and experience to accomplish required testing. The laboratory must meet the requirements of ASTM C 1077 and be CCRL inspected.

C. Upon arrival of the first concrete truck delivery:

1. Provide compressive strength testing, per AASHTO T-22 & T-23.

a. 1 set during the first concrete delivery.

b. Test two cylinders at 7 days; two cylinders at 28 days, and hold two cylinders in reserve.

2. Provide slump test at the site of discharge, per AASHTO T 119.

3. Provide air content test for air-entrained concrete per AASHTO T 152 or T 196.

4. Determine temperature of concrete at time of placement in accordance with ASTM C

1064.

END OF SECTION 03 30 00

SUBMITTAL REGISTER
SECTION 00 01 15 – LIST OF DRAWINGS AND SPECIFICATIONS
PART 1 - GENERAL
1.1 LIST OF DRAWINGS
A. FOOL HOLLOW ROAD AND SITE REPAIRS, Dated 01/22/2020
1. C-01 Concrete Details
1.2 LIST OF SPECIFICATIONS
A. DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
1. Section 00 01 15 LIST OF DRAWINGS AND SPECIFICATIONS
2. Section 00 50 00 CONTRACTING FORMS AND SUPPLEMENTS
B. DIVISION 01 – GENERAL REQUIREMENTS
1. Section 01 11 00 SUMMARY OF WORK
2. Section 01 14 00 WORK RESTRICTIONS
3. Section 01 42 13 ABBREVIATIONS AND ACRONYMS
C. DIVISION 03 – CONCRETE
1. Section 03 11 00 CONCRETE FORMING AND ACCESSORIES
2. Section 03 15 16 CONCRETE JOINTS
3. Section 03 20 00 CONCRETE REINFORCEMENT
4. Section 03 30 00 CAST-IN-PLACE CONCRETE
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
SECTION 00 50 00 – CONTRACTING FORMS AND SUPPLEMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This section consists of standard forms required during the course of the project. It is not intended to be a full and complete list of forms, but typical forms used during a project.
B. All forms are attached to this specification section. Electronic copies available upon request.
1.2 PRE-CONSTRUCTION FORMS
A. Standard Form (SF) 1413 – STATEMENT AND ACKNOWLEDGMENT
1. Required for each individual subcontractor for the project.
2. Must be submitted prior to the subcontractor(s) starting a feature of work, and approved in writing by the Contracting Officer.
1.3 PROGRESS AND FINAL PAYMENT FORMS
A. FAR 52-232-5 – PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTACTS
1. Required with submission of all progress and final payments.
B. WH-347 – CERTIFIED PAYROLL
1. Required weekly and submitted with all payment requests.
2. Contractor-developed forms may be used in lieu of, but must contain, at minimum, all information as required on WH-347.
1.4 CLOSEOUT FORMS
A. All those required under Section 1.3.
B. FSH 6309.11 – CONTRACT RELEASE FORM
1. Required at the time of final payment submission for all contracts.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
SECTION 01 11 00 – SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Work for this project consists of the demolition, removal, and replacement of 6-inch concrete in roadways and camp sites at the Fool Hollow Lake Recreation Area.
1.2 LOCATION
A. The project work is located Fool Hollow Lake Recreation Area, 1500 North Fool Hollow Lake Road, Show Low, AZ, 85901.
1.3 GENERAL SITE CONDITIONS AND WEATHER
A. The area sits at an elevation of approximately 6,300 feet above sea level. Fall and winter months see high temperatures in the 40s and 50s, with nighttime temperatures dropping to 20 degrees and colder. Snowfall can be expected starting in November...
1.4 FIELD VERIFICATION
A. Field verify all new and existing dimensions and project conditions affecting the work of the project prior to starting the work. If there are any discrepancies from the contract drawings and specifications, notify the Contracting Officer before pr...
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
SECTION 01 14 00 – WORK RESTRICTIONS
PART 1 - GENERAL
1.1 SUMMARY
A. This section covers general and specific work restrictions at the project site.
1.2 USE OF PREMISES
A. Contractor’s use of premises is limited by the Government’s right to perform work or to retain other contractors for other projects. Coordinate work activities with other contractors, if applicable, on site to avoid conflict causing construction de...
B. Conduct operations to ensure the least inconvenience to the public, government employees, and other contractors onsite.
C. Limit use of premises to work in within the construction limits. Do not disturb portions of the project site beyond where the construction limits are indicated.
D. Keep roadways and entrances clear and available to Government employees and vehicles, emergency vehicles, and the public at all times. Do not use these areas for parking or storage of materials.
E. Use of Government’s existing toilet facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to the Government.
F. Provide adequate signing and barricades, and take necessary safety measures to protect the public during all construction operations, per MUTCD and OSHA. Minimize disturbance of all undisturbed areas.
G. Overnight camping may be available on the project where there is little to no available accommodations within a reasonable distance to the construction site. Coordinate with the Contracting Officer if for overnight stays at designated areas in and ...
1.3 WORK SCHEDULING
A. Normal working hours for construction activities are from 8:00 AM to 6:00 PM, Monday through Thursday.
B. Request for additional work hours requires written approval from the Contracting Officer 7 days in advance of the proposed work period.
C. Depending on conditions, normal fire restrictions may apply to activities associated with this project. Refer to the fire plan for mandatory requirements for different fire restrictions.
1.4 UTILITIES
A. WATER
1. Water is available at the site(s). Contact AZSP manager at 928-537-3680.
B. ELECTRIC
1. Electric is available at the site(s). Contact AZSP manager at 928-537-3680.
C. SANITATION
1. Flush-toilet facilities are available to the Contractor, so long as the facilities are kept in the same condition before use.
1.5 PRESERVATION OF NATURAL FEATURES
A. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damages trees and plants, at no additional cost to the Government.
B. Do not remove, injure, or destroy trees or other plants without prior approval, or as indicated in the contract.
C. Carefully supervise excavating, grading, backfilling, and other construction operations near trees to prevent damage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
SECTION 01 42 13 – ABBREVIATIONS AND ACRONYMS
PART 1 - GENERAL
1.1 CONTRACTING
A. CO – Contracting Officer
B. COR – Contracting Officer’s Representative
C. FAR – Federal Acquisition Regulation
D. FIO – For Information Only
E. GA – Government Approval
F. SF – Standard Form
1.2 OTHER
A. MUTCD – Manual on Uniform Traffic Control Devices
1.3 TECHNICAL AND PROFESSIONAL GROUPS
A. AASHTO – American Association of State Highway and Transportation Officials
B. ACI – American Concrete Institute
C. ANSI – American National Standards Institute
D. APA – American Plywood Association
E. ASTM – American Society for Testing and Materials
F. CCRL – Cement and Concrete Reference Laboratory
G. CRSI – Concrete Reinforcing Steel Institute
H. NIST – National Institute of Standards and Technology
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
SECTION 03 11 00 – CONCRETE FORMING AND ACCESSORIES
PART 1 - GENERAL
1.1 SUMMARY
A. This section covers requirements for concrete forming and accessories, for replacing and new concrete applications.
PART 2 - PRODUCTS
2.1 MATERIALS FOR FORMS
A. General
1. Use wood, metal, or other suitable material for forms.
B. Wood Forms.
1. Provide lumber that is square edges or tongue-and-groove boards, free of raised grain, knotholes, or other surface defects.
2. Provide plywood that complies with NIST PS 1, B-B concrete form panels or better or APA A135.4, hardboard for smooth form lining.
C. Plastic Forms.
1. Provide plastic forms that contain a minimum of 50 percent post-consumer recycled content, or a minimum of 50 percent post-industrial recycled content.
D. Steel Forms.
1. Provide steel form surfaces that to not contain irregularities, dents, or sags.
PART 3 - EXECUTION
3.1 FORMS
A. Design and construct forms that are free of bulge and warp and allow for removal without injuring the concrete. When concrete contains a retarding admixture, fly ash, or other pozzolan replacement for cement, design the forms for a lateral pressure...
B. Set forms mortar-tight and true to line and grade.
C. Before concrete placement, coat the contact surfaces of forms with a form release agent.
D. Use forms that extend the full depth of the concrete.
E. Construct formwork to ensure that after removal of forms and prior to patching and finishing of formed surfaces; provide concrete surfaces in accordance with tolerances specified in ACI 301 Section 5 and ACI 117.
F. Reuse forms providing the structural integrity of concrete and the aesthetics of exposed concrete are not compromised. Wood forms must not be clogged with paste and must be capable of absorbing high water-cementitious material ratio paste.
G. Provide form ties in accordance with ACI 301 Section 2.
H. After placing concrete, removal of forms must be in accordance with ACI 301 Section 2.
SECTION 03 15 16 – CONCRETE JOINTS
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes requirements for control, isolation, and construction joints in concrete, both for replacing and new concrete activities.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Bond Breaker: Non-staining type which provides positive bond prevention.
1. White opaque polyethylene film under ASTM C 171 except the minimum thickness must be 6 mils.
2. White curing paper under ASTM C 171.
3. Geosynthetic bond breaker.
PART 3 - EXECUTION
3.1 GENERAL
A. Do not vary longitudinal joints more than ½ inch and transverse joints more than ¼ inch from the true alignment.
B. Methods
1. Dry-cut saw method.
a. Install joints as soon as sawing equipment can be supported, and before uncontrolled cracking occurs.
b. Do not ravel the joints while sawing.
c. Do not saw a joint if a crack occurs at or near the joint location before sawing.
d. Discontinue sawing when a crack develops ahead of the saw.

2. Tooled.

C. Remove and place newly placed concrete where uncontrolled cracking occurs.
1. Do not saw a joint if a crack occurs at or near the joint location before sawing.
2. Discontinue sawing when a crack develops ahead of the saw.
3.2 CONTROL (CONTRACTION) JOINTS
A. Install control joints as shown and detailed in the drawings.
3.3 COLD JOINTS
A. In lieu of isolation joints and where indicated on the drawings, install base bond breaker. Install bond breaker per the manufacturer’s instructions.
B. Clean groove of foreign matter and loose particles after surface has dried.
SECTION 03 20 00 – CONCRETE REINFORCING
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes required concrete reinforcement product standards and installation of various types of concrete reinforcement.
1.2 SECTION REQUIREMENTS
A. Delivery, Storage, and Handling
1. Store reinforcement and accessories off the ground on platforms, skids, or other supports.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Reinforcing Bars.
1. Deformed, ASTM A615/A615M grade 60 bars and sizes as indicated
B. Dowel Bars.
1. Conform to AASHTO M 254, type A or B.
PART 3 - EXECUTION
3.1 DOWEL INSTALLATION
A. Use plain round bars, free from burring or other deformation restricting free movement in the concrete.
B. Dowel with lengths as indicated on the drawings. Immediately prior to placing the dowel, clean hole of dust and other deleterious material with a high pressure air hose. Fill hole halfway with epoxy or non-shrink grout, and insert dowel by rotating...
C. Install dowels in slabs on grade at locations indicated and at right angles to joint being doweled.
D. Accurately position and align dowels parallel to the finished concrete surface before concrete placement.
E. Rigidly support dowels during concrete placement.
SECTION 03 30 00 – CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes requirements for cast-in-place concrete for various placement applications.
1.2 SECTION REQUIREMENTS
A. Reference Sections:
1. 03 11 00 – CONCRETE FORMING AND ACCESSORIES
2. 03 15 16 – CONCRETE JOINTS
B. Submittals:
1. Concrete mix design (SD-05, Design Data), GA
2. Concrete testing results (SD-06, Test Reports), GA
C. Weather Limitations:
1. When air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes.
2. When air temperature is less than 40 deg F, use ACI 306 A Guide to Cold Weather Concreting. Submit a detailed plan for the producing, transporting, placing, protecting, curing, and temperature monitoring of concrete.
3. When rain is threatening during paving operations, stop paving operations and protect the concrete pavement from rain with plastic sheeting or other methods approved by the Contracting Officer. Remove, replace, or repair pavement damaged by rain or...

D. Ready-Mixed Concrete Producer Qualifications: ASTM C 94/C 94M.

PART 2 - PRODUCTS
2.1 MATERIALS
A. Portland Cement: ASTM C 150, Type I or II.
B. Aggregates: ASTM C 33, Class 3S coarse aggregate or better.
1. Maximum Coarse-Aggregate Size: 1-1/2 inches nominal.
2. Maximum Aggregate Size for Concrete in Insulating Concrete Forms: 3/4 inch.
C. Air-Entraining Admixture: ASTM C 260.
D. Chemical Admixtures: ASTM C 494, water reducing, high-range water reducing, water reducing and accelerating, and water reducing and retarding. Do not use calcium chloride or admixtures containing calcium chloride.
E. Synthetic Fiber: ASTM C 1116/C 1116M, Type III, polypropylene fibers, 1/2 to 1-1/2 inches long.
F. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.
2.2 CONCRETE MIXTURES
A. Normal-Weight Concrete:
1. Minimum Compressive Strength: 4000 psi at 28 days.
2. Maximum Water-Cementitious Materials Ratio: 0.45.
3. Slump Limit: 4 inches for concrete with verified slump of 3 to 5 inches before adding high-range water-reducing admixture or plasticizing admixture, plus or minus 1 inch.
4. Air Content: 4-6 percent.
5. Synthetic Fiber: 1.5 lb/CY.
B. Measure, batch, mix, and deliver concrete according to ASTM C 94.
1. Maintain temperature of the concrete mixture just before placement between 50 and 90 deg F.
2. Complete concrete discharge operations within 1-1/2 hours after the introduction of the mixing water to the cement and aggregates.
3. Adding water to the mix not permitted beyond the batching and mixing operations.
PART 3 - EXECUTION
3.1 CONCRETING
A. Compact subgrade and subbase to firm and stable surface.
B. Provide 24-hour notice of any concrete placement operations that will be occurring.
C. Place concrete in a continuous operation and consolidate using mechanical vibrating equipment.
1. Place concrete to avoid segregation of material.
2. Do not exceed 30 minutes between deliveries of batches for a single pour.
D. Protect concrete from physical damage, premature drying, and reduced strength due to hot or cold weather during mixing, placing, and curing. Repair and patch defective areas. Methods for protecting concrete, and repairing and patching defective are...
E. Being curing concrete slabs after finishing.
1. Cure concrete at least 7 days.
2. If high early strength cement is used, cure concrete at least 3 days.
3.2 FINISHES
A. Slab Finishes: Comply with ACI 302.1R for screeding, re-straightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces. Provide the following finishes:
1. Non-slip (medium-broom) finish to exterior concrete roadways.
3.3 CONCRETE JOINTS
A. Install control, isolation, and construction joints where indicated, and per 03 15 16 – CONCRETE JOINTS.
3.4 CONCRETE REPLACEMENT
A. Furnish concrete saws, drop hammers, hydro-hammers, and jack jammers to break concrete. Saws shall have sufficient power to saw full depth and complete the work with water-cooled, diamond-edged blades or abrasive wheels. Equip saws with blade guard...
B. Furnish equipment that will not damage the subgrade, subbase, base, or existing concrete slabs designated to remain.
C. If new or existing slabs not scheduled for replacement are chipped, spalled, or damaged during the removal operations, replace the damaged slabs at no cost to the Government.
D. Dowel into the sides of existing concrete, such as foundations, curb and gutter, and sidewalk.
3.5 FIELD QUALITY CONTROL
A. Provide independent certified testing agency, minimum Grade I ACI Concrete Field Testing Technician.
B. Concrete testing laboratory must have the necessary equipment and experience to accomplish required testing. The laboratory must meet the requirements of ASTM C 1077 and be CCRL inspected.
C. Upon arrival of the first concrete truck delivery:
1. Provide compressive strength testing, per AASHTO T-22 & T-23.
a. 1 set during the first concrete delivery.
b. Test two cylinders at 7 days; two cylinders at 28 days, and hold two cylinders in reserve.
2. Provide slump test at the site of discharge, per AASHTO T 119.
3. Provide air content test for air-entrained concrete per AASHTO T 152 or T 196.
4. Determine temperature of concrete at time of placement in accordance with ASTM C 1064.
contractorOrSub: Off
contractor:
address:
payrollNo:
weekEnding:
projectAndLocation:
projectOrContractorNo:
day1:
day2:
day3:
day4:
day5:
day6:
day7:
date1:
date2:
date3:
date4:
date5:
date6:
date7:
deductionLabel1:
deductionLabel2:
nameAddrSSN1:
noWithholdingExemptions1:
workClassification1:
OT11:
OT12:
OT13:
OT14:
OT15:
OT16:
OT17:
totalHoursOT1: 0
rateOfPayOT1:
ST11:
ST12:
ST13:
ST14:
ST15:
ST16:
ST17:
totalHoursST1: 0
rateOfPayST1:
rateOfPaySTfringe1:
gross1: 0
gross1T:
fica1:
withholding1:
deductionA1:
deductionB1:
deductionOther1:
totalDeductions1: 0
netWages1: 0
nameAddrSSN2:
noWithholdingExemptions2:
workClassification2:
OT21:
OT22:
OT23:
OT24:
OT25:
OT26:
OT27:
totalHoursOT2: 0
rateOfPayOT2:
ST21:
ST22:
ST23:
ST24:
ST25:
ST26:
ST27:
totalHoursST2: 0
rateOfPayST2:
rateOfPaySTfringe2:
gross2: 0
gross2T:
fica2:
withholding2:
deductionA2:
deductionB2:
deductionOther2:
totalDeductions2: 0
netWages2: 0
nameAddrSSN3:
noWithholdingExemptions3:
workClassification3:
OT31:
OT32:
OT33:
OT34:
OT35:
OT36:
OT37:
totalHoursOT3: 0
rateOfPayOT3:
ST31:
ST32:
ST33:
ST34:
ST35:
ST36:
ST37:
totalHoursST3: 0
rateOfPayST3:
rateOfPaySTfringe3:
gross3: 0
gross3T:
fica3:
withholding3:
deductionA3:
deductionB3:
deductionOther3:
totalDeductions3: 0
netWages3: 0
nameAddrSSN4:
noWithholdingExemptions4:
workClassification4:
OT41:
OT42:
OT43:
OT44:
OT45:
OT46:
OT47:
totalHoursOT4: 0
rateOfPayOT4:
ST41:
ST42:
ST43:
ST44:
ST45:
ST46:
ST47:
totalHoursST4: 0
rateOfPayST4:
rateOfPaySTfringe4:
gross4: 0
gross4T:
fica4:
withholding4:
deductionA4:
deductionB4:
deductionOther4:
totalDeductions4: 0
netWages4: 0
nameAddrSSN5:
noWithholdingExemptions5:
workClassification5:
OT51:
OT52:
OT53:
OT54:
OT55:
OT56:
OT57:
totalHoursOT5: 0
rateOfPayOT5:
ST51:
ST52:
ST53:
ST54:
ST55:
ST56:
ST57:
totalHoursST5: 0
rateOfPayST5:
rateOfPaySTfringe5:
gross5: 0
gross5T:
fica5:
withholding5:
deductionA5:
deductionB5:
deductionOther5:
totalDeductions5: 0
netWages5: 0
nameAddrSSN6:
noWithholdingExemptions6:
workClassification6:
OT61:
OT62:
OT63:
OT64:
OT65:
OT66:
OT67:
totalHoursOT6: 0
rateOfPayOT6:
ST61:
ST62:
ST63:
ST64:
ST65:
ST66:
ST67:
totalHoursST6: 0
rateOfPayST6:
rateOfPaySTfringe6:
gross6: 0
gross6T:
fica6:
withholding6:
deductionA6:
deductionB6:
deductionOther6:
totalDeductions6: 0
netWages6: 0
nameAddrSSN7:
noWithholdingExemptions7:
workClassification7:
OT71:
OT72:
OT73:
OT74:
OT75:
OT76:
OT77:
totalHoursOT7: 0
rateOfPayOT7:
ST71:
ST72:
ST73:
ST74:
ST75:
ST76:
ST77:
totalHoursST7: 0
rateOfPayST7:
rateOfPaySTfringe7:
gross7: 0
gross7T:
fica7:
withholding7:
deductionA7:
deductionB7:
deductionOther7:
totalDeductions7: 0
netWages7: 0
nameAddrSSN8:
noWithholdingExemptions8:
workClassification8:
OT81:
OT82:
OT83:
OT84:
OT85:
OT86:
OT87:
totalHoursOT8: 0
rateOfPayOT8:
ST81:
ST82:
ST83:
ST84:
ST85:
ST86:
ST87:
totalHoursST8: 0
rateOfPayST8:
rateOfPaySTfringe8:
gross8: 0
gross8T:
fica8:
withholding8:
deductionA8:
deductionB8:
deductionOther8:
totalDeductions8: 0
netWages8: 0
date:
nameOfSignatory:
title:
contractorCopy1:
building:
commenceDay:
commenceMonth:
commenceYear:
endDay:
endMonth:
endYear:
contractorCopy2:
txt1page2:
txt1page2line2:
txt1page2line3:
txt1page2line4:
fringe: Off
fringeCash: Off
exception1:
explanation1:
exception2:
explanation2:
exception3:
explanation3:
exception4:
explanation4:
exception5:
explanation5:
exception6:
explanation6:
exception7:
explanation7:
exception8:
explanation8:
remarks:
nameTitle:

File details come from the government source that posted it. Updated .