This document is an Infection Control Risk Assessment Guidelines for construction projects in a Department of Veterans Affairs healthcare facility. It outlines the different classes of construction projects (A-D) and patient risk groups (low, medium, high, highest), and matches them to the required infection control precautions (Classes I-V). The document provides detailed descriptions of the specific requirements for each precaution class, covering measures such as dust control, HVAC isolation, negative pressure, and waste containment. It also includes an Infection Control Construction Permit form for Class IV and V precautions, as well as a Daily Log template to document compliance with the prescribed infection control measures. This document sets the requirements for maintaining infection control during construction activities within the VA healthcare network.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INFECTION CONTROL RISK ASSESSMENT GUIDELINES – VA DESERT PACIFIC HEALTHCARE NETWORK
Identify the Type of Construction Project Activity (Types A-D) A Non-invasive activities, including, but not limited to:
a. Removal of ceiling tiles where no dust or asbestos is expected
b. Painting, but not sanding
c. Wall covering, electrical trim work, minor plumbing, and activities which do not generate dust or require cutting of walls or access to ceilings other than for visual inspection B Small scale, short duration activities which create minimal dust, including but not limited to:
a. Installation of electrical, plumbing, HVAC, telephone and computer cabling
b. Access to chase spaces where asbestos is not present
c. Cutting of walls or ceiling where dust migration can be controlled.
C Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies, including but not limited to:
a. Sanding of surfaces for painting or wall covering
b. Removal of floor coverings, ceiling tiles, and casework
c. New wall construction
d. Minor duct work or electrical work above ceilings
e. Major cabling activities
f. Any type A, B or C activity that cannot be completed within a single work shift.
D Major demolition and construction projects, including but not limited to:
a. Activities requiring heavy demolition or removal of a complete utility or cabling system
b. New construction and renovation.
c. Friable asbestos and mold abatement projects.
Identify the Patient Risk Group that will be affected. If more than one risk group will be affected, select the higher group. For all construction classes, patients must be removed from the room while work is performed.
Low
Medium High Highest Risk All outpatient clinics, offices areas, administrative and industrial spaces.
All non-critical inpatient areas.
cardiology, echocardiography, endoscopy, nuclear medicine, rehabilitation medicine, radiology, MRI, respiratory therapy, dry research labs.
DOU, emergency room, clinical laboratory, wet lab research, ambulatory surgery, pharmacy, surgical and medical inpatient beds, procedure center.
Immunocompromised patient area, cath lab, SPD, ICU, occupied, negative pressure rooms, PACU operating rooms.
Match the Patient Risk Group with the Construction Project Type (A, B, C, D) to find the Class of Precautions (I – V)
EXHIBIT L
Lessor: _______ Govt: _______ Exhbit L
Construction Project Type Patient Risk Group TYPE A TYPE B TYPE C TYPE D
Low Risk
I II III V
Medium Risk I II IV V High Risk I II IV V Highest Risk II III V V
Lessor: _______ Govt: _______ Exhbit L vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text
Description of Required Infection Control Precautions by Class
Class During Construction Project Upon Completion of Project
Class I
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace ceiling tile if displaced.
Class II 1. High Risk patients must remain out of room for one hour after completion of work and cleanup.
2. Execute work by methods to minimize raising dust.
3. Immediately replace ceiling tile if displaced.
1. Remove all visible debris with a wet towel and/or mop.
2. Housekeeping to wipe work surfaces and floors with disinfectant.
Class III 1. Execute work by methods to minimize raising dust.
2. Immediately replace ceiling tile if displaced
3. Provide active means to prevent airborne dust from dispersing into atmosphere.
4. Water-mist work surfaces to control dust while cutting.
5. Seal unused doors with duct tape.
6. Isolate HVAC system in areas where work is being performed to prevent contamination of duct system.
7. Place dust mat at entrance and exit of work area.
8. Cover construction waste before transport in covered containers
1. Cover construction waste before transport in covered containers.
2. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.
3. Open previously sealed HVAC registers and grills.
4. Housekeeping to wipe work surfaces and floors with disinfectant.
Class IV 1. Install plastic dust barriers to seal area from non-work area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.
2. Isolate HVAC system in areas where work is being performed to prevent contamination of duct system.
3. Maintain negative pressure within work site utilizing HEPA equipped air filtration units.
4. Place dust mat at entrance and exit of work area.
5. Cover construction waste before transport in covered containers.
6. All work associated with a major project that has an approved ICRA authorization form will be assessed on an individual basis.
1. Cover construction waste before transport in covered containers.
2. Wet mop and vacuum with HEPA filtered vacuum.
3. Do not remove barriers from work area until a Health System responsible person inspects completed project.
4. Remove barrier materials carefully to minimize spread of dirt and debris associated with construction.
5. Wet mop and vacuum with HEPA filtered vacuum before leaving work area.
6. Remove isolation of HVAC system in areas where work was being performed.
7. Housekeeping to wipe work surfaces and floors with disinfectant.
Class V 1. Construct gypsum board/metal stud dust partition, extend and seal to ceiling.
2. Isolate HVAC system within work areas to prevent contamination of duct system.
3. Seal doors opening to adjacent areas with duct tape.
4. Block off and seal HVAC registers, grills and any openings in ductwork to remain.
5. Maintain negative pressure within work site utilizing HEPA equipped air filtration units.
6. Place dust mat at entrance and exit of work area.
1. Cover construction waste before transport in covered containers.
2. Wet mop and vacuum with HEPA filtered vacuum.
3. Do not remove barriers from work area until a Health System responsible person inspects completed project.
4. Remove barrier materials carefully to minimize spread of dirt and debris associated with construction.
5. Wet mop and vacuum with HEPA filtered vacuum before leaving work area.
6. Remove isolation of HVAC system in areas where work was being performed.
7. Housekeeping to wipe work surfaces and floors with disinfectant.
Lessor: _______ Govt: _______ Exhbit L vhalonlestik Typewritten Text
7. Cover construction waste before transport in covered and sealed containers. Biohazards to be double bagged.
8. All work associated with a major project that has an approved ICRA authorization form will be assessed on an individual basis.
9. Provide monitoring and clearance samples for mold/asbestos.
INFECTION CONTROL CONSTRUCTION PERMIT FOR CLASS IV AND V PRECAUTIONS
Location of Activity: Project Start Date:
Project Coordinator: Estimated Duration:
Contractor Performing Work: Permit Expiration Date:
Supervisor: Telephone:
Construction Type:
Risk Group: Precaution Class:
Class I
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace ceiling tile if displaced.
3. Clean work area upon completion of task.
Class II 1. High Risk patients must remain out of room for one hour after completion of work and cleanup.
2. Execute work by methods to minimize raising dust.
3. Immediately replace ceiling tile if displaced.
4. Remove all visible debris with a wet towel and/or mop.
5. Housekeeping to wipe work surfaces and floors with disinfectant.
Class III 1. Execute work by methods to minimize raising dust.
2. Immediately replace ceiling tile if displaced
3. Provide active means to prevent airborne dust from dispersing into atmosphere.
4. Water-mist work surfaces to control dust while cutting.
5. Seal unused doors with duct tape.
6. Isolate HVAC system in areas where work is being performed to prevent contamination of duct system.
7. Place dust mat at entrance and exit of work area.
8. Cover construction waste before transport in covered containers
9. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.
10. Open previously sealed HVAC registers and grills.
11. Housekeeping to wipe work surfaces and floors with disinfectant.
Class IV 1. Obtain infection control permit before construction begins.
2. Install plastic dust barriers to seal area from non-work area or implement
7. All work associated with a major project that has an approved ICRA authorization form will be assessed on an individual basis using the Risk Assessment and Exposure Control
Lessor: _______ Govt: _______ Exhbit L control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.
3. Isolate HVAC system in areas where work is being performed to prevent contamination of duct system.
4. Maintain negative pressure within work site utilizing HEPA equipped air filtration units.
5. Place dust mat at entrance and exit of work area.
6. Cover construction waste before transport in covered containers.
Checklist.
8. Wet mop and vacuum with HEPA filtered vacuum.
9. Do not remove barriers from work area until a Health System responsible person inspects completed project.
10. Remove barrier materials carefully to minimize spread of dirt and debris associated with construction.
11. Wet mop and vacuum with HEPA filtered vacuum before leaving work area.
12. Remove isolation of HVAC system in areas where work was being performed.
13. Housekeeping to wipe work surfaces and floors with disinfectant.
14. Complete daily log documenting work activity and completion of remedial and preventive procedures required.
Class V 1. Obtain infection control permit before construction begins.
2. Construct gypsum board/metal stud dust partition, extend and seal to ceiling.
3. Isolate HVAC system within work areas to prevent contamination of duct system.
4. Seal doors opening to adjacent areas with duct tape.
5. Block off and seal HVAC registers, grills and any openings in ductwork to remain.
6. Maintain negative pressure within work site utilizing HEPA equipped air filtration units.
7. Place dust mat at entrance and exit of work area.
8. Cover construction waste before transport in covered containers.
9. All work associated with a major project that has an approved ICRA authorization form will be assessed on an individual basis using the Risk Assessment and Exposure Control Checklist.
10. Wet mop and vacuum with HEPA filtered vacuum.
11. Cover construction waste before transport in covered and sealed containers. Biohazards to be double bagged.
12. Provide monitoring and clearance samples for mold/asbestos.
13. Do not remove barriers from work area until a Health System responsible person inspects completed project.
14. Remove barrier materials carefully to minimize spread of dirt and debris associated with construction.
15. Wet mop and vacuum with HEPA filtered vacuum before leaving work area.
16. Remove isolation of HVAC system in areas where work was being performed.
17. Housekeeping to wipe work surfaces and floors with disinfectant.
18. Complete daily log documenting work activity and completion of remedial and preventive procedures required.
Exceptions or additions to this permit are noted on the attached page. Yes No Permit Requested By: Date: Approval By Service Affected: Date:
Approval by Safety Officer/IH: Date: Approval by Infection Control: Date:
VA Department of Veterans Affairs
DAILY LOG - FORMAL CONTRACT STATION:
PROJECT TITLE NAME OF CONTRACTOR
DATE CONTRACT NUMBER
DAY OF WEEK PROJECT NUMBER
WEATHER TEMPERATURE
BRANCH OF WORK SKILLED UNSKILLED LOCATION AND DESCRIPTION
WORKERS WORKERS OF WORK
DELIVERY OF MATERIALS:
REMARKS:
Barrier installed YES NO N/A Isolate HVAC YES NO N/A Seal Doors YES NO N/A Maintain negative pressure YES NO N/A Dust mat at entrance to work area YES NO N/A Cover construction waste for transport YES NO N/A Iwet mop, HEPA vacuum and inspectionprior to barrier removal YES NO N/A Remove construction barrier YES NO N/A Wet mop and HEPA vacuum YES NO N/A Reinstate HVAC YES NO N/A Wipe work surfaces with disinfectant YES NO N/A
Signature of Project Manager
Typewritten Text
VA Department of Veterans Affairs
DAILY LOG - SAFETY/ILSM CHECKLIST STATION:
PROJECT TITLE NAME OF CONTRACTOR
DATE CONTRACT NUMBER
DAY OF WEEK PROJECT NUMBER
Interim Life Safety Measure / Hazard Surveillance
Means of egress is clear in construction and adjacent areas. YES NO N/A Access for the fire department and emergency services is clear. YES NO N/A Note the status of the fire detection/sprinkler system Fire sprinkler system is active. YES NO N/A Fire alarm system is active. YES NO N/A Smoke detectors are active. YES NO N/A Temporary systems are in place YES NO N/A Construction partitions are being maintained and are smoketight. YES NO N/A Good housekeeping practices are being maintained. YES NO N/A Exterior balconies, corridors, and stairways clear of storage YES NO N/A Flammables & combustibles kept to a minimum and in proper containers. YES NO N/A Buildings, grounds, and equipment are maintained in a safe manner. YES NO N/A Smoking regulations are being followed. YES NO N/A Fire extinguisher are readily available in construction area. YES NO N/A Hot work permit issued YES NO N/A Work site inspected after hot work YES NO N/A Other Environmental Considerations / Hazard Surveillance Caution/ danger signs and barricades in place where needed. YES NO N/A Lock out/tagout in place YES NO N/A Extension cords protected/disconnected at end of day. YES NO N/A Dust barriers maintained. YES NO N/A MSDS maintained on site and products labeled. YES NO N/A Asbestos is properly controlled and interstitial doors are closed & locked. YES NO N/A Area is secured from public and at the end of the day. YES NO N/A Odors from construction operations are cleared. YES NO N/A Safety and temporary signage is in place. YES NO N/A Emergency recall numbers left at work site. YES NO N/A Utility systems returned to operation in occupied areas. YES NO N/A Construction storage/field offices maintained and secured. YES NO N/A Excavations properly barricaded. YES NO N/A All external openings in walls/roof are sealed from inclement weather YES NO N/A Exterior storm drains flushed and cleared of debris YES NO N/A Subcontractors aware/trained in safety/environmental issues YES NO N/A HEPA unit in place, functioning, and on E Power YES NO N/A Environmental monitoring for mold YES NO N/A
Inspected by:
Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text vhalonlestik Typewritten Text
VA Desert Pacific Healthcare System Project:
Date:
Hazard Concern? Y/N Control Measure Remarks Asbestos
Dust
Moisture/water leaks
Vapors/fumes
Noise
Vibration
Air pressure relationships
Traffic flow
Open outside walls
Impact to levels above and below
Proximity of air intakes
Pest control within construction area
Proximity of immune suppressed patients
Approval Signatures:
Project Manager: ______________________ Chief Engineering Section: _____________
Infection Control: _____________________ Industrial Hygienist: _____________________
Contractor: __________________________ Service/Section/Program Chief: _____________
Control Measures
Asbestos
1. Contractor has hired an asbestos abatement contractor for control and cleanup.
2. VA to hire independent IH to inspect and clear area for re-occupancy based on monitoring and/or professional judgment.
3. Published asbestos protocol to be followed for work thru ceiling.
4. Published asbestos protocol to be followed for work above ceilings.
5. Perimeter barrier will be constructed in the interstitial space to isolate the construction area with other areas in the interstitial.
6. Project area will be encased with spray applied hard surface encasement material.
7. Provide mini containments under negative air in public areas.
8. Sealed gypsum board barrier will be constructed to isolate the construction area from the public.
9. Transit Panels will be removed which is considered Class B removal
Dust
1. Sealed gypsum board barrier will be constructed to isolate the construction area from the public.
2. Trash carts will be covered when transported thru the building.
3. Provide negative air machine exhausted to outside.
4. Provide mini containments under negative air in public areas.
5. Provide negative air machine in space as air scrubber.
6. Provide walk off mats at entrances to work area
7. Perimeter barrier will be constructed in the interstitial space to isolate the construction area with other areas in the interstitial.
Moisture Water Leaks
1. Contain any water from core drilling activities.
2. Dike any floor penetrations to minimize risk of leaks from construction zone.
Vapors/Fumes
1. Use of products with low VOC’s.
2. Provide negative air in construction zone exhausted to outside away from intakes.
3. Seal work area airtight barrier.
4. Cut all metal outside the building.
5. Seal any floor penetrations to minimize risk of fumes thru construction zone.
6. Shut down air handler to minimize infiltration of fumes from outside.
Noise
1. Schedule demolition work after normal work hours.
2. Cut all metal outside the building.
Vibration
1. Schedule demolition work after normal work hours.
2. Coordinate with occupants in surrounding areas to explain the work occurring
Air Pressure Relationships
1. Provide negative air during asbestos abatement.
2. Provide negative air during construction
3. Seal off supply and exhaust HVAC registers.
4. Provide anti room under negative pressure at entrance to project zone.
Typewritten Text vhalonlestik Typewritten Text
Traffic Control
1. Access construction area via exterior door.
2. Schedule delivery of large quantities of material and demolition haul out after hours.
Open Outside Walls
1. Construct temporary outside wall to limit the infiltration of wind, air, and temperature differences into the project site.
Impact to Levels Above and Below
1. Coordinate with occupants in surrounding areas to explain the work occurring.
2. Follow asbestos protocol when doing under floor work
3. Vacate areas when doing below floor work off of the catwalk.
Proximity of Air Intakes
1. Shut down air handlers to reduce infiltration of fumes from exterior activities such as painting, gasoline powered engines, roofing operations, equipment, etc.
Pest Control Within Construction Area
1. Provide barriers to any open outside walls
2. Contact Pest Controller if any evidence of pests are found during the course of the work.
Proximity of immune suppressed patients
1. Relocate patients away from construction zone for entire project.
2. Relocate patients away from construction zone during demolition operations.
| LONG BEACH, CALIFORNIA 90815 |
| Issuing Office: |
| Express Mail, Regular Mail or Hand Delivered to: |
| 2. AMOUNT AND TYPE OF SPACE |
| 3. QUALITY AND APPEARANCE OF BUILDING (AUG 2008) |
| 4. BUILDING SHELL REQUIREMENTS (AUG 2008) |
| 5. submissions (AUG 2008) |
| 6. AWARD (AUG 2008) |
| 7. OTHER AWARD FACTORS (AUG 2008) |
| 8. SPECIAL REQUIREMENTS – see Schedule A, B, and C |
| 9. unique requirements |
| 10. LOCATION: INSIDE OR OUTSIDE CITY CENTER (AUG 2008) |
| 11. SCHEDULE OF PERIODIC SERVICES |
| 12. NOVATION AND CHANGE OF NAME (AUG 2008) |
| 13. CENTRAL CONTRACTOR REGISTRATION (AUG 2008) |
| 14. WAIVER OF RESTORATION (AUG 2008) |
| 15. labor standards (aug 2003) |
| 16. ATTACHMENTS |
| SOLICITATION PROVISIONS |
| (Acquisition of Leasehold Interests in Real Property) |
| 1. 552.270-1 - INSTRUCTIONS TO OFFERORS – ACQUISITION OF LEASEHOLD INTERESTS IN REAL PROPERTY (MAR 1998) |
| Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal. |
| 2. 552.270-3 - PARTIES TO EXECUTE LEASE (SEP 1999) |
| 3. 52.233-2 - SERVICE OF PROTEST (AUG 1996) (VARIATION) |
| 4. 852.233-70 - PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (JAN 2008) |
| 5. 852.233-71 - ALTERNATE PROTEST PROCEDURE (JAN 1998) |
| 6. 52.215-5 - FACSIMILE PROPOSALS (OCT 1997) |
| 7. FLOOD PLAINS AND WETLANDS (APR 1984) |
| EXISTING BUILDING |
| SCHEDULE B: BUILDING REQUIREMENTS TO BE INCLUDED IN |
| RENTAL RATE |
| GENERAL REQUIREMENTS - ALL AREAS |
| CEILINGS |
| FIRE SAFETY |
| The Lessor shall provide the GOVERNMENT with a management plan for inspection, testing, and maintenance of the building(s) utility systems and features of fire protection within two weeks of the effective date of the lease. This plan should describe ... |
| The Lessor shall routinely provide the GOVERNMENT with written documentation of the completed preventive maintenance, testing, and inspection activities for fire protection systems and features. The Lessor shall also routinely provide copies of inspe... |
| The Lessor shall immediately communicate to the GOVERNMENT any building equipment problems identified that could negatively affect the safety or health or patients, staff and other people coming to the facilities, as well as a plan to resolve each issue. |
| FINISHES |
| DOORS |
| WALL PARTITIONS |
| WINDOW BLINDS/SOLAR FILM |
| HEATING VENTILATING AND AIR CONDITIONING |
| PLUMBING |
| ELECTRICAL |
| TELEPHONE /DATA |
| LIGHTING |
| ASBESTOS |
| SECURITY SYSTEM |
| SIGNAGE |
| PARKING |
| SPECIFIC REQUIREMENTS BY ROOM |
| 2. Dispenser, paper towel, multifold, stainless steel, wall mounted 40" above floor |
| TELE/COMPUTER ROOM |
| Break /Storage Room |
| 1. Cabinet, wall mounted, two shelves, 60" Wx16"D x 40"H. |
| 2. A six foot counter with sink, hot and cold water. Cabinets above sink 4ft x 6ft |
| 3. Dispenser, paper towel, multifold, stainless steel, wall mounted 40" above floor. |
| 4. Mop rack, wall mounted, and waterline for refrigerator. |
| RESTROOM 1 - 2 |
| 1. Restrooms must meet ADA requirements. |
| 2. Dispenser, toilet tissue |
| 3. Lavatory, wall hung with faucet |
| 4. Dispenser, paper towel, multifold, stainless steel, wall mounted 40" above floor. |
| 5. Dispenser, soap, plastic, wall mounted. |
| 6. Mirror, over lavatory |
| 7. Privacy lock on door |
| SCHEDULE C: SERVICES, UTILITIES, MAINTENANCE TO BE |
| INCLUDED IN RENTAL RATE |
| GENERAL |
| NORMAL HOURS |
| OVERTIME USAGE |
| UTILITIES |
| MAINTENANCE |
| MAINTENANCE DOCUMENTATION |
| CLEANING SERVICES |
| Daily |
| Sweep entrances and sidewalks adjacent to entrances. |
| Weekly |
| Quarterly |
| Semi Annually |
| Wash all windows and doors inside and out. |
| Annually: |
| As directed by the Office Manager/Lessor: |
| Wash walls in waiting rooms and group rooms. |
| Wash all mini blinds. |
| TRASH OR SOLID WASTE DISPOSAL/REMOVAL |
| SCHEDULE OF PERIODIC SERVICES |
| Infection Control Construction Permit For Class IV and V Precautions |
| 1. EXISTING FIT-OUT, SALVAGED, OR RE-USED BUILDING MATERIAL (SEP 2000) |
| 2. JANITORIAL SERVICES (AUG 2008) |
| 3. RECYCLED CONTENT PRODUCTS (COMPREHENSIVE PROCUREMENT GUIDELINES) (SEP 2000) |
| 4. ENVIRONMENTALLY PREFERABLE BUILDING PRODUCTS AND MATERIALS (DEC 2007) |
| 5. WOOD PRODUCTS (AUG 2008) |
| 6. ADHESIVES AND SEALANTS (SEP 2000) |
| 7. ENERGY COST SAVINGS (AUG 2008) |
| 8. PAINTING (DEC 2007) |
| 9. CARPET: BROADLOOM (AUG 2008) |
| 10. CARPET TILE (AUG 2008) |
| 11. RECYCLING (DEC 2007) |
| Highest Risk |
| TYPE A |
| TYPE B |
| TYPE C |
| TYPE D |
| High |
| Medium |
| Low Risk |
| Class I |
| Construction Type: |
| Class I |
| Exceptions or additions to this permit are noted on the attached page. Yes No |
| Signature of Project Manager |
File details come from the government source that posted it. Updated .