About this file

This is a Construction Overhead Cost Breakdown exhibit (Exhibit E) for a Design-Build project at Georgia Institute of Technology in Atlanta, Georgia. The document provides a detailed template for bidders to itemize construction overhead costs across multiple categories including site supervision and management, site office expenses, safety and security, bonds and insurance, and miscellaneous costs. The breakdown requires contractors to specify quantities, labor costs, material costs, and subcontractor costs for each line item, with subtotals and notes sections for clarification. The form explicitly states that any attempts to recategorize items as "Fee," "Cost of Work," or "By Others" will render the proposal non-responsive, ensuring proper cost allocation and transparency in overhead estimation.

The exhibit references a projected fee of $1,231,000 based on a $46 million Guaranteed Maximum Price (GMP), with a grand total line for all general contractors' costs and fees. Currently, all cost fields in the template are populated with $0 values, indicating this is a blank form awaiting contractor completion during the bidding process for Project No. BR-30-2206-DB "Ferst Drive Corridor Realignment." The document serves as the standardized cost breakdown mechanism to ensure consistent proposal evaluation and prevent cost miscategorization among competing bidders.

Text of this file

Attach. B - Const. OH Cost)

EXHIBIT E
Fill-in all applicable costs, any attempts to recategorize any of these items as "Fee", "Cost of Work", or "By Others" will be treated as a non-responsive proposal.
CONSTRUCTION OVERHEAD COST BREAKDOWN
DescriptionQtyUnitLabor*Mat'l**SubLabor SubtotalMat'l SubtotalSub SubtotalTotalNotesQtyUnitLabor*Mat'l**SubLabor SubtotalMat'l SubtotalSub SubtotalTotalNotes
Site Supervision & Management:
1Senior Project Mgr.mos$0$0$0$0$0$00$0
2Project Mgr.mos$0$0$0$0$0$00$0
3Project Supt.mos$0$0$0$0$0$00$0
4Asst. Project Supt.mos$0$0$0$0$0$00$0
5Area Supt.mos$0$0$0$0NA
6Secretarymos$0$0$0$0$0$00$0
7Project Engineermos$0$0$0$0$0$00$0
8Engineer or Eng. Companymos$0$0$0$0$0$00$0
9Cost Controlmos$0$0$0$0$0$00$0
10Safety Engineermos$0$0$0$0$0$0
11Schedulingmos$0$0$0$0$0$0
12Purchasingmos$0$0$0$00$30,000
13Project Accountantmos$0$0$0$0$0$00$0
140$0
15Incl.
Subtotal$0$0$00$0
$30,000
Site Office Expense:
18Job Office Trailer Rentmos$0$0$0$0
19Office Jobsite Build Outls$0$0$0$0NA
20Office Jobsite Set-upls$0$0$0$0$0$00$0
21Temp. Const. Trailer/Storageea$0$0$0$0$0$00$0
22Office Furniturels$0$0$0$0NA
23Office Machines/Equip.mos$0$0$0$0Incl. Below
24Copy Machines/Maintenancemos$0$0$0$0$0$00$0
25Office Suppliesmos$0$0$0$0Incl. Above
26Janitor/San. Suppliesmos$0$0$0$0$0$00$0
27Postage & Shippingmos$0$0$0$0$0$0
28First Aid/Med. Treat.mos$0$0$0$0$0$00$0
29Telephone Systemls$0$0$0$0$0$0
30Phone Installationls$0$0$0$0$0$00$0
31Phone Chargesmos$0$0$0$00$0
32Phone Charges-Long Dist.mos$0$0$0$00$0
33Radio Communicationsea$0$0$0$0By Arch.
34Radio Maintenancels$0$0$0$0$0$00$0
35Computer-PCSmos$0$0$0$0Incl.
36Computersmos$0$0$0$0$0$00$0
37Softwareallow$0$0$0$0Incl.
38MIS Chargesmos$0$0$0$0
39Temp. Electric-Officemos$0$0$0$0
40Security-Officemos$0$0$0$0$0$00$0
41Water - Field Officemos$0$0$0$0
42
430$0
Subtotal$0
$0
Safety & Security:
43Safety Incentivesls$0$0$0$0
44Watchman/Guard Ser.ls$0$0$0$0NA
45Traffic Controlls$0$0$0$00$0
46Safety Equipmentls$0$0$0$0$0$00$0
47Rainwear/Hardhats, etc.ls$0$0$0$0$0$00$0
48Drug Testingea$0$0$0$00$0
49$0$0$0$0$0$00$0
50$0$0$0$00$0
Subtotal$0
$0
Bonds & Insurance:
51Perform. & Payment Bondsmos$0$0$0$00$0
52Workers Comp. Insurancemos$0$0$0$0Incl.
53Liability Insurancemos$0$0$0$0$0$00$0
54Fed. & State Unemploymentmos$0$0$0$0$00$0
55FICAmos$0$0$0$0
56Builders Risk Insurancemos$0$0$0$00$0
57
58
Subtotal$0
$0
Miscellaneous
59Off-Site Parkingmos$0$0$0$0
60Ceremony Expensels$0$0$0$0
61Vehicle for On-Site Project Managermos$0$0$0$0
62Vehicle for On-Site Superintendentmos$0$0$0$0
63Vehicle Repairs/Maintenancels$0$0$0$00$0
64Water - Coolersmos$0$0$0$0Incl.
65Water Barrelsmos$0$0$0$0$0$00$0
66Ice Machinemos$0$0$0$0NA
67Ice and/or Cupsls$0$0$0$0NA
68Temporary Toilets Installea$0$0$0$0NA
69Temporary Toiletsmos$0$0$0$0$00$0
70Cold Weather Protectionls$0$0$0$0Incl.
71Temp. Heat for Bldg.ls$0$0$0$0$00$0
72Job Signsea$0$0$0$0Incl.
73Progress Photosea$0$0$0$00$0
74Extra Plans & Specs.ea$0$0$0$00$0
75Blueprint/Photostat.allow$0$0$0$0Incl.
76Temp. Electric -Buildingmos$0$0$0$0$0$00$0
77Building Permitls$0$0$0$0Incl.
78Plan Check Feesls$0$0$0$0NA
79NA
80NA
Subtotal$0
TOTAL ALL CONSTRUCTION OVERHEAD COSTS:$0
108Projected Fee (Based on $46 Million GMP)
$1,231,000
109Grand Total GCs & Fee$0
ERROR:#REF!

&D &T &P

Sheet2

Sheet3

Other files

File Type Posted
Award Information —
Exhibit A —
Exhibit D —
Exhibit G —
Exhibit C —
GIT BR-30-2206-DB RFQ-RFP —
Egnyte Upload Instructions —
Exhibit B —
Exhibit F —
GIT BR-30-2206 Addendum No. 1 —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .