Exhibit C Draft Statement of Work.pdf

PDF 164 KB Posted

Attached to
California Gulch Groundwater Monitoring
Solicitation number
RFP FAAA 2027000068 1
Issued by
Denver County, Denver City, Colorado

About this file

This is a Draft Statement of Work for the California Gulch Groundwater Monitoring project, involving the Colorado Department of Public Health and Environment (CDPHE), the United States Environmental Protection Agency (EPA), and Colorado Mountain College's Natural Resource Management Program. The project provides technical support and monitoring services at the California Gulch Superfund Site, a 18-square-mile area in and around Leadville, Lake County, Colorado, at an elevation of approximately 10,000 feet. The site encompasses 12 Operable Units and addresses environmental contamination resulting from over 100 years of heavy industrial mining, mineral processing, and smelting that has created acidic, metal-laden groundwater. The contractor must attend a kickoff meeting no later than 60 days following contract execution and conduct comprehensive groundwater monitoring activities, including maintaining and operating continuous groundwater monitoring equipment, downloading quarterly data, providing quarterly reports, updating the California Gulch website at californiagulch.us, maintaining a Geostationary Operational Environmental Satellites agreement, and sustaining an Early Alert System at designated monitoring locations. Quarterly Groundwater Level Monitoring Reports must be submitted to the CDPHE Project Manager no later than one month following each quarter reported, with the Project Manager required to approve or request changes within 21 calendar days and the contractor obligated to submit revisions within 14 calendar days thereafter.

The Statement of Work does not specify pricing terms, set-aside information, or incumbent details. The contractor must maintain continuous groundwater monitoring equipment including transducers and water level meters, and quarterly reports must include summaries of groundwater level data and groundwater elevation plots. The CDPHE Project Manager will monitor contract compliance throughout the contract period through documentation review, progress reports, and quarterly reports. Non-compliance issues will be addressed through a structured resolution process requiring written notification within ten calendar days of discovery, with both parties collaborating within fifteen calendar days to determine corrective actions and establish completion timelines. If the contractor demonstrates inaction or disregard for the agreed-upon compliance resolution plan, the State may exercise its contractual rights.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT C

Choose an item.Click or tap here to enter text. Ver. 01.11.19

DRAFT STATEMENT OF WORK

These provisions are to be read and interpreted in conjunction with the provisions of the contract specified above.

I. Project Description:

This project serves to provide technical support of activities at the California Gulch Superfund Site. The activities will include support services for monitoring and assessing groundwater conditions across CalGulch.

Placer gold was discovered in the California Gulch area in 1860. Subsequent discovery of silver bearing lead carbonate ore initiated over 100 years of heavy industrial mining, mineral processing and smelting. Acidic, metal laden water from the historically mined area flows through the shallow groundwater and down

California Gulch approximately six miles to its confluence with the Arkansas River.

The California Gulch was placed on the National Priorities List (Superfund) in 1983. The California Gulch

Superfund Site (“CalGulch”) encompasses about 18 square miles in and around Leadville, in Lake County, Colorado, at an elevation of about 10,000 feet. The United States Environmental Protection Agency (EPA) is the lead agency for CalGulch and the Colorado Department of Public Health and Environment (CDPHE) is the cooperating agency. Colorado Mountain College’s Natural Resource Management Program provides field and logistical services to both the EPA and CDPHE.

CalGulch was divided into 12 Operable Units. Additional work of this project is to provide recommendations for the improvement of the monitoring program and for Operable Units to maintain effectiveness. The majority of the Record of Decision mandated activities have been completed at CalGulch. The Record of

Decision is a publicly accessible document.

II. Definitions:

1. CDPHE Colorado Department of Public Health and Environment

2. CalGulch California Gulch Superfund Site

3. EPA United States Environmental Protection Agency

4. O&M Operations and Maintenance

III. Work Plan:

Goal #1: To improve the quality of the environment and public health for the citizens of Colorado by continuously improving efforts to for proper management of hazardous materials and waste.

Objective #1: No later than the expiration of this contract, the Contractor shall provide technical support for activities at

CalGulch.

Primary Activity #1

The Contractor shall attend a kick off meeting no later than 60 days following the execution of this contract.

Primary Activity #2

The Contractor shall conduct groundwater monitoring

Choose an item.Click or tap here to enter text. Ver. 01.11.19

Sub-Activities #2

1. The Contractor shall maintain and operate continuous groundwater monitoring equipment.

2. The Contractor shall download continuous groundwater level monitoring data quarterly.

3. The Contractor shall provide a quarterly report of continuous groundwater level monitoring data.

4. The Contractor shall update the California Gulch Website at calforniagulch.us.

5. The Contractor shall maintain the Geostationary Operational Environmental Satellites agreement with Upper Arkansas Water Conservancy District, National Oceanic and

Atmospheric Administration, and Data Collection System

6. The Contractor shall maintain the Early Alert System.

Standards and

Requirements

1. The content of electronic documents located on CDPHE and non-CDPHE websites and information contained on CDPHE and non-CDPHE websites may be updated periodically during the contract term. The contractor shall monitor documents and website content for updates and comply with all updates.

2. The Contractor shall submit all deliverables and correspondence to the CDPHE Project

Manager via email.

a. The CDPHE Project Manager will approve the deliverable or request changes within 21 calendar days.

b. The Contractor shall update the deliverable to include any requested changes within 14 calendar days.

c. The Contractor shall submit the updated deliverable to the CDPHE Project

Manager by the close of business on the 14th day following the receipt of requested changes from the CDPHE Project Manager.

d. The CDPHE Project Manager may approve extensions to the Contractor’s deliverables schedule via email for extenuating circumstances.

3. The continuous groundwater monitoring equipment shall include:

a. Transducers

b. Water level meters

4. The Contractor shall include at a minimum the following in the Quarterly Groundwater

Level Monitoring Report:

a. A summary of groundwater level data.

b. Groundwater elevation plots.

5. The Contractor shall maintain the California Gulch Stream Data website located at calforniagulch.us and provide updated site data of the following:

a. California Gulch near Malta

b. Gaw Shaft Well, SPR-23

c. Leadville Mine Drainage Tunnel 36+77

d. Leadville Mine Drainage Tunnel 46+66

e. Marian Ditch Near Leadville

6. The Early Alert System shall be at the following groundwater monitoring locations:

a. LDT36+77

b. LDT46+66

Expected Results of

Activity(s)

1. Real-time monitoring of groundwater conditions at the Site.

file:///C:/Users/nfelton/Downloads/californiagulch.us file:///C:/Users/ksandor/Desktop/californiagulch.us

Choose an item.Click or tap here to enter text. Ver. 01.11.19

Measurement of Expected

Results

1. Quarterly reporting.

Completion Date

Deliverables

The Contractor shall submit quarterly Groundwater Level Monitoring

Reports to the CDPHE Project Manager.

No later than 1 month following the quarter being reported, not to exceed the expiration of this

IV. Monitoring:

CDPHE’s monitoring of this contract for compliance with performance requirements will be conducted throughout the contract period by the CDPHE Project Manager. Methods used will include a review of documentation determined by CDPHE to be reflective of performance to include progress reports, quarterly reports and other fiscal and programmatic documentation as applicable. The Contractor’s performance will be evaluated at set intervals and communicated to the contractor. A Final Contractor Performance

Evaluation will be conducted at the end of the life of the contract.

V. Resolution of Non-Compliance:

The Contractor will be notified in writing within ten (10) calendar days of discovery of a compliance issue.

Within fifteen (15) calendar days of discovery, the Contractor and the State will collaborate, when appropriate, to determine the action(s) necessary to rectify the compliance issue and determine when the action(s) must be completed. The action(s) and time line for completion will be documented in writing and agreed to by both parties. If extenuating circumstances arise that requires an extension to the time line, the

Contractor must email a request to the CDPHE Project Manager and receive approval for a new due date.

The State will oversee the completion/implementation of the action(s) to ensure time lines are met and the issue(s) is resolved. If the Contractor demonstrates inaction or disregard for the agreed upon compliance resolution plan, the State may exercise its rights under the provisions of this contract.