This document is an Attachment outlining the Status Reporting Requirements for a federal contract opportunity. The key details include:
The status report must include the contract number, funded amount (funds expended, funds remaining, percentage expended and remaining), period of performance (start/end dates, days elapsed and remaining, percentage elapsed and remaining), mechanic time tracking (straight time and overtime hours expended and remaining), management time tracking (hours expended and remaining), and projections (projected funded fully expended date, mechanic straight time and overtime hours expended dates). The report must also include graphical representations of the actual, budgeted, and forecasted straight time hours, overtime hours, and funds expended.
The related federal contract opportunity is for Touch Labor Shipfitter support services at the Portsmouth Naval Shipyard. The solicitation seeks 15 experienced Marine Shipfitter personnel, along with supervisors and a Program Manager, to assist with submarine overhaul, modernization, and repair work. The period of performance is from August 5, 2024 to May 23, 2025. Work will be performed on-site at the Portsmouth Naval Shipyard.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 1-DD254.pdf | ||
| DD1423 CDRL A001- A004.pdf | ||
| Exhibit A004-Onboarding and Offboarding.xlsx | XLSX spreadsheet | |
| Attachment 8 - Wage Determination.pdf | ||
| Attachment 3-List of Identity Proofing Documents.pdf | ||
| Attachment 6-Quality Assurance Surveillance Plan.pdf | ||
| Exhibit A003-Contractor Weekly Reporting Hours.xlsx | XLSX spreadsheet | |
| Attachment 5-Past Performance Report Form.doc | DOC document | |
| Attachment 4-Past Performance Information Form.doc | DOC document | |
| N3904024R0145 Solicitation.pdf | ||
| Attachment 2-SECNAV 5512-1.pdf | ||
| Exhibit A005-Contractor Employee Injury Report.pdf | ||
| Exhibit A002-Contracted Employee Timesheet.docx | DOCX document | |
| DD1423 CDRL A005.pdf | ||
| Attachment 7-QASP Matrix.xlsx | XLSX spreadsheet |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1
Attachment 1 – Status Report Requirements
Status Reporting Requirements
Items to include in status report:
1. Contract number.
2. Contract number.
3. Data date for data being used.
4. Funded amount.
a. Funds expended to date.
b. Funds remaining.
c. Percentage of funds expended to date.
d. Percentage of funds remaining.
5. Period of performance.
a. PoP Start Date.
b. PoP End Date.
c. Days PoP elapsed.
d. Days PoP remaining.
e. Percentage PoP elapsed.
f. Percentage PoP remaining.
6. Mechanic Time Tracking.
a. Straight time hours expended in reporting period (week).
b. Straight time hours expended to date.
c. Straight time hours remaining.
d. Overtime hours expended in reporting period (week).
e. Overtime hours expended to date.
f. Overtime hours remaining.
Attachment 1
Attachment 1 – Status Report Requirements
7. Management Time Tracking.
a. Hours expended in reporting period (week).
b. Hours expended to date.
c. Hours remaining.
8. Projections.
a. Projected funded fully expended date.
b. Projected mechanic straight time hours expended date.
c. Projected mechanic overtime hours expended date.
9. Graphical Representations (Updated Weekly)
a. Graph #1: Actual Straight Time Hours, Budgeted Straight Time Hours, Forecasted Straight Time
Hours.
b. Graph #2: Actual OT Hours, Budgeted OT Hours, Forecasted OT Hours.
c. Graph #3: Actual Funds Expended, Budgeted Funds Expended, Forecasted Funds Expended.
Graphical Data Representation Example: