Summary: Exhibit A Scope of Work - Landscaping Services
This is a Scope of Work document issued by the Idaho Division of Veterans Services for landscaping services at the Idaho State Veterans Home-Pocatello (ISVH-P). The contractor shall maintain the landscaping and grounds to ensure they remain neat, clean, and healthy. Services are to be performed during normal business hours of Monday through Friday, 8:00 a.m. to 5:00 p.m. MST, or outside these hours with prior approval from the Maintenance Supervisor, provided that work does not disturb residents through noise or other disturbances. The scope encompasses general landscaping maintenance including mowing, edging, trimming, pruning, monitoring sprinkler systems, debris control and removal, weed control, fertilization, and insect and disease control. Contractor personnel must be trained in industry-standard landscaping techniques with knowledge of local soil and climate requirements, proper chemical and insecticide use, and proper procedures for cutting, trimming, watering, and cultivating vegetation. The contractor is responsible for furnishing all labor, equipment, supplies, tools, materials, and OSHA-compliant personal protective equipment. The contractor must maintain current Idaho applicator licenses for herbicide and insecticide chemical spraying and provide detailed records of all services weekly to the Maintenance Supervisor.
Performance requirements include maintaining grass height between two and three inches, completing trimming on the same day as mowing, removing all debris prior to mowing, hand-pulling weeds around sensitive plants, applying pre- and post-emergence herbicides according to label directions, performing weekly deadheading of flowers, and monitoring sprinkler systems for appropriate water application. All chemicals used must be applied by or under direct supervision of a Certified Pesticide Applicator, with Safety Data Sheets maintained and provided prior to first application. All contractor personnel must wear clearly identified uniform shirts, and no unauthorized persons may accompany workers. The contractor must remove all natural vegetation and inorganic debris from the site and dispose of materials at proper facilities meeting applicable federal, state, and local requirements. The contractor is responsible for replacing or repairing any property damaged during work. ISVH-P will commence formal performance assessments thirty days after contract commencement through random no-notice visual inspections, with the contractor required to re-accomplish any incomplete or incorrectly completed tasks at no additional cost. Non-compliance may result in ISVH-P procuring services and recovering all costs from the contractor.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Idaho Division of Veterans Services Event 1212
Exhibit A
Scope of Work for Landscape Services Pocatello
Services. Contractor must maintain the landscaping and grounds of the Idaho State Veterans Home- Pocatello (ISVH-P) to keep the landscaping and grounds are neat, clean, and healthy. Services shall be conducted during normal business hours of Monday through Friday 8:00 am to 5:00 pm MST or outside of normal business hours with the prior approval of the Maintenance Supervisor or his designee. Work conducted after normal business hours must not interrupt residents of the home (including but not limited to the disturbance from high noise levels such as mowers and blowers).
Maintenance services:
1. The Contractor and all personnel providing service must be trained in industry-standard landscaping techniques and procedures, with knowledge of local area soil and climate requirements for all grass, shrubs, and plants; proper use of chemicals and insecticides; and proper procedures for cutting, trimming, watering, and cultivating shrubs and trees.
2. Contractor shall furnish all labor, equipment, supplies, tools, and materials; as well as all personal protective equipment (PPE) (all PPE equipment, gloves, protective eyewear, masks, etc.)
which must be Occupational Safety and Health Administration (OSHA) compliant to perform the landscaping required below. Contractor must provide copies of all applicable required Idaho applicator licenses for herbicide and insecticide chemical spraying. General landscaping will be mowing, edging, trimming, pruning, monitoring sprinkler systems, debris control and removal, and overall landscaping care for ISVH-P.
3. Contractor shall immediately advise the Maintenance Supervisor, Rickey Frandsen at 208-235- 7881 or designated staff if there are any issues or concerns with any of the ISVH-P premises.
Contractor shall be responsible for replacing or repairing to original condition, at their expense, any property damaged by the Contractor.
4. Contractor shall provide detailed records of all services provided to the Maintenance Supervisor or designated staff by email (provided to Contractor by ISVH-P prior to contract start date) after each weekly occurrence, in a format designated by ISVH-P.
5. Contractor’s Manager/Supervisor shall schedule a monthly inspection of the areas designated for landscaping with Maintenance Supervisor or designated staff to ensure quality of landscaping is at the standard of ISVH-P.
6. Contractor shall maintain and keep current the Safety Data Sheet (SDS) on all chemicals (hazardous or non-hazardous substances) used at ISVH-P. A copy must be provided to the Maintenance Supervisor or designated staff prior to first time application of chemical.
7. All Contractor’s personnel must wear a “uniform” shirt while performing landscaping services at ISVH-P. The “uniform” shirt must clearly identify the individual as an employee of the Contractor.
8. No persons, other than Contractor or employees of the Contractor, shall accompany the Contractor’s personnel while performing work under the contract.
9. Definitions. The Contractor shall perform the services below and meet the requirements as identified for each service. ISVH-P trash bins are not permitted for use by contractor.
9.1. Mowing: Grass must be cut no lower than two inches (2”) and left no higher than three inches (3”). Any bare ground areas may become populated with grass or weeds through natural spread (i.e. not artificially planted) thus these areas must be cut also. Grass cutting must be done such that it is free of scalping, rutting, bruising, uneven and rough cutting. Only exception to the height stated above is during extreme drought and/or high temperatures.
9.1.2. Prior to mowing, the Contractor must remove and dispose of all rubbish, debris, and trash, which includes but is not limited to leaves, rocks, paper, and other removable objects on the ground and any tree or shrubbery areas.
9.1.3. Trimming: All grass under and around trees, shrubbery, fences, poles, walls, sprinkler heads, valves, asphalt, or concrete paved areas including sidewalks, walkways, shrubs or any other permanent structure must be trimmed to match the height and appearance of the surrounding mowed grass.
9.1.3.1 Trimming must be done on the same day as grass cutting. Grass cutting will not be considered complete until all trimming operations are accomplished.
9.1.4. Fertilization: Fertilization must be done in accordance with the predominant grass type for that area. An application rate must be selected that will prevent damage to the grass due to unnecessary over fertilization.
9.1.5. Weed Control: Pre-emergent herbicide must be applied to control both annual and perennial grassy and broadleaf weeds in accordance with label directions. If weeds appear, control will be provided with post-emergence herbicides in accordance with label directions. Use non-selective and/or pre-emergent herbicides as necessary for expansion joints and cracks of paved surfaces. It is the Contractor’s responsibility to remove all annual grasses and weeds from expansion joints and cracks of hard surfaces once they have been sprayed and are dead.
9.1.5.1 Tree collars, flowering beds, and any additional bed areas must be maintained in weed free condition through the use of herbicides and hand labor.
9.1.5.2. Where commercial herbicides may cause damage to sensitive plants (seasonal color, bulbs, ground covers, etc.), weeds must be pulled by hand to minimize plant loss or damage.
9.1.5.3. Weekly shearing of spent flower buds, "deadheading" of all necessary flowers in all flower beds and planters on ISVH-P grounds.
9.2. Monitoring Sprinkler Systems: Sprinkler systems for ISVH-P with natural vegetation must be monitored for the appropriate water application for the specific time of year. The Contractor must notify The Maintenance Supervisor or designee if sprinkler system needs adjusting (i.e. an increase in duration of water application) to maintain the health of the natural vegetation.
9.3. Insect and Disease Control: As insect and disease problems occur, apply appropriate chemicals to trees, deciduous trees and shrubs in leaf, and groundcovers/ perennials as directed, to control all forms of pests and diseases. All chemicals used for control purposes must be applied by, or applied under, the direct supervision of a Certified Pesticide Applicator.
9.3.1. All-natural vegetation (leaves, branches, grass clippings, trimmings, etc.) must be removed from the site, including, but not limited to sidewalks, parking areas, and any paved areas surrounding the locations.
9.3.2. All inorganic materials (plastic, glass, metal, paper, rocks, etc.) and any other miscellaneous debris must be removed from the site, including, but not limited to sidewalks, parking areas, and any paved areas surrounding the locations.
9.3.3. All materials, trash, and debris from the landscaping services from each site must be collected and discarded off-site at a proper solid waste/compost disposal facility meeting all applicable federal, state, and local requirements.
10. Contract Monitoring ISVH-P will commence formal assessment of the Contractor’s performance thirty (30) days after the effective date of the Contract. A designated representative of ISVH-P will assess the Contractor’s performance. The designated representative will conduct at random, a no notice visual spot check inspection during the month to assess performance of all or randomly selected services under this Contract. The Contractor will be given a copy of inspection reports as they are completed. If it is determined by the designated representative during the random visual inspection that the services were not completed or done incorrectly the Contractor will be required to re-accomplish the tasks at no additional cost to ISVH-P.
10.1 Financial Impact of non-compliance: The Contractors' failure to perform the required task may lead to increased work hazards and risk the safety of the Veterans in their Home and to the staff members who support them. The non-compliance will cost ISVH-P in staff, time, equipment, tools, materials and/or supplies to accomplish the services. The ISVH-P reserves the right to procure all services stated above in the event contractor fails to provide the services and Contractor agrees to reimburse the total costs ISVH- P incurs for all services procured.