Exhibit A - Landscaping and tree pruning work at CMR 2025 - 00001.pdf
PDF 2 MB Posted
- Solicitation number
- 19SN1025Q0030-00001
- Issued by
-
Department of State US Embassy Singapore
About this file
This document is a Statement of Work (SOW) for landscaping maintenance at the CMR Residence, Residence 8 Leedon Park, U.S. Embassy Singapore, dated April 10th, 2025. The SOW details comprehensive tree and landscape maintenance requirements, including pruning, trimming, crowning, and removal of dead or undesirable branches across multiple specific locations within the property. The scope of work involves detailed interventions for various tree types including standard trees, coconut trees, and bamboo clusters, with specific instructions for height reduction, branch removal, and maintaining clear boundaries near fences, walkways, and structures.
The contract requires the contractor to commence work within 60 calendar days of contract award and complete the project within 10 calendar days from the start date. Working hours are restricted to 0900-1700 Monday through Friday, excluding holidays. The contractor is responsible for providing all materials, equipment, and personnel, ensuring high-quality workmanship, obtaining necessary permits, complying with safety regulations, and protecting property during the work. Key responsibilities include professional execution of landscaping tasks, prompt reporting of incidents, and maintaining safety standards, with embassy staff reserving the right to stop work if unsafe practices are observed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit B - Landscaping and tree pruning work at DCR 2025 - 00001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
STATEMENT OF WORK
FOR
Landscaping maintenance at
CMR Residence.
Project:
Residence 8 Leedon Park
U.S. Embassy Singapore
April 10th, 2025
2 | P a g e
The U.S. Embassy intends to award a contract for various landscaping maintenance work at its property at 8 Leedon Park. The contractor is to supply all material, equipment, labor and tools to complete the following:-
Intend:-
The intend for pruning and trimming of the trees in the compound is to encourage trees to develop a strong structure and reduce the likelihood of damage during severe weather. Removing broken or damaged limbs encourage wound closure. Pruning for aesthetics, involves enhancing the natural form and character of trees or stimulating flower production. Also, to remove overgrown branches from crops such as trees, shrubs, and hedges. Extreme growth can prevent sunlight exposure to most parts of the tree hence inhibiting growth.
Scope of work:-
• Pruning/Trimming/Crowning
• Removal / Cutting of dead branches
• Removal of vines and plants on tree trunk
• Disposal and cleaning up of work area
Safety
NOTE : Contractors are responsible to barricade and take all necessary safety measures prior in conducting the work. They are to dispose at an appropriate/ designated site that are approved by local law. To clean affected area after work is done.
All safety procedures, certificate, work from height and safety plan are to be submitted to APOSHO prior to start of work.
3 | P a g e
FIG 1
• Pruning/Trimming/Crowning
• Remove dead / superfluous or undesirable branch.
FIG 2a
• Trim all leaves and branches that crosses over the fence.
• Remove all dead branches.
FIG 2b
• Height reduction 2m
• Crowning
• Remove dead / superfluous or undesirable branch.
PalanisamM Highlight
PalanisamM Highlight
PalanisamM Highlight
PalanisamM Highlight
4 | P a g e
FIG 3
• Height reduction 3m
• Crowning
FIG 4
• Pruning/Trimming/Crowning
5 | P a g e
FIG 5
• Trim all leaves and branches that crosses over the fence.
• From guard house to upslope of the driveway.
FIG 6
• Pruning/Trimming
• Trim all leaves and branches that crosses over the fence.
6 | P a g e
FIG 7
• Remove all dead leaves
• Trim all leaves and branches that crosses over the fence.
FIG 8
• Trim to push back to fences (OPTIONAL)
7 | P a g e
FIG 9
• Trim to push back to fences
FIG 10
• Total of 7 trees clustered
• Height reduction 3m
• Pruning/Trimming/Crowning
• Remove dead / superfluous or undesirable branch.
8 | P a g e
FIG 10a
• Remove dead / superfluous or undesirable branch.
• Trim all leaves and branches that crosses over the fence.
FIG 10b
• Remove dead / superfluous or undesirable branch.
• Trim all leaves and branches that crosses over the fence.
9 | P a g e
FIG 11
• Total of 6 coconut trees
• Remove all coconuts
• Remove all dead leaves
FIG 12
• Bamboo trees (2 cluster)
• Trim to push back 1m from walkway
• Remove dead bamboo trees
• Remove completely all slanting bamboo trees
10 | P a g e
FIG 13
• Bamboo trees (8 cluster)
• Height reduction 2m
• Remove dead bamboo trees
• Pruning/Trimming
• Remove completely all slanting bamboo trees
FIG 14
• Height reduction 3m
• Pruning/Trimming/Crowning
• Trim back 1m away from chiller enclosure
11 | P a g e
FIG 15
• Height reduction 3m
• Pruning/Trimming/Crowning
• Remove dead / superfluous or undesirable branch.
FIG 16
• Pruning/Trimming/Crowning
• Trim back from driveway 3-4 m
12 | P a g e
FIG 17
• Height reduction 3m
• Pruning/Trimming/Crowning
• Remove dead / superfluous or undesirable branch.
FIG 18
• Coconut trees
• Remove all coconuts
• Remove all dead leaves
13 | P a g e
FIG 19
• Bamboo tree
• Height reduction 2m
• Remove all dead branches
• Pruning/Trimming
• Remove completely all slanting bamboo trees
FIG 19a
• Remove dead / superfluous or undesirable branch.
• Clear all bushes on the ground
• Remove bamboo fish tail tree behind.
14 | P a g e
FIG 20
• Cluster of 4 trees
• Height reduction 3m
• Pruning/Trimming/Crowning
• Remove dead / superfluous or undesirable branch.
FIG 21a
• Height reduction 1m
• Pruning/Trimming
FIG 21b
• Remove tree branch completely
15 | P a g e
1. CONTRACT ADMINISTRATION
a. OBO does not make representations or warranties of whatsoever kind or nature, either expressed or implied, as to the quality, level of completion, accuracy, extent of compliance with the standards, codes and requirements described or referred to in this SOW, or the extent of coordination between or among the documents provided to the Contractor.
b. Neither the Embassy’s nor OBO’s review, approval, or acceptance of, nor payment for the services required under this contract, shall be considered to operate as a waiver of any rights under this contract or any cause of action against the Contractor arising out of the performance of this contract.
c. OBO has the right to inspect and test all services called for by the contract, to the extent practicable, at all times and places during the term of the contract. OBO may perform quality assurance inspections (QAI) to confirm the work is being performed according to the Statement of Work.
2. RESPONSIBILITY OF THE CONTRACTOR
a. The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all construction and other services furnished under this contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its construction and other services.
b. The Contractor is to provide floor and wall protection for all areas accessed during the work and will be responsible for the repair of damage to floors, walls, furnishings, or property caused by work performed under this contract, at no additional cost.
c. The Contractor is responsible for safety, obtaining any necessary licenses and permits and shall comply with all local labor laws, regulations, customs, and practices pertaining to labor, safety, and similar matters. Embassy staff reserve the right to stop work is unsafe practices are observed. Personal
Protection Equipment appropriate for the work being done is required for everyone on site.
d. The Contractor shall promptly report all incidents resulting in lost time, disabling, or fatal injuries to the Contracting Officer’s Representative (COR) to be identified during the site visit. The Contractor shall also be responsible for all damages to persons or property that occurs as a result of the
Contractor’s fault or negligence.
16 | P a g e
3. CONSTRUCTION REQUIREMENTS
a. The Contractor shall be responsible for all required materials (unless stated otherwise), equipment and personnel to manage, administer, and supervise this project. All workmanship shall be of good quality and performed in a skillful manner as determined of OBO.
b. The period of performance; work is to commence within 60 calendar days of contract award
(including all material ordering lead time) and will be finished within 10 calendar days from start.
Scheduled start date needs to be coordinated with the COR and end customer.
c. The Contractor shall have limited access to the remainder of the building outside the areas designated for the project, except with permission by the CO or COR.
d. Working hours will be from 0900 – 17:00 Monday – Friday, excluding local and U.S. holidays.
Weekend or afterhours work must be approved by the CO or COR and will not be justification for additional cost.
4. DELIVERABLE SCHEDULE
The Contractor shall commence work under this contract promptly, execute the work diligently, and achieve final completion and acceptance of the project, including final cleanup of the premises, within the contract period specified.
END OF STATEMENT OF WORK