This is a Contract Data Requirements List (CDRL) for HY-80 PLATE materials, containing 11 data items required under Contract Line Item Number 0002, Exhibit A. The contract requires vendor submission of detailed technical and certification documentation to Portsmouth Naval Shipyard for review and acceptance prior to each material shipment.
The required data items include: (A001) Inspection and Test Plan with inspection system procedures per DI-QCIC-81110; (A002) Certification data for special emphasis material covering chemical/mechanical properties per DI-MISC-81020; (A003) Special emphasis certificate of conformance per DI-MISC-80678; (A004) Ultrasonic (UT) test procedures approval prior to any testing, referencing T9074-BD-GIB-010/0300, T9074-AS-GIB-010/271, and ASTM-A435; (A005) NDT ultrasonic test certifications per DI-MISC-80678; (A006) First Article Testing certification per DI-MISC-80809 per T9074-BD-GIB-010/0300 Chapter B.4.3; (A007) Process Control Plan certification per T9074-BD-GIB-010/0300; (A008) Qualification Plan certification per DI-NDTI-80809; (A009) Chemical or spectrographic analysis certification per DI-MISC-80678; (A010) Tension test certification per T9074-BD-GIB-010/0300; and (A011) Impact test certification per T9074-BD-GIB-010/0300. All submissions require one final copy with distribution to the Purchasing Activity and must be submitted under separate shipment numbers. Payment and submission reference clauses 252.232-7006, 252.232-7003, or 52.232-36. The document was prepared by Jason Laflamme on 03/28/2026 and approved by Edward Walsh on 03/31/26.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 -TDP-LLDAX1041- VER 001.pdf | ||
| Solicitation - SPMYM326Q5054.pdf | ||
| Attachment 2 -TDP-LLDAX1039- VER 001.pdf | ||
| Attachment 3 -TDP-LLDAX1040- VER 001.pdf | ||
| Exhibit B.pdf | ||
| Exhibit C.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
TDP
D. SYSTEM/ITEM
HY-80 PLATE
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
INSPECTION AND TEST PLAN
3. SUBTITLE
INSPECTION SYSTEM PROCEDURES
4. AUTHORITY (Data Acqisition Document No.)
DI-QCIC-81110 (SE)
5. CONTRACT REFERENCE
TDP: PARA 3.11.3
6. REQUIRING OFFICE
PURCHASING ACTIVITY
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
B
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
N/A
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repro
16. REMARKS
Paragraph 10.4 of DI-QCIC-81110 does not apply.
Code 136.2 0 1 0
15. Total 0 1 0
G. PREPAREDBY
Jason Laflamme
H. DATE I. APPROVED BY J. DATE
Page 1 of 11 Page(s) SD Form 1423-1, JUN 90
S/N 0102-LF-010-5600
03/28/2026
For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36. Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material.
Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.
Edward Walsh 03/31/26
A0002
Form Approved OMB No. 0704-0188
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
TDP
D. SYSTEM/ITEM
HY-80 PLATE
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A002
2. TITLE OF DATA ITEM
CERT DATA FOR SPECIAL EMPHASIS MATL
3. SUBTITLE
CHEMICAL/ MECHANICAL
4. AUTHORITY (Data Acqisition Document No.)
DI-MISC-81020 (DD)
5. CONTRACT REFERENCE
TDP: PARA 3.18
6. REQUIRING OFFICE
PURCHASING ACTIVITY
7. DD 250 REQ
SD
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
N/A
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repro
16. REMARKS
For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36. Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material. Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.
CODE 133.2 0 1 0
15. Total 0 1 0
G. PREPAREDBY
Jason LaFlamme
H. DATE I. APPROVED BY J. DATE
DD Form 1423-1, JUN 90 Page 2 of 11 Page(s)
S/N 0102-LF-010-5600
03/28/2026 Edward Walsh 03/31/26
Form Approved OMB No. 0704-0188
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
TDP
D. SYSTEM/ITEM
HY-80 PLATE
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A003
2. TITLE OF DATA ITEM
CERTIFICATION/DATA REPORT
3. SUBTITLE
SPECIAL EMPHASIS C OF C
4. AUTHORITY (Data Acqisition Document No.)
DI-MISC-80678 (CCDD)
5. CONTRACT REFERENCE
TDP: PARA 3.23
6. REQUIRING OFFICE
PURCHASING ACTIVITY
7. DD 250 REQ
SD
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
N/A
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repro
16. REMARKS
Block 4 - Paragraphs 10.2.1, 10.2.2, 10.2.3, 10.3, and 10.4 of DI-MISC-80678 do not apply.
For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36. Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material.
Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.
CODE 133.2 0 1 0
15. Total 0 1 0
G. PREPARED BY
Jason Laflamme
H. DATE
03/28/2026
I. APPROVED BY J. DATE
DD Form 1423-1, JUN 90 Page 3 of 11 Page(s)
S/N 0102-LF-010-5600
Form Approved OMB No. 0704-0188
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
TDP
D. SYSTEM/ITEM
HY-80 PLATE
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A004
2. TITLE OF DATA ITEM
PROCEDURES, TEST
3. SUBTITLE
TEST PROCEDURES (UT) APPROVAL
4. AUTHORITY (Data Acqisition Document No.)
UDI-T-23732B
5. CONTRACT REFERENCE
TDP: PARA 3.9
6. REQUIRING OFFICE
PURCHASING ACTIVITY
7. DD 250 REQ
SD
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
PRIOR TO ANY UT
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
ASREQ
Draft Final
Reg Repro
CODE 135T 0 1 0
15. Total 0 1 0
G. PREPARED BY
Jason Laflamme
H. DATE I. APPROVED BY J. DATE
DD Form 1423-1, JUN 90 Page 4 of 11 Page(s)
S/N 0102-LF-010-5600
16. REMARKS
Block 4 - Paragraph 10.1 of UDI-T-23732B does not apply.
Non-Destructive Test Inspection Procedure:
ULTRASONIC (UT):
Performance: T9074-BD-GIB-010/0300, T9074-AS-GIB-010/271 & ASTM-A435 Acceptance: T9074-BD-GIB-010/0300 & ASTM-A435
For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36. Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material.
Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.
03/28/2026 Edward Walsh 03/31/26
Form Approved OMB No. 0704-0188
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
TDP
D. SYSTEM/ITEM
HY-80 PLATE
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A005
2. TITLE OF DATA ITEM
CERTIFICATION/DATA REPORT
3. SUBTITLE
TEST CERTIFICATIONS
4. AUTHORITY (Data Acqisition Document No.)
DI-MISC-80678 (DD)
5. CONTRACT REFERENCE
TDP: PARA 3.10
6. REQUIRING OFFICE
PURCHASING ACTIVITY
7. DD 250 REQ
SD
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
N/A
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repro
16. REMARKS
Block 4 - Paragraphs 10.2.2, 10.2.3, 10.2.4, and 10.3 of DI-MISC-80678 do not apply.
For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36. Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material.
Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.
CODE 133.2 0 1 0
15. Total 0 1 0
G. PREPARED BY
Jason Laflamme
H. DATE J. DATE
DD Form 1423-1, JUN 90 Page 5 of 11 Page(s)
S/N 0102-LF-010-5600
All Test Certifications of NDT Procedures:
ULTRASONIC (UT) with acceptance.
03/28/2026
I. APPROVED BY
Edward Walsh 03/31/26
A
Form Approved OMB No. 0704-0188
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
TDP
D. SYSTEM/ITEM
HY-80 PLATE
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A006
2. TITLE OF DATA ITEM
CERTIFICATION/DATA REPORT
3. SUBTITLE
TEST CERTIFICATIONS-(FAT)
4. AUTHORITY (Data Acqisition Document No.)
DI-MISC-80809
5. CONTRACT REFERENCE
TDP: PARA 3.3.1
6. REQUIRING OFFICE
PURCHASING ACTIVITY
7. DD 250 REQ
SD
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
N/A
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repro
16. REMARKS
Block 4 - Paragraphs 10.2.2, 10.2.3, 10.2.4, and 10.3 of DI-MISC-80678 do not apply.
For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36. Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material. Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.
CODE 133.2 0 1 0
15. Total 0 1 0
G. PREPARED BY
Jason Laflamme
H. DATE J. DATE
DD Form 1423-1, JUN 90 Page 6 of 11 Page(s)
S/N 0102-LF-010-5600
First Article Testing required IAW T9074-BD-GIB-010/0300, Chapter B.4.3. (FAT)
03/28/2026
I. APPROVED BY
Form Approved OMB No. 0704-0188
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
TDP
D. SYSTEM/ITEM
HY-80 PLATE
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A007
2. TITLE OF DATA ITEM
CERTIFICATION/DATA REPORT
3. SUBTITLE
TEST CERTIFICATIONS
4. AUTHORITY (Data Acqisition Document No.)
DI-MISC-80809
5. CONTRACT REFERENCE
TDP: PARA 3.3.2
6. REQUIRING OFFICE
CODE 245
7. DD 250 REQ
SD
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
N/A
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repro
16. REMARKS
Block 12 - See Clause 52.209-3 for submittal timeframes.
Test Certification of the Process Control Plan IAW T9074-BD-GIB-010/0300
For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36.
Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material. Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.
133.2 0 1 0
15. Total 0 1 0
G. PREPARED BY
Jason Laflamme
H. DATE
03/28/2026
I. APPROVED BY J. DATE
DD Form 1423-1, JUN 90 Page 7 of 11 Page(s)
S/N 0102-LF-010-5600
(Process Control Plan)
Form Approved OMB No. 0704-0188
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
TDP
D. SYSTEM/ITEM
HY-80 PLATE
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A008
2. TITLE OF DATA ITEM
CERTIFICATION/DATA REPORT
3. SUBTITLE
TEST CERTIFICATIONS
4. AUTHORITY (Data Acqisition Document No.)
DI-NDTI-80809
5. CONTRACT REFERENCE
TDP: PARA 3.3.3
6. REQUIRING OFFICE
CODE 245
7. DD 250 REQ
SD
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
N/A
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repro
16. REMARKS
Block 4 - Paragraphs 10.2.2, 10.2.3, 10.2.4, and 10.3 of DI-MISC-80678 do not apply.
Test Certification of Qualification Plan IAW T9074-BD-GIB-010/0300
For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36.
Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material. Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.
133.2 0 1 0
15. Total 0 1 0
G. PREPARED BY
Jason Laflamme
H. DATE
03/28/2026
I. APPROVED BY J. DATE
DD Form 1423-1, JUN 90 Page 8 of 11 Page(s)
S/N 0102-LF-010-5600
(Qualification Plan)
Form Approved OMB No. 0704-0188
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
TDP
D. SYSTEM/ITEM
HY-80 PLATE
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A009
2. TITLE OF DATA ITEM
CERTIFICATION/DATA REPORT
3. SUBTITLE
TEST CERTIFICATIONS
4. AUTHORITY (Data Acqisition Document No.)
DI-MISC-80678 (DD)
5. CONTRACT REFERENCE
TDP: PARA 3.10
6. REQUIRING OFFICE
CODE 245
7. DD 250 REQ
SD
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
N/A
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repro
16. REMARKS
Block 4 - Paragraphs 10.2.2, 10.2.3, 10.2.4, and 10.3 of DI-MISC-80678 do not apply.
-Test Certification of Chemical or Spectrographic Analysis IAW T9074-BD-GIB-010/0300
For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36.
Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material. Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.
133.2 0 1 0
15. Total 0 1 0
G. PREPARED BY
Jason Laflamme
H. DATE
03/28/2026
I. APPROVED BY J. DATE
DD Form 1423-1, JUN 90 Page 9 of 11 Page(s)
S/N 0102-LF-010-5600
(Chemical or Spectrographic Analysis)
Form Approved OMB No. 0704-0188
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
TDP
D. SYSTEM/ITEM
HY-80 PLATE
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM
CERTIFICATION/DATA REPORT
3. SUBTITLE
TEST CERTIFICATIONS
4. AUTHORITY (Data Acqisition Document No.)
DI-MISC-80678 (DD)
5. CONTRACT REFERENCE
TDP: PARA 3.10
6. REQUIRING OFFICE
CODE 245
7. DD 250 REQ
SD
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
N/A
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repro
16. REMARKS
Block 4 - Paragraphs 10.2.2, 10.2.3, 10.2.4, and 10.3 of DI-MISC-80678 do not apply.
Test Certification of Tension Test IAW T9074-BD-GIB-010/0300.
For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36.
Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material. Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.
133.2 0 1 0
15. Total 0 1 0
G. PREPARED BY
Jason Laflamme
H. DATE
03/28/2026
I. APPROVED BY J. DATE
DD Form 1423-1, JUN 90 Page 10 of 11 Page(s)
S/N 0102-LF-010-5600
(Tension Test)A010
Form Approved OMB No. 0704-0188
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
TDP
D. SYSTEM/ITEM
HY-80 PLATE
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A011
2. TITLE OF DATA ITEM
CERTIFICATION/DATA REPORT
3. SUBTITLE
TEST CERTIFICATIONS
4. AUTHORITY (Data Acqisition Document No.)
DI-MISC-80678 (DD)
5. CONTRACT REFERENCE
TDP: PARA 3.10
6. REQUIRING OFFICE
CODE 245
7. DD 250 REQ
SD
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
N/A
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repro
16. REMARKS
Block 4 - Paragraphs 10.2.2, 10.2.3, 10.2.4, and 10.3 of DI-MISC-80678 do not apply.
Test Certification of Impact Test IAW T9074-BD-GIB-010/0300
For payment & submission of data refer to clauses 252.232-7006 and 252.232-7003 or 52.232-36.
Certification data shall be submitted to Portsmouth Naval Shipyard for review and acceptance prior to each shipment of material. Each data item submitted by vendor must be submitted under separate shipment number. No material is to be shipped prior to the receipt of Acceptance.
133.2 0 1 0
15. Total 0 1 0
G. PREPARED BY
Jason Laflamme
H. DATE
03/28/2026
I. APPROVED BY J. DATE
DD Form 1423-1, JUN 90 Page 11 of 11 Page(s)
S/N 0102-LF-010-5600
(Impact Test)
File details come from the government source that posted it. Updated .