Exhibit A - Chancellor HS & MS Combined Specifications.pdf.pdf

PDF 7 MB Posted

Attached to
Chancellor HS & MS HVAC Replacement & Mechanical Upgrades
Solicitation number
IFB-131873
Issued by
Stafford County, Virginia

About this file

This is a Project Manual and technical specifications document for Chancellor High School & Middle School HVAC Replacement & Mechanical Upgrades, a construction project in Fredericksburg, Virginia, managed by Spotsylvania County Public Schools with Moseley Inc. of Richmond, Virginia serving as the architect. The project is structured as a single prime contract based on a stipulated fixed-sum price. The work encompasses comprehensive HVAC system replacement and mechanical upgrades including hydronic piping replacement, valve additions/replacements, and related mechanical systems work. A lump-sum allowance of $200,000 is designated for chilled and heating hot water piping replacement and valve additions/replacements. The project includes ten unit prices for replacement costs of existing hydronic hot water and chilled water piping ranging from 3/4 inch to 8 inch diameter pipe, and nine unit prices for replacement or addition costs of existing hydronic hot water and chilled water valves from 3/4 inch to 6 inch diameter. The contract requires phased construction to accommodate ongoing owner occupancy, with work limited to designated areas. Within 15 days of contract award, the contractor must provide summaries of on-site personnel, all subcontractors and their contact information, and coordination drawings. Background checks performed by Virginia State Police are mandatory for all site personnel, and identification badges with photographs are required. The project manual establishes comprehensive administrative requirements including preconstruction meetings, construction waste management conferences, and indoor air quality management planning sessions.

Pricing is structured as a stipulated fixed-sum contract with applications for progress payments submitted at intervals using AIA Forms G702 and G703, with retainage applied as specified in the agreement. The contractor is responsible for all costs including labor, materials, overhead, and profit unless otherwise specified under allowances or unit prices. For change orders, the architect issues Construction Change Directives on AIA Document G714, and the contractor must provide detailed cost substantiation including quantities, labor hours, wage rates, material invoices, and justification for any time extensions. The document specifies that contractor-proposed changes will be evaluated based on the contractor's fixed-price quotation, while architect-requested changes fall under fixed-price contract evaluation. All major subcontractors must review and accept the proposed construction schedule, and any recovery schedule necessitated by delays of 14 or more days must receive owner approval before proceeding. The contractor is required to maintain a comprehensive quality control plan addressing management structure, inspection and testing procedures, and defect tracking, with the owner retaining the right to mandate personnel changes or operational modifications to ensure specified work quality.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

CHANCELLOR HS & MS HVAC

REPLACEMENT & MECHANICAL

UPGRADES

ARCHITECT’S PROJECT NO.: 650043

ARCHITECT/ENGINEER RICHMOND, VIRGINIA

BID

VOLUME 1 OF 1

NOVEMBER 10, 2026

CHANCELLOR H.S. & M.S. HVAC REPLACEMENT & MECHANICAL UPGRADES

FREDERICKSBURG, VA

Architect’s Project No: 650043

TABLE OF CONTENTS TOC - 1

TABLE OF CONTENTS

TECHNICAL SPECIFICATIONS

DIVISION 1 – GENERAL REQUIREMENTS

011000 Summary

012000 Price and Payment Procedures

012100 Allowances

012200 Unit Prices

125000 Substitution Procedures

012501 Substitution Request Form (After Receipt of Bids)

013000 Administrative Requirements

013216 Construction Progress Schedule

014000 Quality Requirements

014200 Definitions and Reference Standards

015000 Temporary Facilities and Controls

016000 Product Requirements

017000 Execution and Closeout Requirements

017419 Construction Waste Management and Disposal

017800 Closeout Submittals

017900 Demonstration and Training

018119 Indoor Air Quality Requirements

019100 General Commissioning Requirements

019110 Functional Performance Testing Procedures

DIVISION 2 – EXISTING CONDITIONS

024100 Demolition

DIVISION 3 – CONCRETE

033000 Cast-in-Place Concrete

DIVISION 4 – MASONRY

DIVISION 5 – METALS

DIVISION 6 – WOOD PLASTICS AND COMPOSITES

DIVISION 7 – THERMAL AND MOISTURE PROTECTION

075301 EPDM – Minor Alterations

DIVISION 8 – OPENINGS

DIVISION 9 – FINISHES

095100 Acoustical Ceilings

099100 Painting

TABLE OF CONTENTS TOC - 2

DIVISION 10 – SPECIALTIES

DIVISION 11 – EQUIPMENT

DIVISION 12 – FURNISHINGS

DIVISION 13 – SPECIAL CONSTRUCTION

DIVISION 14 – CONVEYING SYSTEMS

DIVISION 21 – FIRE SUPPRESSION

DIVISION 22 – PLUMBING

220500 Common Work Results for Plumbing

220513 Motors for Plumbing Equipment

220517 Sleeves and Sleeve Seals for Plumbing Piping

220519 Meters and Gages for Plumbing Piping

220523 General-Duty Valves for Plumbing Piping

220529 Hangers and Supports for Plumbing Piping and Equipment

220553 Identification for Plumbing Piping and Equipment

220700 Plumbing Insulation

221113 Facility Natural Gas Piping

221116 Domestic Water Piping

221119 Domestic Water Piping Specialties

221125 Circulating Pumps

221316 Sanitary Waste and Vent Piping

221319 Sanitary Waste Piping Specialties

223400 Fuel-Fired, Domestic-Water Heaters

DIVISION 23 – MECHANICAL

230130.52 Existing HVAC Air Distribution System Cleaning

230500 Common Work Results for HVAC

230513 Motors for HVAC Equipment

230514 Variable Speed Drives

230517 Sleeves and Sleeve Seals for HVAC Piping

230519 Meters and Gages for HVAC Piping

230523 General Duty Valves for HVAC Piping

230529 Hangers and Supports for HVAC Piping and Equipment

230533 Heat Tracing for HVAC Piping

230548 Vibration Control for HVAC

230553 Identification for HVAC Piping and Equipment

230593 Testing, Adjusting, and Balancing for HVAC

230700 HVAC Insulation

230800 Mechanical Systems Commissioning

230900 Building Automation System

230993 Sequence of Operations for HVAC Controls

230998 Commissioning for HVAC Controls

232113 Hydronic Piping

232123 Hydronic Pumps

232350 Refrigerant Detection and Alarm

TABLE OF CONTENTS TOC - 3

232500 HVAC Water Treatment

232533 Cooling Tower Filtration System

233113 Metal Ducts

233300 Air Duct Accessories

233423 HVAC Power Ventilators

233600 Air Terminal Units

233713 Diffusers, Registers, and Grilles

233723 HVAC Gravity Ventilators

234100 Particulate Air Filtration

235216 Condensing Boilers

235700 Heat Exchangers for HVAC

236416 Centrifugal Water Chillers

236500 Cooling Towers

237313 Modular Indoor Air Handling Units

237314 Existing Air Handling Units Replacement Components

237433 Indirect-Fired Heating and Ventilating Units

238126 Split-System Air Conditioners

238216 Hydronic Air Coils

238219 Fan Coil Units

238239 Electric and Gas Unit Heaters

238240 Cabinet Unit Heaters

DIVISION 26 – ELECTRICAL

260519 Low-Voltage Electrical Power Conductors and Cables

260526 Grounding and Bonding for Electrical Systems

260529 Hangers and Supports for Electrical Systems

260533 Raceways and Boxes for Electrical Systems

260544 Sleeves and Sleeve Seals for Electrical Raceways and Cabling

260553 Identification for Electrical Systems

262413 Switchboards

262416 Panelboards

262813 Fuses

262816 Enclosed Switches and Circuit Breakers

265119 LED Interior Lighting

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

280500 Common Work Results for Electronic Safety and Security

280513 Conductors and Cables for Safety and Security

283111 Digital, Addressable Fire Alarm System

TABLE OF CONTENTS TOC - 4

DIVISION 31 – EARTHWORK

DIVISION 32 – EXTERIOR IMPROVEMENTS

DIVISION 33 – UTILITIES

DIVISION 34 – TRANSPORTATION

END OF TECHNICAL SPECIFICATIONS

END OF TABLE OF CONTENTS

Summary 011000 - 1

SECTION 011000

SUMMARY

PART 1 GENERAL

1.01 PROJECT

A. Project Name: Chancellor HS & MS HVAC Replacement & Mechanical Upgrades.

B. Owner's Name: Spotsylvania County Public Schools.

C. Architect's Name: Moseley Inc. of Richmond, VA.

1.02 CONTRACT DESCRIPTION

A. Contract Type: A single prime contract based on a Stipulated Price (Fixed Sum) as described in the Bidding and Contractual Requirements (Division 00) included in this Project Manual.

1.03 PROFESSIONAL SEALS

A. Use of Professional Seals on Bidding, Procurement, and Contract Documents: For the purposes of this paragraph, the term “Regulant” refers to the individual who signs and seals parts of the Contract Documents (e.g. the Drawings and Specifications). Certain information has been excerpted verbatim from a source or sources (e.g., UL assemblies, SMACNA details, applicable state/jurisdiction building code) which was considered or used by Regulant in preparing parts of the Contract Documents, as follows:

1. The excerpted information was neither prepared under the direct control nor personal supervision nor created by the Regulant, as it was prepared by the source and owner of the excerpted information.

2. For purposes of bidding, procuring, and performance of the Work, and in any event of conflicts or ambiguities between the excerpted information in the Contract Documents and the requirements of applicable codes and standards, provide the better quality or greater quantity of Work which, at a minimum, complies with the requirements of the applicable codes and standards.

3. Advise Architect immediately upon becoming aware of requirements of the Work which are not consistent with the requirements of the excerpted information.

4. Attribution is acknowledged for information obtained and included herein verbatim from other source or sources.

5. Regulant has taken into consideration and used certain excerpted information from other sources which are applicable to the Contract Documents, and the Regulant indicates by its seal that it is assuming responsibility for its services in use and application of the excerpted information to the requirements of Work, but not for the excerpted information itself which was prepared by others. Regulant does not indicate by its seal that it is responsible for use or application of other information in such source or sources which was not included herein.

1.04 OWNER OCCUPANCY

A. Owner intends to occupy the Project upon Substantial Completion.

B. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.

C. Schedule the Work to accommodate Owner occupancy.

1. Maintain routes of egress and life safety systems for Owner and occupants at all times.

1.05 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: Limited to areas noted on Drawings.

Summary 011000 - 2

1. Locate and conduct construction activities in ways that will limit disturbance to site.

B. Provide access to and from site as required by law and by Owner:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

C. Existing building spaces may not be used for storage.

D. Existing building shall be maintained weathertight. Do not modify elements of the existing building except as indicated on the Construction Documents. Repair damage to the existing building due to construction activity.

E. Time Restrictions:

1. Comply with local regulations for hours of work, noise ordinances, and similar requirements.

F. Utility Outages and Shutdown:

1. Limit disruption of utility services to hours the building is unoccupied.

2. Do not disrupt or shut down life safety systems, including but not limited to fire sprinklers and fire alarm system, without 7 days notice to Owner and authorities having jurisdiction.

3. Prevent accidental disruption of utility services to other facilities.

G. Controlled Substances: The use of alcohol and drugs is not permitted on the Project site.

Provide a designated outdoor smoking area for construction personnel that is at least 30 feet away from the building.

1.06 PHASED WORK

A. Construct Work in phases as indicated on Drawings.

B. Coordinate construction schedule and operations with Owner and Architect.

1.07 SPECIFICATION SECTIONS APPLICABLE TO ALL WORK

A. The provisions of the Owner/Contractor agreement, General Conditions of the Contract, Supplementary Conditions (if any), and all Division 01 sections shall apply to all sections of the Project Manual.

1.08 SECURITY PROVISIONS

A. Background Check: The Owner requires that a background check be performed on all personnel working on the site. Comply with Owner's requirements for screening service to be used. Maintain a list of all accredited persons, submit a copy to Owner on request.

B. Identification Badges: Provide identification badges to each person authorized to enter premises. Badge shall include personal photograph, name, employer, expiration date, and an assigned number. Have personnel return badges to Contractor after completion of their portion of the Work.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF SECTION 011000

Price and Payment Procedures 012000 - 1

SECTION 012000

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.01 SCHEDULE OF VALUES

A. Use Schedule of Values Form: AIA G703, unless otherwise agreed to by Owner in writing.

B. Forms filled out by hand will not be accepted.

C. Format: Utilize the Table of Contents of this Project Manual. Identify each line item with number and title of the specification section. Identify site mobilization.

D. Include in each line item, the amount of Allowances specified in this section. For Quantity Allowances, identify quantities taken from Contract Documents multiplied by the unit cost to achieve the total for the item.

E. Include separately from each line item, a direct proportional amount of Contractor's overhead and profit.

F. Revise schedule to list approved Change Orders, with each Application For Payment.

1. When a Change Order includes multiple PCOs, break down the total Change Order to include each PCO as an individual line item.

1.02 APPLICATIONS FOR PROGRESS PAYMENTS

A. Payment Period: Submit at intervals stipulated in the Agreement.

B. Use Form AIA G702 and Form AIA G703.

C. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to Architect for approval.

D. Forms filled out by hand will not be accepted.

E. For each item, provide a column for listing each of the following:

1. Item Number.

2. Description of work.

3. Scheduled Values.

4. Previous Applications.

5. Work in Place and Stored Materials under this Application.

6. Authorized Change Orders.

7. Total Completed and Stored to Date of Application.

8. Balance to Finish.

9. Retainage.

F. Execute certification by signature of authorized officer.

G. Use data from approved Schedule of Values. Provide dollar value in each column for each line item for portion of work performed and for stored products.

H. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of work.

1. When a Change Order includes multiple PCOs, break down the total Change Order to include each PCO as an individual line item.

I. Submit one electronic and three hard-copies of each Application for Payment.

J. Include the following with the application:

Price and Payment Procedures 012000 - 2

1. Transmittal letter as specified for submittals in Section 013000.

2. Construction progress schedule, revised and current as specified in Section 013000.

3. Partial release of liens from major subcontractors and vendors.

4. Affidavits attesting to off-site stored products.

1.03 MODIFICATION PROCEDURES

A. For minor changes not involving an adjustment to the Contract Sum or Contract Time, Architect will issue instructions directly to Contractor on AIA Document G710 "Architect's Supplemental Instructions."

B. For changes for which advance pricing is desired, Architect will issue a document that includes a detailed description of a proposed change with supplementary or revised drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required and the period of time during which the requested price will be considered valid. Contractor shall prepare and submit a fixed price quotation within 14 days, unless otherwise indicated in Proposal Request.

C. Contractor may propose a change by submitting a request for change to Architect, describing the proposed change and its full effect on the work, with a statement describing the reason for the change, and the effect on the Contract Sum and Contract Time with full documentation.

D. For other required changes, Architect will issue a Construction Change Directive, on AIA Document G714, signed by Owner instructing Contractor to proceed with the change, for subsequent inclusion in a Change Order.

1. The document will describe the required changes and will designate method of determining any change in Contract Sum or Contract Time.

2. Promptly execute the change.

E. Computation of Change in Contract Amount: As specified in the Agreement and Conditions of the Contract.

1. For change requested by Architect for work falling under a fixed price contract, the amount will be based on Contractor's price quotation.

2. For change requested by Contractor, the amount will be based on the Contractor's request for a Change Order as approved by Architect.

3. For pre-determined unit prices and quantities, the amount will based on the fixed unit prices.

F. Substantiation of Costs: Provide full information required for evaluation.

1. Provide the following data:

a. Quantities of products, labor, and equipment.

b. Taxes, insurance, and bonds.

c. Overhead and profit.

d. Justification for any change in Contract Time.

e. Credit for deletions from Contract, similarly documented.

2. Support each claim for additional costs with additional information:

a. Origin and date of claim.

b. Dates and times work was performed, and by whom.

c. Time records and wage rates paid.

d. Invoices and receipts for products, equipment, and subcontracts, similarly documented.

G. Execution of Change Orders: Architect will issue Change Orders on AIA Document G701 for signatures of parties as provided in the Conditions of the Contract.

Price and Payment Procedures 012000 - 3

H. After execution of Change Order, promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Sum.

I. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust times for other items of work affected by the change, and resubmit.

1.04 APPLICATION FOR FINAL PAYMENT

A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Sum, previous payments, and sum remaining due.

B. Application for Final Payment will not be considered until the following have been accomplished:

1. All closeout procedures specified in Section 017000.

C. Provide evidence and supporting data for the following, as attachments to the Application for Final Payment:

1. AIA G706, "Contractor's Affidavit of Payment of Debts and Claims."

2. AIA G706A, "Contractor's Affidavit of Release of Liens."

3. AIA G707, "Consent of Surety to Final Payment."

4. Copy of Certificate of Occupancy.

5. Settlement of all debts and claims, including liquidated damages, taxes, and fees.

6. Utility meter readings, fuel levels, and similar measurements, as of the date of turn over to the Owner.

7. Certificates for insured products, and certificate of insurance for completed operations.

PART 2 PRODUCTS - NOT USED

END OF SECTION 012000

Allowances 012100 - 1

SECTION 012100

ALLOWANCES

PART 1 GENERAL

1.01 SUBMITTALS

A. Allowance Proposal: Submit initial proposal for purchase of products and materials, on Change Order form.

B. Supporting Documentation:

1. Products and Material: Provide invoices and other documents as required, for products and materials indicating quantities, prices, taxes, delivery fees, and other costs.

2. Labor and Installation: Provide time sheets and other documents as required, indicating all on-site Subcontractor costs, including hours worked, quantity or amount of product/material installed, hourly wages, and Subcontractor overhead and profit.

1.02 LUMP-SUM AND QUANTITY ALLOWANCES

A. Costs Included in Lump-Sum and Quantity Allowances: All General Contractor's costs: General coordination, GC's overhead and profit. All Subcontractor's costs: Cost of products and materials, taxes, freight, delivery, receiving and handling, labor and installation, Subcontractor overhead and profit.

B. Contractor Responsibilities:

1. Assist Architect in selection of products.

2. Obtain proposals from suppliers and installers and offer recommendations.

3. On notification of which products have been selected, execute purchase agreement with designated supplier and installer.

4. Arrange for and process shop drawings, product data, and samples. Arrange for delivery.

C. Contractor shall return unused products and materials that were purchased under allowance to the manufacturer or supplier, and provide credit to the Owner.

D. At closeout of contract, differences in costs for each allowance will be adjusted by Change Order to increase the contract sum or to provide a credit to the Owner, as applicable.

1.03 LUMP SUM ALLOWANCE SCHEDULE

A. Lump Sum Allowance No. 1: Include the stipulated sum of $200,000 for chilled and heating hot water piping replacement and valve addition / replacement.

PART 2 PRODUCTS - NOT USED

END OF SECTION 012100

Unit Prices 012200 - 1

SECTION 012200

UNIT PRICES

PART 1 GENERAL

1.01 COSTS INCLUDED

A. Unit Prices included on the Bid Form shall include full compensation for all required labor, products, tools, equipment, plant, transportation, services and incidentals; erection, application or installation of an item of the Work; overhead and profit.

1.02 MEASUREMENT OF QUANTITIES

A. Measurement methods delineated on the Drawings or in the individual specification sections complement the criteria of this section. In the event of conflict, the requirements of the Drawings or individual specification section govern.

B. Take all measurements and compute quantities. Measurements and quantities will be verified via mutual agreement, and by personnel authorized by Owner, if required.

C. Assist by providing necessary equipment, workers, and survey personnel as required.

D. Perform surveys required to determine quantities, including control surveys to establish measurement reference lines. Notify Architect prior to starting work.

E. Contractor's Engineer Responsibilities: Sign surveyor's field notes or keep duplicate field notes; calculate and certify quantities for payment purposes.

1.03 PAYMENT

A. Payment for Work governed by unit prices will be made on the basis of the actual measurements and quantities of Work that is incorporated in or made necessary by the Work and accepted by the Architect, multiplied by the unit price.

B. Payment will not be made for any of the following:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products not completely unloaded from the transporting vehicle.

4. Products placed beyond the lines and levels of the required Work.

5. Products remaining on hand after completion of the Work.

6. Loading, hauling, and disposing of rejected Products.

1.04 SCHEDULE OF UNIT PRICES

A. Unit Price 1: Replacement cost per linear foot of existing hydronic hot water and chilled water piping: 3/4" pipe.

B. Unit Price 2: Replacement cost per linear foot of existing hydronic hot water and chilled water piping: 1" pipe.

C. Unit Price 3: Replacement cost per linear foot of existing hydronic hot water and chilled water piping: 1 1/4" pipe.

D. Unit Price 4: Replacement cost per linear foot of existing hydronic hot water and chilled water piping: 1 1/2" pipe.

E. Unit Price 5: Replacement cost per linear foot of existing hydronic hot water and chilled water piping: 2" pipe.

F. Unit Price 6: Replacement cost per linear foot of existing hydronic hot water and chilled water piping: 3" pipe.

Unit Prices 012200 - 2

G. Unit Price 7: Replacement cost per linear foot of existing hydronic hot water and chilled water piping: 4" pipe.

H. Unit Price 8: Replacement cost per linear foot of existing hydronic hot water and chilled water piping: 5" pipe.

I. Unit Price 9: Replacement cost per linear foot of existing hydronic hot water and chilled water piping: 6" pipe.

J. Unit Price 10: Replacement cost per linear foot of existing hydronic hot water and chilled water piping: 8" pipe.

K. Unit Price 11: Replacement or addition cost per valve of existing hydronic hot water and chilled water valves: 3/4" valve.

L. Unit Price 12: Replacement or addition cost per valve of existing hydronic hot water and chilled water valves: 1" valve.

M. Unit Price 13: Replacement or addition cost per valve of existing hydronic hot water and chilled water valves: 1 1/4" valve.

N. Unit Price 14: Replacement or addition cost per valve of existing hydronic hot water and chilled water valves: 1 1/2" valve.

O. Unit Price 15: Replacement or addition cost per valve of existing hydronic hot water and chilled water valves: 2" valve.

P. Unit Price 16: Replacement or addition cost per valve of existing hydronic hot water and chilled water valves: 3" valve.

Q. Unit Price 17: Replacement or addition cost per valve of existing hydronic hot water and chilled water valves: 4" valve.

R. Unit Price 18: Replacement or addition cost per valve of existing hydronic hot water and chilled water valves: 5" valve.

S. Unit Price 19: Replacement or addition cost per valve of existing hydronic hot water and chilled water valves: 6" valve.

PART 2 PRODUCTS - NOT USED

END OF SECTION 012200

Substitution Procedures 012500 - 1

SECTION 012500

SUBSTITUTION PROCEDURES

PART 1 GENERAL

1.01 DEFINITIONS

A. Substitutions: Changes from Contract Documents requirements proposed by Contractor to materials, products, assemblies, and equipment.

1. Substitutions for Cause: Proposed due to changed Project circumstances beyond Contractor's control, such as unavailability, regulatory changes, or unobtainable warranty terms.

2. Substitutions for Convenience: Proposed due to possibility of offering substantial advantage to the Project.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 GENERAL REQUIREMENTS

A. A Substitution Request for products, assemblies, materials, and equipment constitutes a representation that the submitter:

1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product, equipment, assembly, or system.

2. Agrees to provide the same warranty for the substitution as for the specified product.

3. Agrees to provide same or equivalent maintenance service and source of replacement parts, as applicable.

4. Agrees to coordinate installation and make changes to other work that may be required for the work to be complete, with no additional cost to Owner.

5. Waives claims for additional costs or time extension that may subsequently become apparent.

6. Agrees to reimburse Owner and Architect for review or redesign services associated with re-approval by authorities.

B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents. Burden of proof is on proposer.

1. Note explicitly any non-compliant characteristics.

C. Substitutions shall be submitted directly by a General Contractor/prime bidder. Substitutions submitted by a subcontractor, manufacturer, supplier or other entity other than General Contractor are not acceptable and shall be rejected.

D. Content: Include information necessary for tracking the status of each Substitution Request, and information necessary to provide an actionable response.

1. A copy of the Substitution Request Form that shall be used is included at the end of this Section for informational purposes. Request a Word or editable PDF version of the form from the Architect and complete the form digitally; do not complete the form by hand.

2. Contractor's Substitution Request documentation must include the following:

a. Substitution Request Information:

1) Indication of whether the substitution is for cause or convenience.

2) Issue date.

Substitution Procedures 012500 - 2

3) Reference to particular Contract Document(s) specification section number, title, and article/paragraph(s).

4) Description of Substitution.

5) Reason why the specified item cannot be provided.

6) Description of how proposed substitution affects other parts of work.

b. Attached Comparative Data: Provide point-by-point, side-by-side comparison addressing essential attributes specified, as appropriate and relevant for the item:

1) Physical characteristics.

2) In-service performance.

3) Expected durability.

4) Visual effect.

5) Sustainable design features.

6) Warranties.

7) Other salient features and requirements.

8) Include, as appropriate or requested, the following types of documentation:

(a) Product Data:

(b) Samples.

(c) Certificates, test, reports or similar qualification data.

(d) Drawings, when required to show impact on adjacent construction elements.

c. Impact of Substitution: Provide data indicating cost savings to Owner and change in Contract Time due to accepting substitution.

E. Limit each request to a single proposed substitution item.

1. Submit an electronic document, combining the request form with supporting data into single document.

3.02 SUBSTITUTION PROCEDURES DURING CONSTRUCTION

A. Architect will consider requests for substitutions for convenience only within 30 days after date of Agreement.

1. Substitutions for convenience submitted after this time period may or may not be considered, at the Architect's discretion.

B. Submit request for Substitution for Cause immediately upon discovery of need for substitution, but not later than 14 days prior to time required for review and approval by Architect, in order to stay on approved project schedule.

C. Submit request for Substitution for Convenience immediately upon discovery of its potential advantage to the project, but not later than 14 days prior to time required for review and approval by Architect, in order to stay on approved project schedule.

1. In addition to meeting general documentation requirements, document how the requested substitution benefits the Owner through cost savings, time savings, greater energy conservation, or in other specific ways.

2. Document means of coordinating of substitution item with other portions of the work, including work by affected subcontractors.

3. Bear the costs engendered by proposed substitution of:

a. Owner's compensation to the Architect for any required redesign, time spent processing and evaluating the request.

b. Other unanticipated project considerations.

D. Substitutions will not be considered under one or more of the following circumstances:

Substitution Procedures 012500 - 3

1. When they are indicated or implied on shop drawing or product data submittals, without having received prior approval.

2. Without a separate written request.

3.03 RESOLUTION

A. Architect may request additional information and documentation prior to rendering a decision. Provide this data in an expeditious manner.

B. Architect will notify Contractor in writing of decision to accept or reject request.

3.04 ACCEPTANCE

A. Accepted substitutions change the work of the Project. They will be documented and incorporated into work of the project by Change Order, Construction Change Directive, Architectural Supplementary Instructions, or similar instruments provided for in the Conditions of the Contract.

3.05 CLOSEOUT ACTIVITIES

A. See Section 017800 - Closeout Submittals, for closeout submittals.

END OF SECTION 012500

Substitution Request Form – After Receipt of Bids

All Substitution Requests shall be submitted by the Contractor only. Substitution Requests received from subcontractors, sub-subcontractors, manufacturers, vendors, etc., will be “rejected” without review.

General Information

Project Name

A/E Project Number

Specified Product/Item Information

Specification Title

Section

Page

Article / Paragraph

Description

Proposed Substitution Information

Proposed Substitution

Reason for not providing specified product/item

Comparative Data Attach a point-by-point comparative data list. Include all differences between the proposed substitution and the specified product/item. If not provided, this Request will be rejected.

Manufacturer

Manufacturer Address

Manufacturer Phone

Manufacturer Representative Email address

Trade / Model Name

Model Number

Installer

Installer Address

Installer Phone

History

New product

2-5 years

5-10 yrs

10 yrs or longer

Proposed substitution affects other parts of the Work

Yes No

If yes, explain

Savings to Owner for accepting proposed substitution

Proposed substitution affects Contract Time

Yes No

If yes Add Deduct

If yes, number of calendar days

Proposed Substitution Similar Installation

Have you (this Contractor) used this product/item on any other projects

Yes No

Project

Project Address

Architect/Engineer

A/E Phone

Owner

Owner Phone

Date installed

Attached Supporting Data

Drawings Product Data/Specs Samples Tests Reports

Contractor certifies all of the following:

Contractor shall provide specified product/item in the event this Substitution request is rejected.

Proposed substitution has been fully investigated and determined to be equal or superior in all respects to the specified product, except as may otherwise be specifically and clearly indicated herein.

If applicable, proposed substitution shall not adversely affect LEED requirements nor shall it prevent achieving the relative number of applicable LEED point[s] the specified product would have received.

Proposed substitution’s function, appearance, and quality are equal or superior in all respects to the specified product, except as may otherwise be specifically and clearly indicated herein.

Same or superior warranty and/or guarantees shall be furnished for proposed substitution as is required for the specified product/item.

Same maintenance service and source replacement parts, as applicable, are available; including local availability.

Proposed substitution shall have no adverse effect on other trades.

Cost data as stated herein is complete. Claims for additional costs related to the accepted proposed substitution which may subsequently become apparent shall be waived; including licenses, fees, and/or royalties.

Proposed substitution shall not affect dimensions and functional clearances. If the proposed substitution does affect dimensions and/or functional clearances, Contractor shall adjust the Work as required and necessary to accommodate the proposed substitution at no additional cost to the Contract.

Payment shall be made by the Contractor, via a deduct/credit Change Order, for changes to the building design, including A/E fees for the design and detailing, caused by the proposed substitution.

Coordination, installation, and changes to the Work as necessary for the accepted proposed substitution shall be complete in all respects.

Contractor Information

Submitted by

Signed By

Date

Email address of Signee above

Company Name

Address

Phone

Architect / Engineer Review and Action

Acceptance of this substitution request is an acceptance of only the manufacturer and product/item for general conformance with the design concept reflected in the Contract Documents. The A/E has made no attempt to verify specific performance data, or to check the details of the proposed substitution as to special features, capacities, physical dimensions, or code and/or regulatory compliance, all of which remain the responsibility of the Contractor.

Proposed Substitution is found to be acceptable for inclusion in Change Order, if approved by Owner – Provide submittals in accordance with Contract Document requirements.

Proposed Substitution is found to be acceptable as noted for inclusion in Change Order, if approved by Owner - Provide submittals in accordance with Contract Document requirements.

Proposed Substitution is rejected – Provide specified product/item.

Proposed Substitution submittal/form not in accordance with Contract Documents (not timely, incomplete)

Comments / Remarks

Reviewed by

Signed By

Date

END OF SUBSTITUTION REQUEST FORM

Administrative Requirements 013000 - 1

SECTION 013000

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 GENERAL ADMINISTRATIVE REQUIREMENTS

A. Comply with requirements of Section 017000 - Execution and Closeout Requirements for coordination of execution of administrative tasks with timing of construction activities.

B. Electronic File Distribution: Upon request, Contractor may be provided electronic files for use in coordination of the Work and preparation of submittals. Contractor shall submit a signed Request Form for Electronic Files, provided by the Architect.

1. Electronic files do not contain all of the information of the Bid Documents or Contract Documents for construction of the Project, and the Architect shall not be responsible for differences between electronic files, Bid Documents, and Contract Documents.

1.02 SUBMITTALS

A. General Contractor Personnel: Within 15 days after award of Contract, provide a summary of General Contractor's on site personnel. Identify each individual, beginning with project superintendent. List project responsibilities, cell phone number, and email address.

B. Subcontractors: Within 15 days after award of Contract, provide a summary of all companies and individuals engaged as subcontractors for any part of the Project. Include a contact name, company address, phone number, and email address, and identify what part of the Work shall be completed by each subcontractor.

C. Coordination Drawings: Submit completed Coordination Drawings for Architect's information.

1.03 SECURITY PROVISIONS

A. Background Check: The Owner requires that a background check be performed on all personnel working on the site. Comply with Owner's requirements for screening services.

Background check is to be performed by the Virginia State Police Virginia Criminal Record Check – Criminal History Records Check (SP-230). Maintain a list of all accredited persons, submit a copy to Owner on request. Additional information may be found at vsp.virginia.gov/services/criminal-background .

B. Identification Badges: Provide identification badges to each person authorized to enter premises. Badge shall include personal photograph, name, employer, expiration date, and an assigned number. Have personnel return badges to Contractor after completion of their portion of the Work.

1.04 PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

2.01 ELECTRONIC DOCUMENT SUBMITTAL SERVICE

A. All documents transmitted for purposes of administration of the contract are to be in electronic (PDF, MS Word, or MS Excel) format, as appropriate to the document, and transmitted via an Internet-based submittal service that receives, logs and stores documents, provides electronic stamping and signatures, and notifies addressees via email.

1. Besides submittals for review, information, and closeout, this procedure applies to Requests for Interpretation (RFIs), progress documentation, contract modification documents (e.g. supplementary instructions, change proposals, change orders), applications for payment, field reports and meeting minutes, Contractor's correction

Administrative Requirements 013000 - 2 punchlist, and any other document any participant wishes to make part of the project record.

2. It is Contractor's responsibility to submit documents in allowable format.

3. Subcontractors, suppliers, and Architect's consultants will be permitted to use the service at no extra charge.

4. Paper document transmittals will not be reviewed unless previously approved; emailed electronic documents will not be reviewed.

5. All other specified submittal and document transmission procedures apply, except that electronic document requirements do not apply to samples or color selection charts.

B. Submittal Service: Coordinate method for exchanging files no later than the Preconstruction Meeting. The Architect's Procore service and procedures can be used at no charge. If the Contractor chooses to use a different platform and methodology:

1. The Architect may reject the methodology or platform proposed and:

a. use the Architect's Procore service, or

b. the project team will revert to traditional hard-copy exchange;

2. or the Contractor shall bear the cost of software, licensing, training, etc., for the project team to participate.

C. Project Closeout: Architect will determine when to terminate the service for the project and is responsible for obtaining archive/record copies of files for Owner. If the Project Team uses an alternate platform preferred by the Contractor, the Contractor shall be responsible for distributing archive/record copies of files to Owner and Architect.

2.02 PRECONSTRUCTION MEETING

A. Architect will schedule a meeting after Notice of Award.

B. Attendance Required:

1. Owner.

2. Architect.

3. Contractor.

4. Owner's Commissioning Agent.

5. Major subcontractors, consultants, and others as necessary and appropriate.

C. Agenda:

1. Execution of Owner-Contractor Agreement.

2. Submission of executed bonds and insurance certificates.

3. Distribution of Contract Documents.

4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.

5. Designation of personnel representing the parties to Contract and Architect.

6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

7. Scheduling.

8. Site mobilization and utilization.

9. Other project-specific items on pre-distributed agenda.

D. Architect shall record minutes and distribute digital copies to Owner, Contractor, and other attendees. Contractor shall be responsible for distribution to subcontractors and other personnel affected by decisions made.

Administrative Requirements 013000 - 3

2.03 CONSTRUCTION WASTE MANAGEMENT CONFERENCE

A. Architect will schedule a meeting after Notice of Award. Upon mutual agreement of all parties, the CWM conference may be incorporated as part of the sustainability preconstruction conference above.

B. Attendance Required:

1. Owner.

2. Architect.

3. Contractor.

4. Demolition subcontractor.

5. Major subcontractors, consultants, and others as necessary and appropriate.

C. Agenda:

1. Waste generated during demolition activities:

a. Methods for reusing, recycling, and donating materials.

b. Identification of materials that must be disposed at a landfill.

c. How to quantify amounts of materials in each category.

2. Waste generated during construction and renovation activities:

a. Methods for reusing, recycling, and donating materials.

b. Identification of materials that must be disposed at a landfill.

c. How to quantify amounts of materials in each category.

3. How and where to separate waste on site.

4. Methods of documenting and reporting for amounts of material reused, recycled, donated, and landfilled.

2.04 INDOOR AIR QUALITY (IAQ) MANAGEMENT PLAN DEVELOPMENT SESSION

A. Architect will schedule a meeting after Notice of Award.

B. Attendance Required:

1. Owner.

2. Owner's Commissioning Agent.

3. Architect.

4. Mechanical engineer.

5. Contractor.

6. HVAC subcontractor.

7. Other major subcontractors, consultants, and others as necessary and appropriate.

C. Agenda:

1. Protection of Materials: Discussion of how and where materials that could impact IAQ will be stored, including but not limited to, the following:

a. Insulation.

b. Gypsum board.

c. Flooring materials.

d. Ceiling panels.

e. Furnishings.

f. Odorous chemicals.

2. Protection of HVAC: Discussion of how HVAC equipment will be stored, installed, and operated during construction.

Administrative Requirements 013000 - 4

3. Pathway Interruption: Discussion of how airflow between construction zones will be limited to prevent the spreading of pollutants from one part of the building to another.

4. Housekeeping: Discussion of how the building will be kept clean and dry.

5. Materials Installation Scheduling: Discussion of what wet (odor emitting) materials will be used on the project, in order to schedule their installation before fuzzy (odor absorbing) materials.

2.05 PREINSTALLATION MEETINGS

A. When required in individual specification sections, convene a preinstallation meeting at the site prior to commencing work of the section. Do not allow installation of affected work to proceed until preinstallation meeting can be held.

1. Include all preinstallation meetings on the Project Schedule.

B. Require attendance of parties directly affecting, or affected by, work of the specific section.

C. Notify Architect and Owner in advance of meeting date.

D. Prepare agenda and preside at meeting:

1. Review conditions of examination, preparation and installation procedures.

2. Review coordination with related work.

E. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

2.06 PROGRESS MEETINGS

A. Architect will make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

B. Attendance Required:

1. Owner.

2. Architect.

3. Contractor's superintendent.

4. Other subcontractors or consultants as required for the specific parts of the Work to be discussed.

C. Agenda:

1. Review minutes of previous meetings.

2. Review of work progress.

3. Field observations, problems, and decisions.

4. Identification of problems that impede, or will impede, planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of RFIs log and status of responses.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Maintenance of quality and work standards.

11. Effect of proposed changes on progress schedule and coordination.

12. Other business relating to the work.

D. Architect shall record minutes and distribute copies to the Owner, Contractor, and other consultants, Owner's representatives, or other third party attendees. The Contractor shall be responsible for distributing to any affected subcontractors and other personnel.

Administrative Requirements 013000 - 5

2.07 CLOSEOUT MEETING

A. Schedule and administer closeout meeting no later than 90 days before the scheduled Date of Substantial Completion.

B. Make arrangements for the meeting, prepare agenda with copies for participants, and preside at the meeting.

C. Attendance Required:

1. Owner.

2. Architect.

3. Contractor's superintendent.

4. Major subcontractors.

5. Other subcontractors or consultants as required.

D. Agenda:

1. Review closeout requirements and procedures in Division 1 Section "Execution and Closeout Requirements."

2. Review startup, testing, and adjusting of all systems, including testing/adjusting/balancing (TAB) and Commissioning.

3. Coordination of inspections by local authorities having jurisdiction and third party Special Inspectors as required to obtain Certificate of Occupancy.

4. Coordination of Owner's occupancy and changeover of utilities, insurance, and building keying/lock system.

5. Procedures for Contractor's Correction Punch List, Architect's Substantial Completion inspection, and Final Correction Punch List.

6. Delivery, turnover, and storage of maintenance materials, attic stock, special tools, and other non-installed materials.

7. Coordination of closeout documentation, including demonstration and training materials and videos, as built/record documents, operation and maintenance binders, and warranty binders.

8. Removal of temporary facilities, construction equipment, and tools.

9. Final cleaning, touchup, restoration, and preventive maintenance.

10. Coordination of final Applications for Payment.

E. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

2.08 DAILY CONSTRUCTION REPORTS

A. Include only factual information. Do not include personal remarks or opinions regarding operations and/or personnel.

B. Prepare a daily construction report recording the following information concerning events at Project site and project progress:

1. Date.

2. High and low temperatures, and general weather conditions.

3. List of subcontractors at Project site.

4. Approximate count of personnel at Project site.

5. Major equipment at Project site.

6. Material deliveries.

7. Safety, environmental, or industrial relations incidents.

8. Meetings and significant decisions.

Administrative Requirements 013000 - 6

9. Unusual events (submit a separate special report).

10. Stoppages, delays, shortages, and losses. Include comparison between scheduled work activities (in Contractor's most recently updated and published schedule) and actual activities. Explain differences, if any. Note days or periods when no work was in progress and explain the reasons why.

11. Directives and requests of Authority(s) Having Jurisdiction (AHJ).

12. Testing and/or inspections performed.

13. Signature of Contractor's authorized representative.

2.09 COORDINATION DRAWINGS AND COORDINATION CONFERENCE

A. Coordination Drawings: The Contractor shall prepare coordination drawings of all spaces where utilities, systems, and other components converge or intersect and efficient installation is required to accommodate all components.

1. Prepare coordination drawings of the following spaces, at minimum. Supplement with additional spaces as required by project-specific conditions.

a. Above ceilings.

b. Vertical chases, shafts, and wall cavities.

c. Mechanical and electrical rooms, fire pump room, and other major utility spaces.

2. Provide accurate overall dimensions of components (for example, outside diameters of pipe and conduit, or overall ductwork dimensions including insulation and enclosure thickness).

3. Include accessory components of systems that could cause potential conflicts, such as bracing, slotted channel framing, hangers, and other supports, valve handles, flanges, fittings, cable/wire management trays, and other similar components.

4. Include sequence of installation of all components, materials, and systems.

5. Include means of access to each component, material, or system, for maintenance and repairs.

6. Provide additional coordination drawings as required by individual specification sections.

7. Prepare Coordination Drawings using project-specific information. Do not use photocopies or reproductions of Contract Documents, and do not use standard details or data from manufacturers, suppliers, or other outside parties.

8. Drawing Files: The Contractor may develop coordination drawings using 2D CAD software or with 3D BIM software with clash-detection functionality.

a. The Architect will furnish original 3D BIM model or 2D DWG files for Contractor's use upon receipt of Architect's "Request Form for Electronic Files". A copy of this form shall be provided to the Contractor upon request.

1) The Architect makes no guarantee to the accuracy of components in electronic files. The Contractor shall coordinate electronic data with the Contract Documents in order to provide final Coordination Drawings.

2) If using 2D files, the Contractor shall prepare drawings in multiple views (for example, RCP and section) to fully represent 3D space, for example plenum heights, wall assembly thicknesses, etc.

9. Submittal: Submit Coordination Drawings as a "Submittal for Information." Architect will not approve Coordination Drawings, but will keep on file for use in subsequent coordination and conflict resolution.

B. Coordination Conference: Schedule and conduct a Coordination Conference prior to beginning construction or rough-in of affected work. Require attendance by all affected trades and installers.

Administrative Requirements 013000 - 7

1. Identify the Coordination Conference as a "milestone" date on the Construction Progress Schedule.

2. Advise the Architect of all potential conflicts identified in the Coordination Drawings and at the Coordination Conference.

3. Do not proceed with construction or installation of components, materials, or systems until potential conflicts have been resolved and affected parties have agreed to a remedy.

4. Remedies to address conflicts not identified in the Coordination Drawings, at the Coordination Conference, or otherwise addressed prior to construction or installation of affected components, materials, and systems, or discovery of a non-workable situation not identified or addressed, will not be considered as a basis for delay, time extension, or additional cost to the Contract.

2.10 REQUESTS FOR INFORMATION (RFI)

A. Definition: A request seeking one of the following:

1. An interpretation, amplification, or clarification of some requirement of Contract Documents arising from inability to determine from them the exact material, process, or system to be installed; or when the elements of construction are required to occupy the same space (interference); or when an item of work is described differently at more than one place in Contract Documents.

2. A resolution to an issue which has arisen due to field conditions and affects design intent.

B. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of Contract Documents.

This is the start of the file's text. The full file is on GovTribe.