This document is a Contract Data Requirements List (CDRL) for the Gymnasticator Upgrades project at Rock Island Arsenal. The CDRL outlines specific documentation requirements for the contractor, including six primary data items to be submitted at different stages of the project. Key documentation includes Installation and Preparation Documentation (with subtasks like Equipment Characteristics, Installation Documentation List, Tool List, Electrical and Hydraulic Schematics, and Equipment Identification), a Maintenance Manual with Preventive Maintenance Procedures, an Operator Manual, and Environmental Compliance Data including Safety Data Sheets and a Chemical List.
The documentation must be submitted in specific electronic formats (PDF, DXF, or Microsoft Word/Excel) with varying submission timelines, typically 30-60 calendar days before or at equipment delivery. All documentation will be sent to Rock Island Arsenal, specifically to Bob McClure at TARA-LGC, and must provide comprehensive details about the equipment, including standard and optional features, technical specifications, maintenance procedures, operational instructions, and environmental compliance information. This documentation supports the modernization of gymnasticator control systems for weapons systems including M1A1, M178/M182, M119, M119A3, M109, and M35.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation - W519TC26QA058.pdf | ||
| Attachment 0001 SOW Gynasticator Upgrades Project Services (27 Mar 20) (updated).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item) Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| DD Form 1423-1, SEP 97 (EG) (Computer Generated) | PREVIOUS EDITIONS ARE OBSOLETE | Page | 1 | of | 17 | Pages |
| A. CONTRACT LINE ITEM NO. |
B. EXHIBIT
C. CATEGORY
D. SYSTEM/ITEM
Gymnasticator Upgrades
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
Installation and Preparation Documentation
3. SUBTITLE
Equipment Characteristics
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
7. DD250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLOCK 16
| a. | ADDRESSEE |
| Draft | |
| Final |
| Reg |
| Repro |
16. REMARKS
The contractor shall provide a copy of this information in either electronic or paper format, no later than 30-calendar-days after award of the contract. The contractor shall provide this information in electronic format using Microsoft Excel format.
The specific data required is:
Identify required info from LMP
GYMNASTICATOR_TYPE
MACHINE_GROUP
SITE_CODE
WEAPON_SYSTEM
PROVIDE COPIES, AS REQUESTED TO THE FOLLOWING:
Rock Island Arsenal
ATTN: TARA-LGC
Bob McClure 2744 Rodman Ave (B220-B-D28) Rock Island, IL 61299-6400
SEE BLOCK 16
15. TOTAL
G. PREPARED BY
Dane Taghon
H. DATE
28-May-2025
I. APPROVED BY
J. DATE
CONTRACT DATA REQUIREMENTS LIST
Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| DD Form 1423-1, SEP 97 (EG) (Computer Generated) | PREVIOUS EDITIONS ARE OBSOLETE | Page | 2 | of | 17 | Pages |
| A. CONTRACT LINE ITEM NO. |
B. EXHIBIT
C. CATEGORY
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
Installation and Preparation Documentation
3. SUBTITLE
Installation Documentation List
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
7. DD250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLOCK 16
| a. | ADDRESSEE |
| Draft | |
| Final |
| Reg |
| Repro |
16. REMARKS
The contractor shall provide a copy of this information in electronic format, a minimum of 60-calendar-days prior to delivery of equipment. The contractor shall provide a second copy of this information in electronic or paper format at the time of delivery of the equipment. Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and Microsoft Word (.doc).
A plainly visible cover sheet shall be provided with the Installation and Preparation Documentation package listing drawings and schematics required for installation.
ATTN: TARA-LGC
Bob McClure
SEE BLOCK 16
15. TOTAL
G. PREPARED BY
H. DATE
28-May-2025
I. APPROVED BY
J. DATE
CONTRACT DATA REQUIREMENTS LIST
Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
Installation and Preparation Documentation
3. SUBTITLE
Tool List
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
7. DD250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLOCK 16
| a. | ADDRESSEE |
| Draft | |
| Final |
| Reg |
| Repro |
16. REMARKS
The contractor shall provide a copy of this information in electronic format a minimum of 60-calendar-days prior to delivery of equipment. The contractor shall provide a second copy of this information in electronic or paper format at the time of delivery of the equipment. Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and Microsoft Word (.doc).
An itemized list of all fixtures, tools, and equipment, whether special or not, required to install, align, and maintain the equipment in this purchase description. NOTE: The contractor is responsible for providing special/custom tools and equipment necessary for installation, moving, and/or set-up as part of the equipment.
ATTN: TARA-LGC
Bob McClure
SEE BLOCK 16
15. TOTAL
G. PREPARED BY
H. DATE
28-May-2025
I. APPROVED BY
J. DATE
CONTRACT DATA REQUIREMENTS LIST
Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
Installation and Preparation Documentation
3. SUBTITLE
Electrical Schematic
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
7. DD250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLOCK 16
| a. | ADDRESSEE |
| Draft | |
| Final |
| Reg |
| Repro |
16. REMARKS
The contractor shall provide a copy of this information in electronic format a minimum of 60-calendar-days prior to delivery of equipment. The contractor shall provide a second copy of this information in electronic or paper format at the time of delivery of the equipment. Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and Microsoft Word (.doc).
The equipment includes this type of utility and a complete system schematic is required. The capacity required at the point of first connection must be clearly stated.
ATTN: TARA-LGC
Bob McClure
SEE BLOCK 16
15. TOTAL
G. PREPARED BY
H. DATE
28-May-2025
I. APPROVED BY
J. DATE
CONTRACT DATA REQUIREMENTS LIST
Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
Installation and Preparation Documentation
3. SUBTITLE
Hydraulic Schematic
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
7. DD250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLOCK 16
| a. | ADDRESSEE |
| Draft | |
| Final |
| Reg |
| Repro |
16. REMARKS
The contractor shall provide a copy of this information in electronic format a minimum of 60-calendar-days prior to delivery of equipment. The contractor shall provide a second copy of this information in electronic or paper format at the time of delivery of the equipment. Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and Microsoft Word (.doc).
The equipment includes this type of utility and a complete system schematic is required. The total amount of fluid in the system and the amount in the reservoir must be clearly identified along with the type and grade.
ATTN: TARA-LGC
Bob McClure
SEE BLOCK 16
15. TOTAL
G. PREPARED BY
H. DATE
28-May-2025
I. APPROVED BY
J. DATE
CONTRACT DATA REQUIREMENTS LIST
Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
Installation and Preparation Documentation
3. SUBTITLE
Equipment Identification
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
7. DD250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLOCK 16
| a. | ADDRESSEE |
| Draft | |
| Final |
| Reg |
| Repro |
16. REMARKS
The contractor shall provide a copy of this information in electronic format a minimum of 60-calendar-days prior to delivery of equipment. Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and Microsoft Word (.doc).
This document shall consist of the make & model of the equipment with a complete list of standard features, optional features being installed in order to meet the specification, and a list of optional features available for field installation but not included. Each section shall be clearly identified.
Also included will be any technical data or brochures applicable to the equipment being provided.
ATTN: TARA-LGC
Bob McClure 2744 Rodman Ave (B220-B-D28)
SEE BLOCK 16
15. TOTAL
G. PREPARED BY
H. DATE
28-May-2025
I. APPROVED BY
J. DATE
CONTRACT DATA REQUIREMENTS LIST
Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
Maintenance Manual
3. SUBTITLE
Preventive Maintenance Procedure
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
7. DD250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLOCK 16
| a. | ADDRESSEE |
| Draft | |
| Final |
| Reg |
| Repro |
16. REMARKS
The contractor shall provide (3) copies of this manual/information with delivery of the equipment. Of these, (2) will be paper, and (1) shall be electronic. Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and Microsoft Word (.doc).
This section of the documentation shall include: Daily Operator Checklist, Visual Inspections, and a Lubrication Schedule. Procedures and schedules for inspections, adjustments, cleaning, and component replacements.
ATTN: TARA-LGC
Bob McClure
SEE BLOCK 16
15. TOTAL
G. PREPARED BY
H. DATE
28-May-2025
I. APPROVED BY
J. DATE
CONTRACT DATA REQUIREMENTS LIST
Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
Operator Manual
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
7. DD250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLOCK 16
| a. | ADDRESSEE |
| Draft | |
| Final |
| Reg |
| Repro |
16. REMARKS
The contractor shall provide (3) copies of this manual/information with delivery of the equipment. Of these, (2) will be paper, and (1) shall be electronic. Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and Microsoft Word (.doc).
This section of the documentation shall include: Procedures for safe operation of the equipment in all modes. It shall include information necessary for performing all the operations and utilizing all the functions listed in the purchase description.
ATTN: TARA-LGC
Bob McClure
SEE BLOCK 16
15. TOTAL
G. PREPARED BY
H. DATE
28-May-2025
I. APPROVED BY
J. DATE
CONTRACT DATA REQUIREMENTS LIST
Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
Environmental Compliance Data
3. SUBTITLE
Safety Data Sheets (SDS)
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
7. DD250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLOCK 16
| a. | ADDRESSEE |
| Draft | |
| Final |
| Reg |
| Repro |
16. REMARKS
The contractor shall provide (1) copy of this information in electronic format no later than 30-calendar-days prior to delivery of the equipment. Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and Microsoft Word (.doc).
SDS Sheets for all liquids (e.g. oils or coolants) and any hazardous materials shall be provided.
ATTN: TARA-LGC
Bob McClure
SEE BLOCK 16
15. TOTAL
G. PREPARED BY
H. DATE
28-May-2025
I. APPROVED BY
J. DATE
CONTRACT DATA REQUIREMENTS LIST
Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
Environmental Compliance Data
3. SUBTITLE
Chemical List
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
7. DD250 REQ
9. DIST STATEMENT REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
SEE BLOCK 16
| a. | ADDRESSEE |
| Draft | |
| Final |
| Reg |
| Repro |
16. REMARKS
The contractor shall provide (1) copy of this information in electronic format no later than 30-calendar-days prior to delivery of the equipment. Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and Microsoft Word (.doc).
A list of all chemicals necessary to operate the equipment shall be provided by the vendor. This is necessary in order to meet environmental compliance requirements. The list shall include the type, grade, and quantity of each liquid or gas regardless of who is to provide the actual material. (E.g. if hydraulic oil is necessary to operate the system, it shall be listed as 200-gal-u.s. of DTE-XX.)
ATTN: TARA-LGC
Bob McClure
SEE BLOCK 16
15. TOTAL
G. PREPARED BY
H. DATE
28-May-2025
I. APPROVED BY
J. DATE
File details come from the government source that posted it. Updated .