EXHIBIT 2 - PRS.pdf

PDF 136 KB Posted

Attached to
RFP Chemical, Environmental, and Munitions (Unrestricted) - CHEM-RU
Solicitation number
W912DY-20-R-016
Issued by

About this file

This document outlines performance requirements for a Chemical, Environmental, and Munitions Response contract. The contract supports the Military Munitions Response Program by providing services for conventional munitions and chemical warfare material responses, environmental compliance and remediation, and other munitions-related activities. Key performance standards include maintaining high safety standards with no Class A safety violations, completing at least 80% of deliverables within two submissions, obtaining approval for all key personnel changes, and receiving no more than five corrective action requests per task order. Performance will be monitored according to metrics like customer satisfaction surveys, inspection reports, and number of resubmissions and corrective actions. Incentives for meeting standards include positive past performance evaluations, while failure to meet them could result in cure notices, terminations, or adverse past performance reports.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 2

Performance Requirements Summary

Contract Level Objectives Performance Standard Acceptance Criteria Measurement/

Monitoring Method Incentive/Disincentives For Meeting or Not Meeting the Acceptable Quality Level

Quality of Product or Service Client satisfaction

Client satisfaction and quality

95% of comments express overall satisfaction

Feedback may be obtained via CEHNC customer satisfaction survey

A Contractor not receiving satisfactory appraisals may have an adverse past performance report issued.

Quality Performance Over All Task Orders Awarded

Quality performance IAW contract PWS and Task order PWS.

80% of all final deliverables received are accepted within 2 submissions

Feedback may be obtained via CEHNC customer satisfaction survey, COR records

A Contractor not receiving satisfactory appraisals may have an adverse past performance report issued.

Project Management Key Personnel Management of Key

Personnel Contractor submits 100% of all key personnel changes to the KO for approval before changes made at the Contract and/or Task Order level.

Key personnel are not routinely changed (more than 2 times) on one or more projects (or more than 3 times for key personnel overseeing base contract requirements over the life of the contract.

COR Surveillance A Contractor not receiving satisfactory appraisals may have an adverse past performance report issued.

Task Order Level – The performance requirements in this summary will be included in every task order. Other performance requirements may be included with the task order as appropriate for the particular project.

Desired Outcomes

Required Services Performance Standards

Monitoring Method Incentive/Disincentives For Meeting or Not Meeting the Acceptable Quality Level

Quality of Product or Service Safety Maintain high safety standards Zero Class A Safety violations where the Contractor is determined at fault.

Submission of accident reports, adverse safety inspection reports, and similar documents.

Issuance of a cure notice and possible termination of task order or contract for continuous or uncorrected safety violations, and/or adverse past performance reports may be issued.

Performance Compliance with PWS and referenced applicable regulations

No more than 5 CARs received by the Contractor within a given task order

COR Submission of CARs, COR report of failure to delivery acceptable product or service in accordance with Performance-Based Milestones/Objectives.

Issuance of a cure notice and possible termination of task order or contract for continuous or uncorrected performance deficiencies, or for failure to complete Performance-Based Milestones/Objectives, and/or an adverse past performance report may be issued.

File details come from the government source that posted it. Updated .