Exhibit 1 (Technical Specifications)~6.doc

DOC document 52 KB Posted

Attached to
ESB - ODOT La Grande I-84 -Crack Seal
Solicitation number
S-73000-00012391
Issued by
Umatilla County, Oregon

About this file

This is a Technical Specifications document (Exhibit 1) from the Oregon Department of Transportation for a crack sealing project on Interstate 84 in District 13. The project involves repairing and resealing cracks in flexible pavements along I-84 from mile post 254.5 to 269.5 in both eastbound and westbound lanes, covering approximately 258,000 linear feet. The work must commence after March 1, 2025, with final completion by June 20, 2025. The contractor must supply all labor, equipment, machinery, materials, and traffic control, with capability to prepare and seal approximately 10,000 linear feet per 10-hour shift. A pre-construction meeting is required, but no pre-bid conference is necessary.

The technical specifications require the contractor to use approved sealant materials from the QPL, with mixing and heating between 280-400 degrees Fahrenheit. Traffic control must accommodate freight mobility standards with 22-foot horizontal clearance for oversized loads, allowing delays up to 20 minutes. The contractor must mark completed quantities in half-mile sections and seal cracks 1/8 inch or wider, excluding alligator areas. All work must comply with the 2024 Oregon Standard Specifications for Construction, and the Project Manager for this section is Brian Wiggins.

View the file

Other files

File Type Posted
00012391 Intent To Award.xlsx XLSX spreadsheet
Q&A #1.pdf PDF
ESB.RFCQ.Attachments~1.docx DOCX document
ESB.RFCQ.Services~1.docx DOCX document
00012391 Preliminary Results.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 1 (Technical Specifications)

PROJECT SPECIFICATIONS

District 13 Crack Seal Locations and Project Manager

Item No.
State Highway
Route Number
Estimated Mile Post Location
Estimated Linear Feet
Project Manager
Phone No.

I-84

254.5 – 259.5 EB in the A lane & 260-269.5 EB &WB in the A&B lane

258,000

Brian Wiggins

541-963-0168

Start Date: After 03/01/2025 Final Completion Date: 06/20/2025 Scope - This project scope consists of supplying all labor, equipment, machinery, material, and traffic control for repairing and resealing cracks in flexible pavements at the described location in the designated state highway section in District 13 according to the Oregon Standard Specifications for Construction 2024 and modifications listed in these contract documents.

General - The Contractor shall always have a responsible party on the job while work is in progress, capable and with authority to make job-site decision as an official Contractor's representative. The Contractor shall provide the Project Manager with a summarization of activities and work performed daily if requested. The Contractor shall mark the quantity of cracks completed in spray paint on the shoulder in half mile sections for verification purposes.

Contractor shall have pre-con meeting with Project Manager.

Contractor shall start at M.P. 254.5 and work east in the A lane to M.P. 259.5 Contractor shall then start at M.P. 260 and work the B lane to M.P.269.5

Contractor shall then start at M.P. 269.5 and work west in the B lane to M.P. 260

Contractor shall then run the meat line in the A lane from M.P.260 to M.P.269.5 EB and WB

Contractor shall carry on the work and adhere to the contract schedule during all disputes or disagreements with the State. No work shall be delayed or postponed pending resolution of any disputes or disagreements, except as specifically permitted by the specifications or as Contractor and State may otherwise agree in writing.

The Contractor must follow the manufacture recommendation for applying the product. The pavement temperature must be 40° and raising for the minimal and the district recommends no crack sealing when the pavement temperature exceeds 130°.

Contractor shall meet with the State Project Manager for a pre-work conference at a time mutually agreed upon. Work shall commence within five working days of this meeting, providing the Notice to Proceed has been issued. A pre-bid conference will not be required. Bidders are solely responsible for inspecting the sites prior to bidding. In no event shall failure to inspect the site constitute grounds for charges to the State more than the bid price. The Project Manager will be as listed above for the section they will be in.

2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION: The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed technical specifications that apply to this Request for Competitive Quotes and resulting Contract.

Some sections of the technical specifications are identified and modified below. Sections of the technical specifications not identified below remain applicable to the Contract according to their original terms. Part 00100 of the Standard Specifications (General Conditions) is not applicable to the Contract; however, if a technical specification (Parts 200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the technical specification. The Standard Specifications are available online:

http://www.oregon.gov/ODOT/HWY/SPECS/Pages/standard_specifications.aspx Section 00746 - Crack Sealing Flexible Pavements

Comply with Section 00746 of the Standard Specifications modified as follows:

Description

00746.00 Scope – Replace paragraph with:

Work of this contract consists of supplying all labor, material, equipment, machinery, and traffic control for repairing and resealing cracks in flexible pavements at locations designated by the Project Manager. Crew size will be the contractor’s option, but the crew must be able to prepare and seal approximately 10,000 linear feet per 10-hour shift.

Materials

00746.10 Sealants – Furnish all sealant materials for crack repair of flexible pavements that is approved in the QPL. Before beginning work, furnish a complete written statement of origin, composition and manufacturer of materials that are to be used.

Equipment

00746.20 Equipment - Replace paragraph with:

Use proper sealing equipment for the specific material listed according to the manufacturer's recommendations. The equipment for sealing compounds shall be a melting kettle of the double boiler, indirect heating type, using oil as a heat-transfer medium. The kettle shall be an effective, mechanically operated agitator equipped with a positive, thermostatic temperature control. All equipment and installation procedures are subject to prior approval of the ODOT Section Manager/Project Manager.

Construction

00746.40 General - Revise: 00225.01 (C): For this contract, refer only to the bulleted item: ODOT “Oregon Temporary Traffic Control Handbook for…”

ADD THE FOLLOWING PARAGRAPHS:

Traffic control for this contract shall be set-up in 2-separate work zones to meet Freight Mobility standards. Traffic cones for the lane joint work zone shall be placed to the right of centerline far enough to allow for 22’ of horizontal clearance to accommodate oversized load movement in the travel lane.

The contractor shall be able to accommodate all loads, including oversize loads. Work equipment and traffic control devices must be able to be moved quickly to enable a load that approaches the work zone unannounced to be waved through. Waved through means that for width, length or weight the work equipment and traffic control devices can be moved (and there is an understanding that it would be) if a permitted vehicle comes to the work zone the contractor shall provide the required clear distance. This may result in a slight delay to the oversize load or the traffic behind the load. It is okay to have a slight delay up to 20 minutes if the load can get through the work zone.

Contractor shall notify property owners 24 hours prior to any work that will interfere with or restrict the use of their property or improvements, such as but not limited to driveways, mailboxes, and utilities.

00746.41 Mixing and Heating - Follow the manufacturer's recommendations for application. Mix and heat the sealant materials to a minimum temperature of 280-degree F. Do not heat the material above 400-degree F.

00746.42 Installation Procedure – Add the following paragraphs: In the event of adverse weather conditions the Contractor shall receive authorization from the State Project Manager before continuing work.

Contractor shall seal cracks 1/8” or wider. “Alligator” areas shall not be sealed.

00746.43 Cleaning and Sanding – Add the following paragraph: The Contractor shall be responsible for cleanup and removal/disposal of all materials used on the project, including all containers of crack sealant materials. Left over materials and containers, (including but not limited to items classified as “hazardous materials”), that are designated as excess or refuse by the State Project Manager shall become the property of the Contractor and disposed of in accordance with all local, State, and federal guidelines.

Measurement

00746.80 Measurement – The quantities of sealed cracks will be measured by length.

Payment

00746.90 Payment – The accepted quantities of sealed cracks will be paid for at the Contract unit price, per foot as appropriate, for item “Crack Sealing”.

Payment will be in full for furnishing and placing all materials, and for furnishing all equipment, labor, traffic control and incidentals necessary to complete the work as specified.

No separate or additional payment will be made for required cleaning and routing.