This file is the General Requirements specification (Section 01 11 00 and related sections) for a Job Order Contract (JOC) at Joint Base Lewis-McChord and associated sub-installations in Washington State.

The contract is an indefinite delivery, indefinite quantity (IDIQ) vehicle for maintenance, repair, and minor construction work across multiple facilities including JBLM, Yakima Training Center, Fort Worden Cemetery, and Fort Lawton Cemetery. Work encompasses diverse trades including civil work, road repair, carpentry, roofing, excavation, electrical, HVAC, plumbing, sheet metal, painting, fencing, demolition, concrete, masonry, welding, and incidental asbestos and lead abatement. The Government will issue individual Task Orders (TOs) to the contractor, who must maintain a management office at JBLM to receive Requests for Task Order Proposals (RTOPs), prepare proposals, and manage correspondence. Contractors must respond to RTOPs within 14 calendar days of the RTOP date or site visit, whichever is later. Pricing is based on RSMeans construction cost data accessed through E4Clicks computerized pricing guide (CPG), with localized costs determined by City Cost Index and multiplied by the contractor's coefficient. The contractor's coefficient encompasses all indirect costs, taxes, insurance, mobilization, overhead, permits, safety, and project management not included in pre-priced line items, with non-pre-priced work limited to 10% of total TO value. Period of performance is negotiated per TO or calculated using a specified formula incorporating TO price, Master Format divisions, concrete/masonry work, advance notices, environmental permits, and material submittals. Contractors must provide e4Clicks software, maintain computer systems with specific software requirements, provide electronic as-built drawings, and establish a single administrative email address for all Government communications. Work is performed during regular hours (7:30 a.m. to 4:00 p.m., Monday–Friday, excluding federal holidays) unless KO approval is obtained seven calendar days in advance. Performance and payment bonds equal 100% of the original contract ceiling, insurance requirements include workers' compensation ($100,000), comprehensive general liability ($500,000 bodily injury per occurrence), and comprehensive automobile liability ($200,000 per person, $500,000 per occurrence), with all bonds and insurance required within 10 calendar days of contract award.

View the file

Other files

File Type Posted
Sources Sought Notice - JOC solesource.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 11 00 - 1

DIVISION 1, GENERAL REQUIREMENTS

SECTION 01 11 00 SUMMARY OF WORK

1. PART I DESCRIPTION OF WORK:

Provide all plant, labor, tools, equipment, and materials (except as indicated otherwise in the specifications) and perform all work in strict accordance with the specifications and plans required for the Job Order Contract (JOC).

The JOC is for a broad range of maintenance, repair and minor construction work on real property at Joint Base Lewis-McChord (JBLM) and other supported organizations as listed below. The work is required in support of Public Works (PW) activities headquartered at Joint Base Lewis-McChord (JBLM). The contract will be an indefinite delivery indefinite quantity type contract and will include a wide variety of individual construction tasks.

During the contract period, the Government will identify construction tasks required to complete each specific job and will issue individual Task Orders (TOs) to the contractor to complete those jobs. The contractor shall be required to furnish all materials, equipment and personnel necessary to manage and accomplish the TOs. The contractor shall be required to maintain a management office on JBLM in order to receive Requests for Proposal (RFPs), prepare and negotiate proposals, receive signed TOs and Notices-To-Proceed (NTPs), receive and initiate contract correspondence and provide other construction services to accomplish individual TOs. TOs will vary in size, with the majority expected to be of a small to medium size, and may include single or multiple disciplines.

The TOs will include tasks in a variety of trades, such as civil work, road repair, carpentry, roofing, excavation, interior/exterior electrical, steam fitting, HVAC, plumbing, sheet metal, painting, fencing, asbestos and lead abatement (incidental to the work), demolition, environmental clean-up (incidental to the work), concrete, masonry, and welding.

1.1 AREA DESCRIPTION

The work will be performed on facilities at Joint Base Lewis-McChord (JLBM), Washington and Sub- Installations. The listing below is intended to be a comprehensive list, but the Government reserves the right to order work at other locations in WA if required. This contract does not involve work at Madigan Army Medical Clinic locations.

1.1.1 JBLM Sub-Installations:

1.1.1.1 Yakima Training Center, Yakima, WA

1.1.1.2 Fort Worden Cemetery, Port Townsend, WA

1.1.1.3 Fort Lawton Cemetery, Seattle, WA

1.2 PRINCIPAL ITEMS TO BE ACCOMPLISHED

1.2.1 Provide, remove and dispose of, replace, repair or modify architectural, structural, civil, mechanical or electrical features or system of a facility, range, landscaping or road work.

1.2.2 Provide exterior service systems for civil, mechanical or electrical systems of a building.

1.2.3 Provide all necessary requirements for the proposal support documents as specified in the TO.

1.2.4 Provide electronic “as-built" drawings. As-Built drawings are only required for the extents of each task order and any supporting systems affected by the extents of the task order.

1.2.5 Provide operation and maintenance manuals for any installed equipment and supply at least 4 hours of training on any installed equipment as required.

1.2.6 Perform other work necessary as described in the TO.

01 11 00 - 2

1.2.7 The Contractor shall be responsible for providing a complete and useable system and shall be responsible for accomplishing all tasks incidental to the completion of the task order requirements. Requirements for a complete and useable product which are not explicitly called out in the SOW but reasonably discernable via any method other than destructive testing shall be considered a requirement of the Task Order.

1.3 PERIOD OF PERFORMANCE

1.3.1 The period of performance is the period between TO Award and the time all work under the TO is complete.

The period of performance will be negotiated for each TO.

1.3.2 In the event the Government and contractor cannot agree upon a Period of Performance, the following formula shall be used to calculate the period of performance.

Period of Performance (Calendar Days) = 5 + 0.00028A + B + C + D + E + F + G

A = The TO price in dollars.

B = The number of Master Format Divisions from which the contractor has drawn line items in pricing the project. Divisions 2 through 44 (This variable would have maximum quantity of 26 if all divisions were utilized).

C = 14 days if the project requires new concrete or masonry construction or new plaster or drywall installation. If no such work is required then C = 0.

D = 10 days if an advance construction notice for family housing or an occupied facility is required. If no such advance notice is required then D = 0.

E = any number of extra days so determined by the Government to be necessary for the proper execution of the work when extraordinary circumstances are present. For example, extensive laboratory testing of materials, unavailability of materials, extensive utilities coordination, or the Contracting Officer (KO) has determined that allowing extra days will be in the best interest of the Government.

F = 10 days if Environmental Permits are required.

G = 15 days if the TO requires Government Approved Material Submittals.

1.4 DRAWINGS

Drawings applicable to all work performed under this contract will be provided with individual TOs when available. The Government does not guarantee the complete accuracy of these drawings or guarantee the existence of any drawings. The accuracy or existence of any drawings does not relieve the Contractor from the responsibility of providing electronic As-Built drawings at the end of a project. The Contractor is required to provide As-Built drawings on all task orders regardless of the availability of existing As-builts or CADD files.

1.4.1 Plans and Specifications: The contractor shall be provided one copy of the Statement of Work, specifications, drawings, and maps as applicable upon issuance of each TO. All further reproduction shall be at the contractor's expense.

1.5 CONSTRUCTION PHASING

The following construction phasing related issues shall affect the work:

1.5.1 Interface with Others: Government use of the facilities is anticipated while the work under this contract is being performed. The work shall be planned and accomplished so that there will be a minimum of interference and inconvenience to occupants in the building and agencies in the vicinity and to other craftsmen who may have

01 11 00 - 3 to do work in the affected facilities. Any blockage of building exits or driveways must be coordinated in advance.

1.5.1.1 Furniture, portable office equipment and wall appurtenances not rigidly fastened to the walls shall be moved by the contractor, protected from damage and replaced to original position upon completion of the work. If the work required by the TO will not allow furniture and portable office equipment to be replaced to its original position, new locations will be designated by the KO or Contracting Officer’s Representative (COR).

Incidental costs associated with moving one-piece furnishings up to approximately 150 pounds to perform such tasks as painting, carpet or tile replacement, etc., are considered a general cost of building renovation and shall be included in the contractor’s coefficient. Costs for large scale or wholesale removal and replacement of large quantities of desks or modular workstations, copiers, multiple full file cabinets, etc. to another location or storage outside the work space, or disassembly and reassembly of modular furniture is not considered part of the contractor’s coefficient and will be priced separately.

1.5.1.2 The work shall, so far as practicable, be done in definite sections or divisions and confined to limited areas which shall be completed before work in other sections or divisions begins.

1.5.2 Work Site Conflicts: In the event of a conflict between the contractor and others in an occupied facility or where other contractors are performing work on the same facility under other contracts, the KO shall attempt to resolve the conflict and the KO's decision shall be final.

1.5.3 Construction Restrictions: Construction restrictions shall be identified as required and indicated on individual TOs. Utility outages require 14 calendar day advanced notice.

1.6 CONTRACT COST BASIS FOR PRICING INDIVIDUAL TASK ORDERS

RSMeans construction cost data has been selected for use as the cost basis for all work under this contract.

E4Clicks shall be the designated Computerized Pricing Guide (CPG). The CPG and RSMeans shall be used as the Total Cost Data for this contract.

1.6.1 Computerized Pricing Guide: The CPG contains unit price construction line items for the description of work to be accomplished and for the unit of measure specified. Line items shall be selected that most accurately and completely represent the work being accomplished in a TO scope. Due to the vast variety of construction items and actions, it shall be understood that line items are considered representative of the work when the line item description meets the majority of the requirements and specifications; pricing is not a factor when determining most accurate and complete line items. When an agreement cannot be made regarding the applicability of a line item, the contractor shall get a written determination from RSMeans, routed through the Government Project Manager to ensure an accurate portrayal of the circumstances, stating the definition, correct use of, and/or any other direction necessary to establish the most accurate and applicable line item. Line item costs will be determined by multiplying the RSMeans “20XX Total Bare Costs” by the nearest available City Cost Index (CCI) to localize the costs. The localized costs are then multiplied by the appropriate contractor’s coefficient. Supplemental items priced by the contractor in the bid schedule, if accepted, shall be treated as pre-priced line items, added to the CPG, and shall receive the same CCI markup and then be multiplied by the appropriate contractor’s coefficient.

1.6.1.1 City Cost Index determination: This contract shall utilize the CCI corresponding to the quarter in which the base contract is awarded and shall be applied to all TOs issued during the entire Base Period. Subsequent anniversary years will incorporate the applicable RSMeans City Cost Index in effect at the anniversary date of the base year award and shall be applied to all TOs for the entire anniversary year. If the new CCI is not available at time of the anniversary year, the CCI for the previous QTR shall be used until the proper CCI is acquired.

1.6.2 The contractor shall purchase, maintain and use the latest version (at time of award) of e4Clicks commercial cost estimating and project management software tool. The contractor shall use this software to estimate and submit all of their projects, both electronically and on paper. The contractor is responsible for deciding the number of copies of the software that they will need to support their contract requirements.

01 11 00 - 4

1.6.3 Upon anniversary of the year award, the contractor shall update, at its own expense, the versions of the RS Means databases in effect at the anniversary of the base year for its use throughout the full year, in as many licenses and copies as listed for the base period. This requirement applies to all software and books listed above.

1.7 CONTRACTOR’S PRICING

Contractor’s pricing shall consist of the contractor’s coefficient as listed in the Coefficient Schedule

1.7.1 Contractor’s Coefficient: The contractor’s coefficient is a numerical factor that represents contractor costs

(indirect and direct costs, sales tax, profit, etc.) not considered to be included in the Total Cost Data. The contractor’s coefficient shall encompass all allowable contractor costs not included in the pre-priced line item cost. Examples of such costs include: state taxes and payroll taxes, such as FICA, workmen’s compensation, state and federal unemployment taxes for direct payroll employees, superintendent salaries, builders risk insurance, contract mobilization and demobilization expenses and bond premiums; and various overhead expenses such as project estimating, site office overhead, field office buildings, furniture and equipment, on-site office staff salaries, vehicle and construction equipment maintenance, office administrative expenses and a proportional share of home office overhead. The contractor’s coefficient shall also include all insurance, additional supervision, paperwork fees associated with a particular TO (i.e.

digging, environmental or PSCAA permits, estimates, reports, etc.), consultant fees, on- and off-site storage (except storage containers where required for property security by the TO), etc. The contractor’s coefficient shall encompass all costs other than the pre-priced unit prices and shall include all adjustments to the Total Cost Data to compensate for any difference between these costs and actual market conditions in the applicable locality. The contractor’s coefficient shall also include costs described as costs to provide submittals, interface with Government representatives, coordination with occupants and other contractors.

1.7.1.1 The contractor’s coefficient shall also include costs for, but not limited to:

a. All Waste and excess material

b. Mobilization and close out for the basic contract and each task order as well as mobilization for the subcontractors for each task order.

c. Clean up on each TO

d. Safety (i.e.; Safety Rails, Safety Nets, tethers, hardhats and safety glasses, personal protective equipment, dust barrier polyethylene sheeting, dust control for equipment, etc.)

e. Project management and supervision

f. Quality Control

g. Office management and supervision

h. Depreciation of mobile office(s)

i. Subcontractor overhead and profit

j. Electronic As-built drawings, submittals, permits, and licenses

k. Risks of doing business (i.e., risk of lower than expected contract dollar value; risk of a high inflation cost; risk of poor subcontractor performance and re-performance.

l. Site Security

m. Electrical Circuit and plumbing/HVAC pipe tracing/identification

n. Acceptance Testing

o. Manufacturer Training provided to DPW (ex: Mechanical equipment training).

p. Costs associated with complying with Environmental and Safety Laws

q. Any and all costs incurred and associated with preparing a proposal and the corresponding proposal support documents as described in the individual TOs.

r. Pre-Scoping Meeting

1.7.1.2 The contractor’s coefficient shall not include costs for work performed per specification 23 05 93 Testing, Adjusting and Balancing of HVAC systems or 23 08 00.00 10 Commissioning of HVAC Systems.

1.7.1.3 The following Subdivisions, as contained in the Total Cost data, shall not be used as line items when pricing TOs issued under this contract. These costs shall be included in the contractor’s coefficient:

01 11 31 – Professional Consultants 01 21 – Allowances

01 11 00 - 5

01 31 – Project Management and Coordination 01 32 – Construction Progress Documentation 01 41 26 – Permits 01 45 – Quality Control 01 52 – Construction Facilities 01 54 23 70 – Scaffolding 01 54 33 40– Rental of Vacuum Cleaners, Pickup Trucks, Portable Toilets, Ladders 01 55 – Vehicular Access & Parking 01 56 16 10 – Dust Barriers & Polyethylene sheets 01 71 – Examination and Preparation 01 74 – Cleaning and Waste Management (Rubbish removal shall be covered in Div. 02 41 19).

22 01 02 20 – Labor adjustment factors other than elevated work 26 01 02 20 – Labor adjustment factors other than elevated work.

1.7.1.4 Provisions have been made in the Coefficient Schedule for allowing different contractor’s coefficients for differing geographical locations. It also provides for separate contractor’s coefficients for work during normal working hours and work during other than normal working hours as well as escort and non-escort required work and non-pre-priced line items.

1.7.2 Anniversary Year Adjustments:

1.7.2.1 The Coefficient Schedule. Contractor’s coefficients are proposed as a percentage increase, (e.g. 1.10) or decrease (e.g. 0.95) to the Total Cost Data. The coefficients, as proposed, are accepted and incorporated into the contract and are used in establishing the price for TOs. No adjustments of accepted coefficients will be made after contract award. Annual increases or decreases in line item unit prices will be made by the incorporation of the current RSMeans Bare Cost databases at each anniversary year. Coefficients will not be adjusted for any other changes or circumstances encountered during the life of the contract. When it is determined that a TO requires modification, the contractor shall calculate his proposal using the same Total Cost Data that was used in calculating the basic TO, regardless of the date of the modification.

1.7.2.2 New Davis-Bacon rates will be incorporated at each anniversary of the base year.

1.7.3 Non-Pre-priced Work. Non-pre-priced work (i.e. Work not priced by the Total Cost Data including the Supplemental Items) shall not exceed 10% of the total TO pre-priced amount. Items of work not covered by Total Cost Data, including the Supplemental Items, but within the scope and general intent of this contract may be negotiated at any time during the contract term and added to the list of Supplemental Items by modification if requested. The price of a line item is not justification for choosing to utilize a Non-pre-priced item, only the lack of salient characteristics are justification for utilizing the Non pre-priced item process. Non-pre-priced work shall be noted on the contractor's TO proposal and shall include all direct and indirect costs and shall be accompanied by three independent quotes for the non-pre-priced items deemed necessary for the completion of the work under the TO. The Contractor shall use the lowest bid of the 3 independent quotes. The contractor’s coefficient shall be the only adder applied to the non-pre-priced item.

1.8 ORDERING AND PROCESSING PROCEDURES FOR TOS:

When the Government requires work under this contract the Government will request a price from the contractor for “one job, lump sum” TO.

1.8.1 The Government will provide the contractor a Request for Task Order Proposal (RTOP) containing a statement of work, drawings, sketches, and/or other documents as deemed necessary to provide sufficient detail for the JOC contractor to discern the project requirements for the TO after attending a pre-proposal site visit. The contractor shall also research existing record drawings and independently conduct as many site visits as necessary to have a satisfactory knowledge of the site conditions that can affect the work or its cost.

1.8.2 The contractor shall respond within fourteen (14) calendar days of the RTOP date or site visit, whichever is later, or as otherwise indicated on a case-by-case basis as determined by the KO. The 14 calendar day

01 11 00 - 6 duration may start from the site visit date as long as the site visit occurs within 5 business days from the RTOP. If the site visit cannot be completed before the 5 day duration, the 14 calendar day requirement shall start 5 calendar days after the RTOP. If the Contractor submits a late proposal, a Contract Deficiency Report (CDR) shall be sent to the Contractor and shall be recorded in the contract file. The Contractor may request an extension to their proposal due date but this request must be received 3 business days prior to the original proposal due date and provide justification as to specifically why an extension is required.

Awaiting Subcontractor pricing is not an acceptable reason to request a proposal due date extension.

Contractor shall respond to a RTOP by submitting a proposal containing the following to the KO:

1.8.2.1 Contractor Line Item Proposal. A standard CPG printout, listing the contractor’s proposal by specific items and quantities multiplied by CPG price and then the appropriate CCI and appropriate contractor’s coefficient. The contractor shall first attempt to price all work using the CPG system. . Items not contained in the CPG system Facilities Construction with Assemblies Cost Data database will first be searched for in the other databases, then in the hardcopy books and then, if not found, will be priced separately as non-pre-priced (NPP) items. Any items omitted from the Contractor’s proposal but ultimately required for completion of the task order are still requirements of the Task Order. It is the Contractor’s responsibility to ensure all required elements of work are captured in the proposal. This line item proposal shall be supplied in PDF and e4Clicks form.

1.8.2.1.1 Line Item Cost Adjustments: The only adjustment of price for the construction line items is the contractor’s coefficient. All prices in the CPG are for complete and in-place construction unless explicitly described otherwise. Line items shall be quantified as required for installation, not the quantity acquired from a manufacturer (ex: if carpet tiles are only ordered in 100 SF increments, a 150 SF room will be estimated at 150SF and not 200SF). Incidental fasteners (nails, screws, weldments, adhesives or other connectors) and hand tools required for a normal installation are to be understood that they are included in the line item cost unless the line item description specifically states otherwise. Line item prices include all work required to provide a finished product specified in the line item unless the line item description specifically states otherwise. Installed line items shall include the testing, adjusting and initial start up of the specific line item, except for specifications 23 05 93 Testing, Adjusting and Balancing of HVAC systems and 23 08 00.00 10 Commissioning of HVAC Systems.

1.8.2.1.2 Linear interpolation between line items shall be used when an item size is between two existing CPG line items, and the resulting item is a manufacturer's standard size. The price of the interpolated item shall be based on linear interpolation based on the prices and sizes of the two closest CPG line items (in size) above and below the interpolated item.

1.8.2.1.3 Linear extrapolation beyond line items shall be used when an item size is within 50 percent of existing

CPG line items, and the resulting item is a manufacturer's standard size. The price of the extrapolated item shall be determined using linear extrapolation based on the bare costs and sizes of the two closest CPG line items (in size) either above or below the extrapolated item and then added to or subtracted from the closest CPG Line Item, depending upon whether the manufacturer's standard size is larger or smaller than the size in the CPG.

1.8.2.1.4 Non-Pre-priced Items. The value of NPP work under a TO shall not exceed 10 percent of the value of the pre-priced work. Non-pre-priced work shall be noted on the contractor’s proposal as such and shall include all direct and indirect costs and shall be accompanied by three independent quotes for the non-pre-priced items deemed necessary for the completion of the work under the TO. The contractor’s coefficient shall be applied to non-pre-priced items and shall be the only addition to the low bid from the 3 independent quotes. Items of work not covered in the CPG or RSMeans pricing guides but within the scope and general intent of the contract may be negotiated and added to the list of Supplemental Items by modification at any time during the contract term.

1.8.2.1.5 Removal and Reinstallation Items. If an item is to be removed and reinstalled and a line item can be found in the Unit Price Book (UPB) for removal and reinstallation, that line item will be used. If there is no line item for removal and reinstallation, the contractor shall represent this work with two (2) line items; the demolition line item shall be used to represent the removal, and the installation line item with no material cost shall be used to represent the reinstallation. If this approach is not possible, the contractor shall locate

01 11 00 - 7 the material line item in the UPB. Then the contractor will create an alternate pre-priced line item removing the cost for the material, and leaving the remaining amount in labor and equipment with a factor of 2; one for the removal and one for the reinstallation.

1.8.2.1.6 Equipment Items. Equipment costs include normal operating expendables and servicing including routine parts. Equipment operating expendables with highly variable wear patterns such as diamond bits and blades are not included. Mobilization and demobilization line items may be used when the only means of moving the equipment to and from a job site is by way of towing behind another piece of equipment.

Contractor may only use the mobilization and demobilization line items when moving a piece of equipment to and from a job site, movement while already on a job site will be the Contractor’s cost and not allowable in the line item proposal. Mobilization and demobilization costs will not be permitted for materials or pieces of equipment capable of being moved in the back of a standard pick-up truck. Operator costs, to include added labor to account for using equipment, shall not be added to equipment line items unless needed for heavy equipment requiring specialized certifications. Forklifts and scissor lifts will not be allowed operator costs since the individuals utilizing this equipment will be using this for their respective discipline and required action. Each piece of equipment is allowed one (1) rental line item (rent per day/week/month) and one hourly operating cost line item. Crew daily costs are not to be used.

1.8.2.2 Project Narrative. The contractor shall submit a project narrative speaking to the elements of work contained within the Government-provided SOW. This narrative shall be in sufficient detail to permit validation of the proposed pricing and demonstrate that the contractor understands of the Government’s requirement and intent. This project narrative shall support, clarify, or otherwise substantiate the contractor’s proposal. The contractor shall not simply copy and paste the Government’s SOW to satisfy this requirement. The Project Narrative is intended to provide the Government with a narrative on how the work will be accomplished. This narrative will be used to justify the Contractor’s line item proposal but will not become part of the final task order award.

1.8.2.3 Project Schedule. A project completion schedule showing all milestones, e.g., ordering materials, demolition, work phasing, and completion date. Contractor shall provide a project schedule which complies with the SOW dictated period of performance. If the Contractor believes the period of performance dictated in the SOW is not feasible, supporting documentation (i.e. product lead times, e4Clicks Labor hours, extenuating circumstances, etc) shall be provided by the Contractor to substantiate the newly proposed period of performance. The KO shall be the determining authority as to the final period of performance.

This project schedule is to be used to substantiate the Contractor’s proposal; durations and actions within this schedule will be compared to the Contractor’s line item proposal.

1.8.2.4 Proposal Support Documents. The contractor should expect to produce any supporting technical calculations or any other data required by the KO in order to allow the Government to verify the accuracy and validity of the contractor proposal. Examples of documentation that might reasonably be expected include but are not limited to sketches, drawings, calculations, specifications, and catalog cuts. The extent of these support documents will depend on the complexity of each TO. The KO shall be the determining authority as to what data is needed from the contractor on individual TOs. The data required may vary with each TO.

1.8.2.4.1 Submittals at time of Proposal: At the KO’s discretion, the RFP may require specific submittals to be included in the Contractor’s proposal which will then become part of the contract documents. These submittals may include material/product submittals, work plans, or any other submittal deemed necessary for validating the Contractor’s proposal or expediting the submittal process of the Task Order

1.8.2.4.2 Technical Advisors for use with Proposal Support Documents. Contractor shall have access to technical advisors for each discipline capable of physically visiting the job site within a reasonable amount of time as determined by the KO. These technical advisors are for use to assist in the creation of the proposal support documents. These technical advisors are required to be in attendance at any negotiation and shall be approved to speak on behalf of the Contractor and their proposal.

01 11 00 - 8

1.8.3 The KO (or authorized representative) will review the contractor’s proposal documents and proposed line items. The KO and/or the authorized representative (DPW Project Manager) shall accomplish a technical evaluation of the contractor’s proposal documents and provide comments for the contractor’s response. The Contractor is then required to respond to the Government’s comments/questions in as much detail as possible. A simple “disagree” response will not be accepted; when asked to justify quantities, the Contractor must provide calculations as to how they arrived at these quantities. Upon receipt of the contractor’s rebuttal to comments and/or revised proposal, the KO and/or authorized representative shall review the comments and determine if any further action is necessary. If further action is necessary, the KO or their representative shall arrange a meeting with the contractor, at which time contractor’s proposal will be discussed and negotiated. The Government reserves the right to proceed directly to discussions and negotiations without utilizing the review and comments stage. Negotiations are not optional and must be attended by an individual from the Contractor’s firm that can sign and accept final pricing on behalf of the firm. A final price will be determined at the conclusion of the negotiations.

1.8.3.1 Answers/discussions/explanations provided during the technical review and/or negotiations stage may be used to review agreed upon requirements and to resolve task order disputes. The burden of proof lies on the Contractor to justify their quantities. If the Contractor cannot justify their quantities/use of a line item via facts, calculations, or some other quantifiable reasoning, the Government’s quantity or line item will be used.

1.8.3.2 In the event the contractor’s proposal does not contain all the requirements or is submitted to an unsatisfactory level, as determined by the TO SOW and the KO, the contractor will be required to revise and resubmit the proposal. The contractor shall typically have 1 business day to resubmit an acceptable proposal or a timeframe as specified by the KO. If the Contractor submits a late and/or incomplete proposal, a Contract Deficiency Report (CDR) shall be sent to the Contractor and shall be recorded in the contract file. The Contractor may request an extension to their proposal due date but this request must be received 3 business days prior to the original proposal due date.

1.8.3.3 The Government reserves the right to adjust, amend, or otherwise alter the original SOW due to information acquired via the project site visit, contractor’s proposal, and/or TO negotiations. The contractor will have a chance to concur with these changes before acceptance of the SOW and therefore acceptance of contractor’s proposal by the Government. The Contractor may not object to items explicitly stated in their proposed schedule, proposal support documents, or line item proposal as these documents were used justify and accept their proposal.

1.8.4 The contractor will be responsible for accomplishing all items of work in accordance with the JOC specifications and contract requirements as outlined by the SOW, contractor’s proposal, and supplemental specifications and sketches/construction drawings that were issued with the TO. Line items agreed upon during negotiations of a Task Order shall be considered to be included in the scope of work for that TO, but the quantities agreed upon will be used only for pricing of the TO and will not be binding on either party.

The intent is to create an understanding of the quality of goods the Government will be receiving (Ex: if the SOW calls out a new door to be installed, the type of door chosen in the line item proposal shall be understood to be the quality of door required during installation).

1.8.5 Issuance of Orders. Upon award of a TO (DD Form 1155), the signed copy will be electronically sent to contractor. Failure to receive the electronic orders shall not relieve contractor of completion in accordance with the TO. The KO may provide verbal NTP for the work in advance of issuing the TO, the NTP may be the date the TO was issued, or the NTP may be delayed and issued under separate cover. Each TO will identify the appropriate NTP date. The TO completion schedule shall be based on the issuance of NTP, verbal or written.

1.8.6 Priorities and Completion. Work shall be completed by the date indicated in the SOW. The KO may revise the completion dates of ongoing work or revise a sequence of priorities for completion of a series of TOs.

01 11 00 - 9

1.8.6.1 Contractor Inspection. Near the completion of all work or stated elsewhere in the specifications, the QC Manager shall conduct an internal inspection of all the work performed to ensure it meets all the requirements of the base contract as well as the specific requirements within each TO. Once this is accomplished, contractor shall notify the Government that the facility is ready for the Government pre-final inspection. The contractor shall give 5 working days notice to the Government Quality Assurance Representative when requesting a pre-final inspection. Further information can be found in Spec Section 01 45 01: Quality Control.

1.8.6.2 Pre-Final Inspection and Punch List Items. Upon request for a pre-final inspection, the Government will schedule a pre-final inspection to verify that the facility is complete and ready to be occupied. This inspection shall consist of the Contractor QC and DPW QAR (PM is optional). A Government pre-final punch list may be developed as a result of this inspection which shall detail the items needing correction.

The contractor’s QC Manager shall ensure that all any items noted on the pre-final inspection have been corrected within 7 calendar days. Once these items have been addressed, contractor shall notify the Government to request a final inspection, giving 5 working days notice. Further information can be found in Spec Section 01 45 01: Quality Control.

1.8.6.3 Final Inspection and Acceptance. Upon request for a final inspection by the Contractor, the Government will schedule a final inspection to verify that the facility is complete and ready to be occupied. For this inspection to commence a representative from contractor, DPW, and Contracting shall be present. If all items listed in the pre-final punch list have been corrected, and all work meets the requirements of the umbrella contract and TO specifications, the Government shall accept the work and take ownership of the site. Further information can be found in Spec Section 01 45 01: Quality Control.

1.8.6.4 Beneficial Occupancy Determination. On a per TO basis, the Government may request a Beneficial

Occupancy Determination (BOD). This request is used to allow Government acceptance of a portion of the project in order for the Government to operate, occupy, or use the facility, area, or equipment. This determination does not alleviate the contractor’s responsibility to accomplish all other requirements of the TO. Further information can be found in Spec Section 01 45 01: Quality Control.

01 11 00 - 10

SECTION 01 14 00 WORK RESTRICTIONS

1. PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of contact personnel; G

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Installation Regulations. The contractor shall ensure its personnel employed on the installation become familiar with and obey installation regulations including safety, fire, traffic and security regulations. The contractor shall keep within the limits of the work and avenues of ingress and egress.

Contractor personnel shall wear personal protective equipment in designated areas. Contractor personnel shall not enter any restricted areas unless required to do so and until cleared for such entry.

The contractor's equipment shall be conspicuously marked for identification.

1.2.2 Personnel Entry Approval. Failure to obtain entry approval will not affect the contract price or time of completion.

1.2.3 Vehicle Emission. Proof of current emission compliance must be shown when required by the Provost Marshal Vehicle Registration Office.

1.2.3.1 The JBLM compliance program requires any motor vehicle that operates on the installation for more than 60 days per year to show proof of Washington State emission compliance, in accordance with the Washington Administrative Code (WAC) 173-422-030.

1.2.3.2 Companies with out-of-state registration and plates and with current emissions compliance certificate from that state will still be required to show proof of Washington State emission compliance if requested. Washington State does not recognize current emissions tests from any other state.

1.2.4 Working Hours. Regular working hours shall consist of an 8-hour period, between 7:30 a.m. and 4:00 p.m., Monday through Friday, excluding Government holidays.

1.2.4.1 Government holidays. The following Government holidays are observed:

New Year's Day 1 January Martin Luther King Jr's Birthday ----------------- Third Monday in January President's Day-------------------------------------- Third Monday in February Memorial Day ---------------------------------------Last Monday in May Juneteenth ------------------------------------------- June 19th Independence Day 4 July Labor Day -------------------------------------------- First Monday in September Columbus Day --------------------------------------- Second Monday in October Veterans Day 11 November Thanksgiving Day ---------------------------------- Fourth Thursday in November Christmas Day 25 December

*The term “Government holidays" includes days on which Government holidays are observed in lieu of the actual holidays. When one of the above designated legal holidays falls on a Sunday, the

01 11 00 - 11 following Monday will be observed as a legal holiday. When a legal holiday falls on a Friday or Saturday, the preceding Thursday is observed as a legal holiday. This list of holidays relates to Government duty days and is not intended to supplement or otherwise alter the provisions of any Wage Determination regarding applicable paid holidays.

In addition to the days designated as holidays, the Government observes the following days:

-Any other day designated by federal statute -Any other day designated by Executive Order -Any other day designated by Presidential Proclamation

The contractor is NOT entitled to observe installation training holidays or other time off given to Government employees by Executive Order or other lawful order of the President of the United States.

It is understood and agreed between the Government and the contractor that observance of such days by Government personnel shall not be a reason for an additional period of performance, or entitlement of compensation except as set forth within the contract.

NOTE: Individual task orders will be more specific if work is allowable on federal holidays.

1.2.4.2 Work Outside Regular Hours. Work outside regular working hours requires KO approval. Make application 7 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Application shall be sent to the task order Project Manager via email and shall be routed to Contracting from there. Based on the justification provided, the KO may approve work outside regular hours. KO may approve work outside normal hours but only for work which does not require inspection of work. If this caveat is provided, Contractor shall not conduct any work that must be inspected. During periods of darkness, the different parts of the work shall be lit in a manner approved by the KO.

1.2.5 Occupied and Existing Buildings. The contractor will be working around existing buildings that are occupied.

1.2.6 Special Scheduling Requirements. Permission to interrupt any activity roads, railroads, and/or utility service shall be requested in writing a minimum of 14 calendar days prior to the desired date of interruption.

1.2.7 Cellular Telephone Use. Driving or being in physical control of a motor vehicle on a Government installation while operating a cellular phone or like device is prohibited unless the vehicle is safely parked or unless the driver of the vehicle is using a hands-free device. The wearing of any other portable headphones, earphones, or other listening devices (except for hands-free cellular phones) while operating a motor vehicle is prohibited. Civilians, contractors, and visitors to the installation who fail to comply with this policy are subject to administrative action to include loss of driving privileges on government installation and removal and/or denial of re-entry to the installation.

1.2.8 Security Levels.

1.2.8.1 Force Protection Conditions (FPCON): Security Forces may incorporate various FPCON levels which impact the ability of the contractor to perform work. FPCON levels may vary from the least restrictive to most restrictive depending upon current installation-wide potential security threat. Access onto the installation may be limited during increased FPCON levels, which may impact contract operations.

All prudent measures will be implemented by the KO to ensure continuity of contractor operations during the establishment of increased FPCON levels.

1.2.8.2 Health Protection Conditions (HPCON): JBLM leadership may incorporate various HPCON levels which impact the ability of the contractor to perform work. HPCON levels may vary from the least restrictive to most restrictive depending upon current installation-wide potential health concerns.

01 11 00 - 12

Activities on the installation may be restrictive or require additional protocols during increased FPCON levels, which may impact contract operations. All prudent measures will be implemented by the KO to ensure continuity of contractor operations during the establishment of increased HPCON levels.

1.2.9 Insurance Requirements: In accordance with FAR 52.228-5, Insurance – Work on a Government

Installation, the following types of insurance and “minimum” amounts are required for this contract:

TYPE AMOUNT

Workers' Compensation $100,000 Comprehensive General Liability:

Bodily Injury per accident or occurrence $500,000 Comprehensive Automobile Liability:

Per Person $200,000 Bodily Injury per occurrence $500,000 Property Damage per occurrence $ 20,000

1.2.10 Performance And Payment Bonds And Alternative Payment Protections For Construction Contracts

And Modifications:

1.2.10.1 Performance and payment bonds shall be required, and the penal sum established, by the contract award ceiling. Reference Contract Clause 52.228-15, Performance and Payment Bonds.

1.2.10.2 Payment Bond: The penal amount of each Payment Bond shall be one hundred percent (100%) of the original contract ceiling. Any subsequent increase in the contract ceiling shall result in an increase in protection which shall equal one hundred percent (100%) of the increase in contract ceiling.

1.2.10.3 Performance Bond: The penal amount of each Performance Bond shall be one hundred percent (100%) of the original contract ceiling. Any subsequent increase in the contract ceiling shall result in an increase in protection which shall equal one hundred percent (100%) of the increase in contract ceiling.

1.2.10.4 Bonds and other payment protections shall be provided within 10 calendar days of contract award.

1.2.10.5 Notice to Proceed will not be issued until the contractor provides sufficient bonding to cover the contract ceiling.

1.2.11 Toilet Facilities: The contractor shall, at its own expense, provide and maintain portable chemical latrines at the job site for use by its employees and subcontractor employees. Portable chemical latrines must comply with the state environmental quality standards, as required. At no time shall portable chemical latrines be placed in or near a roadway, driveway or building egress that would obstruct motorized or foot traffic.

1.2.12 Waste and Excess Quantities included in the Completed In-Place Construction Quantities:

1.2.12.1 All prices in the UPB are for the complete in-place construction unless explicitly described otherwise.

The unit prices include delivery of materials to the job site. Waste or excess material quantities are incidental costs, which are included in the contract coefficient unless explicitly stated otherwise in the UPB. Quantities used on individual job order proposals shall be taken from field measurements or design plans, as appropriate, without allowance for waste and/or incidental extra materials used in performance of work. UPB prices include all waste and incidentals.

1.2.12.2 Incidental nails, screws, weldments, and connectors are included in UPB line items. Unless a connector or fastener is specifically stated as not being included, it is included in the price. For example: Installation of a suspended ceiling grid system includes connectors, fasteners, and wire for the hanging system.

01 11 00 - 13

1.2.13 Documentation To Support Subcontract Awards:

1.2.13.1 Within 10 business days after the award of any subcontract, the contractor shall deliver a completed SF Form 1413 (Statement and Acknowledgment) to the Contracting Officer. Each subcontract shall contain, as a minimum, the Contract Number, Task Order Number (if applicable), and Title. The subcontract must clearly identify what the subcontractor will be performing in relation to other trades on the job. All subcontracts shall contain the anticipated period of performance that correlates with the approved Progress Schedule for that Division of work. A sample format shall be submitted for Contracting Officer approval prior to commencement of work under this contract.

1.2.13.2 FAR Clause 52.222-11, entitled "Subcontracts (Labor Standards)", requires that the clauses listed therein be physically inserted in all subcontracts. However, if the contractor subcontracts by means of purchase orders or other informal types of contractual situations, compliance will be considered provided if clauses are attached to the subcontract form. Written acknowledgement by the subcontractor of these Labor Standards is required. Incorporation by reference does not constitute compliance.

1.2.14 Public Release Of Information:

1.2.14.1 Contractor and subcontractor personnel shall not publicly (or privately) discuss or release information, photographs, or other documents concerning any aspects of the materials or services relating to this contract or its task orders without the express written approval of the Contracting Officer.

1.2.15 Relationship Between Government, Contractor, And Contractor Personnel:

1.2.15.1 The Government and the contractor understand and agree that the services to be delivered under this contract are non-personal services and that no employer-employee or master-servant relationship exists or will exist under the contract between the Government and the contractor or between the Government and the contractor's personnel. Further, the contractor is not the Government's agent.

1.2.15.2 The Government will not exercise any supervision or control over contractor personnel performing services under this contract. Contractor personnel shall not become an integrated part of the Government organization in connection with performance under this contract.

1.2.15.3 The work required under this contract does not require or authorize the contractor or his employees to exercise personal judgment and discretion on behalf of the Government, but rather, the contractor's employees shall act and exercise personal judgment and discretion on behalf of the contractor.

1.2.15.4 Contractor personnel shall not be eligible, by virtue of performance under this contract, for payment by the Government of entitlements and benefits accorded federal employees. The entire consideration to the contractor for performance of this contract is contained in the provisions for payment set forth in this contract.

1.2.16 Key Control:

1.2.16.1 Keys will be provided to the contractor for access to facilities, rooms and other areas necessary to perform work under this contract. Access to restricted areas shall be requested and provided through the COR. At no time are keys provided to the contractor in performance of work under this contract to be removed from DPG. Contractor employees shall retain keys in their possession only while physically performing work required by the task order. All keys not issued to a shift shall be secured in a locked key box provided by the contractor. Only the contractor's Project Manager and supervisors are permitted to have possession of master keys.