Event_32525_Bid_Results.pdf

PDF 604 KB Posted

Attached to
Replace Storefront Doors - Fresno Armory
Solicitation number
0000032525
Issued by
Fresno County, Fremont City, Fresno City, California

About this file

This document contains the bid results for Event 32525 to Replace Storefront Doors at the Fresno Armory in California. The lowest, responsive and responsible bidder for this public works project was American Window and Door Systems, Inc. The scope of work includes furnishing all labor, equipment, materials, permits and fees necessary to replace the storefront doors at the Fresno Armory. A mandatory pre-bid job walk was held on August 29, 2024, and all bids were due on September 19, 2024. The bid opening was held on the same date. This project is not subject to protests as it is a public works contract awarded under the State Contract Act.

The document also outlines the details of the related state and local contract opportunity, including the solicitation type, location, scope of work, required contractor licensing, and key dates such as the mandatory pre-bid job walk, question and answer deadline, and bid opening. The contract will be awarded to the lowest responsive and responsible bidder, and the prime contractor must possess a C-17 Glazing Contractor license or subcontract to one.

View the file

Other files

File Type Posted
E_32525_IFB_Packet.pdf PDF
Event_32525_Job_Walk_Attendees.pdf PDF
NOTICE_TO_AWARD.pdf PDF
Event_32525_Addendum_01.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

23 September 2024 BID Results for Event 32525 | Replace Storefront Doors – Fresno Armory, CA

The lowest, responsive responsible bidder for this project:

Paragraph 6.03 of the State Contracting Manual (Volume 1) is provided for bidder’s information. This is a public works project and not subject to protests.

6.03 PROTEST EXCLUSIONS (Rev 11/12)

Under the following circumstances, there is no jurisdiction for the DGS to consider a protest if:

A. The protestant was not a bidder or proposer.

B. The protestant has not alleged that it was the lowest responsible bidder or the highest-scored proposer.

C. The protestant is not in a position to make a supportable assertion that it was the lowest responsible bidder or should have been the highest-scored proposer.

D. The protest was not submitted timely.

E. The grounds for the protest do not meet the permissible grounds stated in the PCC; or F. The contract award is for a type of contract not subject to the protest procedures. This category includes public works contracts awarded under the State Contract Act (PCC 10100 et seq); contracts for professional architecture or engineering services under GC 4525; contracts awarded under GC 14838.5 and 14838.7.

American Window and Door Systems, Inc.

File details come from the government source that posted it. Updated .