Etnies Skatepark Improvement Project.pdf
PDF 622 KB Posted
- Attached to
- Etnies Skatepark Improvement Project
- Solicitation number
- 25P03
- Issued by
- Orange County, California
About this file
This Request for Proposal (RFP) #25P03 from the City of Lake Forest, California, seeks qualified consultant teams to provide professional design services for the Etnies Skatepark Improvement Project. The Prime Consultant may be either a civil engineering firm or skatepark design firm and must provide demonstrated experience in public skatepark design, municipal civil engineering, and public art. The project includes renovation of existing skatepark areas, construction of a new concrete pump track (approximately 8,000 square feet) on the eastern portion of the site, public art design and integration, and associated site improvements. The facility, which currently encompasses over 62,000 square feet and attracts over 60,000 annual visitors, will be modified to accommodate all-wheel nonmotorized use while retaining opportunities for advanced users. The RFP was released November 4, 2026, with a deadline for questions by November 18, 2026, at 3:00 p.m., and a proposal response deadline of December 4, 2026, at 3:00 p.m. Responses must be submitted electronically through the City's eProcurement Portal. The City anticipates contract award by City Council on February 2, 2027, with a project start date of February 9, 2027. The agreement will have an initial term from January 20, 2027, to January 19, 2030, with options at the City's sole discretion to extend for up to two additional one-year terms.
The cost proposal is structured as a time-and-materials, not-to-exceed basis across twelve tasks, with detailed scope components including project management, existing conditions survey, geotechnical investigation, environmental review, drainage and permitting, final concept design, 60/90/final percent plans and specifications, bidding support, construction support, and record drawings. The consultant's hourly rates and subconsultant costs must be separately identified with markup. Proposers must meet mandatory qualification requirements including California professional licenses, absence of conflicts of interest, compliance with RFP requirements, and minimum experience criteria: the Prime Consultant and Project Manager must have minimum three public skatepark design projects with at least two constructed in the last five years; the Lead Skatepark Designer must personally have led design on three public concrete skatepark projects with at least two completed within five years; the Civil Engineering Lead must be a California licensed civil engineer with three municipal site improvement projects completed in the last five years; and the Public Art Lead must have three completed exterior public art projects in parks or public spaces. Evaluation is conducted in phases using weighted criteria: mandatory elements (pass/fail), qualitative technical proposal evaluation (maximum 100 points, minimum 60 points required to advance), and for shortlisted firms, oral presentation/interview evaluation (maximum 160 points, 80 percent weight) and cost proposal evaluation (maximum 40 points, 20 percent weight). The City reserves the right to reject all proposals, negotiate with multiple respondents, or cancel the RFP; no set-asides are specified in the procurement documents.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL (RFP)
25P03
ETNIES SKATEPARK IMPROVEMENT PROJECT (25P03)
City of Lake Forest
100 Civic Center Dr.
Lake Forest, CA 92630
RELEASE DATE: November 4, 2026
DEADLINE FOR QUESTIONS: November 18, 2026
RESPONSE DEADLINE: December 4, 2026, 3:00 pm
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://secure.procurenow.com/portal/lakeforestca https://secure.procurenow.com/portal/lakeforestca
City of Lake Forest
REQUEST FOR PROPOSAL (RFP)
Etnies Skatepark Improvement Project (25P03)
I. Introduction II. General Information
III. RFP - Proposal Requirements IV. Scope of Work V. Evaluation Details
VI. Evaluation Phases VII. General Provisions
VIII. Pricing Proposal IX. Vendor Questionnaire
Attachments:
A - LAKE FOREST_ MODEL Professional Consultant Services Documents 2022
B - Preliminary Concept Designs
C - Etnies Skate Park Lake Forest As-Builts_August 2003
D - Etnies Skate Park Expansion As-Builts_July 2012
Request for Proposal (RFP) #25P03 Title: Etnies Skatepark Improvement Project (25P03)
1. Introduction
1.1. Summary
Etnies Skatepark Improvement Project (25P03)
Professional Design Services for the Etnies Skatepark Improvement Project (25P03)
The City is seeking proposals from qualified consultant teams to provide Professional Design Services for the Etnies Skatepark Improvements (25P03). The Prime Consultant may be either a civil engineering firm or a skatepark design firm and shall provide a team with demonstrated experience in public skatepark design, municipal civil engineering, and public art.
The Consultant shall build upon the preliminary concept designs and develop a single final concept that addresses the needs of the community and City. No additional public outreach is anticipated. The
Project generally includes renovation of selected existing skatepark areas and features, construction of a new concrete pump track on the eastern portion of the site, public art design and integration, and associated site improvements identified in the preliminary concepts.
The completed Project is intended to accommodate all wheel nonmotorized use, provide additional opportunities for beginner and intermediate users, retain opportunities for advanced users, and maintain the facility as one of the largest public skateparks in California.
Renovations to the existing skatepark building that supports facility operations are being designed under a separate contract and will require coordination with this Project.
1.2. Background
About the City
The City of Lake Forest is located in southern Orange County, California, in the area commonly referred to as the Saddleback Valley, with a population of approximately 85,000. It is the County's thirty-first city and the second largest city within the Saddleback Valley, encompassing 16.6 square miles. The City of Lake Forest's fiscal year begins on July 1 and ends on June 30.
The City was incorporated in 1991, operates under the Council/Manager form of government and is considered a contract city. The five members of the City Council are elected by district. They serve staggered four-year terms, with the Mayor being selected annually from among the Council Members. The Council meets on the first and third Tuesdays of each month.
City Hall is located at 100 Civic Center Drive, Lake Forest, California 92630. The telephone number is (949)
461-3400, and the fax is (949) 461-3511. The City website address is http://www.lakeforestca.gov.
Project Background
The Etnies Skatepark of Lake Forest is owned and operated by the City and located at 20028 Lake Forest
Drive. The skatepark opened in 2003 through a partnership between the City and Etnies. An expansion completed in 2011 added several signature features, including the cradle, flow course, mini bowl, street run, and backyard style pool. The existing facility encompasses over 62,000 square feet and attracts over
60,000 visitors annually.
http://www.lakeforestca.gov/
The facility was originally designed primarily for intermediate, advanced, and professional users.
Participation has increasingly shifted toward beginner and intermediate users, and the facility does not currently operate as an all wheel park.
In 2025, the City conducted three community meetings and an online survey to gather input on future improvements. Based on this input, the City prepared two preliminary concept designs that include additional beginner and intermediate features, retention of advanced riding opportunities, a new pump track, conversion to all wheel nonmotorized use, and associated site improvements. The preliminary concept designs were presented to the Community Services Commission and City Council in May 2026.
The preliminary concept designs includes:
• All Wheel Pump Track (new addition — approximately 8,000 sq ft)
• Street Lane Improvements
• Street Plaza Improvements
• Mini Bowl Improvements
• Clover Bowl Improvements
• Cradle removal and replacement
• Flow Bowl Improvements
• Site Amenities Improvements and Public Art Design and Integration
The selected Consultant shall refine the two preliminary concepts into a final concept and prepare a complete, bid ready PS&E package. Concurrently, renovations to the existing skatepark building that supports facility operations are being designed under a separate contract. The Consultant shall coordinate with the separate skatepark building improvement project and develop construction phasing that maintains operation of portions of the facility to the greatest extent practical. No additional public outreach is anticipated.
Consistent with the terms of the prior contract, the consultant that prepared the preliminary concept designs is not eligible to participate in the subsequent design or construction phases of the Project.
1.3. Contact Information
Ravi Shah
Principal Engineer
100 Civic Center Drive
Lake Forest, CA 92630
Email: rshah@lakeforestca.gov
Phone: (949) 461-3481
Department:
Public Works mailto:rshah@lakeforestca.gov tel:(949)461-3481
1.4. Timeline
The following timeline shows the anticipated schedule for the RFP. The City expects, but does not guarantee, that the contract award will be made by the City Council on the date indicated below. All schedules and timelines are subject to related and required approvals.
Release Project Date November 4, 2026
Pre-proposal Requests for Clarification November 18, 2026, 3:00pm
Proposal Submission Deadline December 4, 2026, 3:00pm
Anticipated Final Selection/City Council
Target Date
February 2, 2027
Anticipated Project Start February 9, 2027
2. General Information
2.1. GENERAL REQUIREMENTS
The City of Lake Forest ("City") seeks proposals ("Proposals") from qualified firms ("Respondents") for
Etnies Skatepark Improvement Project (25P03).
Responses must conform with the requirements of this Request for Proposal ("RFP"). The City reserves the right to waive any irregularity in any proposal or to reject any proposal which does not comply with this RFP. Modifications to the RFP, including, but not limited to the scope of work, can be made only by written addendum issued by the City. Selection of the proposer will be made solely by the City on criteria determined by the City.
The successful Respondent will be required to enter into an Agreement (incorporated herein as
Attachment A) which will include the requirements of this RFP as well as other requirements. By submitting a Proposal, the Respondent agrees to all of the terms of the RFP and Agreement. The City reserves the right to reject any proposal(s) exceptions or changes to the Agreement or Request for
Proposal.
The services are expected to be completed within three years from contract award. The City anticipates awarding a contract with an initial term of January 20, 2027 to January 19, 2030. The City will have the option, at its sole discretion, to extend the agreement for up to two (2) additional one year terms. If the parties are unable to reach an agreement, the City, at its sole discretion, will not move forward with the renewal option and shall re-procure the work.
2.2. PROJECT DESCRIPTION
Project Description
The City is seeking Professional Design Services for the Etnies Skatepark Improvements (25P03) Project.
2.3. PRE-PROPOSAL MEETING
No Pre-Proposal Meeting
There will be no pre-proposal meeting for this RFP.
2.4. REQUESTS FOR CLARIFICATIONS
All questions, requests for interpretations or clarifications, either administrative or technical must be requested via the City's eProcurement Q&A feature.
All written questions will be answered in writing and conveyed to all interested firms. Oral statements regarding this RFP by any persons should be considered unverified information unless confirmed in writing. To ensure a response, questions must be received before 3:00 pm on Wednesday, November
18, 2026.
2.5. SCOPE OF REQUIRED SERVICES
Scope of Work
A detailed Scope of Work is provided under the Scope of Work section. The Respondent will be expected to fulfill, at a minimum, the services and technical requirements described in the Scope of Work. Upon final selection, the Scope of Work may be modified and refined during negotiations with the City.
https://procurement.opengov.com/portal/lakeforestca/projects/274534/document?section=2647718 https://procurement.opengov.com/portal/lakeforestca/projects/274534/document?section=2647718
3. RFP - Proposal Requirements
3.1. PROPOSAL CONTENT
Respondent's Proposal shall be clear, accurate, and comprehensive. Excessive or irrelevant materials will not be favorably received. The content and sequence of the information contained in each copy of the proposal shall be as follows:
1. Summary Sheet o Include a fully-completed copy of the Summary Sheet included with this RFP (To be completed as part of the Vendor Questionnaire).
2. Table of Contents o Include a clear identification of the material by section and by page number.
3. Letter of Transmittal o Identify Respondent's legal name and contact information, including corporate office and local office address, telephone number, fax number, web site address, and e-mail address.
o Summarize key elements of the proposal. The letter must stipulate that the cost proposal will remain valid for a period of at least 180 days. The letter shall be signed by an individual or individuals authorized to execute legal documents on behalf of the Respondent.
4. Key Personnel o Identify the names, qualifications, availability, experience, and applicable professional licenses of the key personnel assigned to the Project. At a minimum, identify the Project
Manager, QA/QC Lead, Civil Engineering Lead, Lead Skatepark Designer, Public Art Lead, and key subconsultant personnel. For each discipline requiring professional licensure, identify the California licensed professional responsible for the work and for signing and sealing the applicable construction documents. Include a resume for each key person.
o Provide an organization chart showing each firm’s role and the responsibilities of key personnel. Describe the Lead Skatepark Designer’s involvement throughout final concept design, PS&E, bidding, and construction support.
o Respondent shall also identify a Management Contact (Representative authorized to sign an agreement for your firm) and a Project Manager (person responsible for day-to-day management of the project).
o The successful Respondent may only change the Management Contact, Project Manager, and other supporting key personnel with prior written permission from the City.
5. Project Management/Schedule o Provide a project management work plan, including a detailed task breakdown and a separate Critical Path Method (CPM) schedule for services that you believe are appropriate per the Scope of Work.
o Describe how the Prime Consultant will coordinate the Project Manager, Civil Engineering
Lead, Lead Skatepark Designer, Public Art Lead, other disciplines, and subconsultants.
o Identify features, skills and/or services which distinguish your firm and make it the better choice for the City.
o Provide an allocation of resources identifying the proposed staff and hours assigned to each task. An example of an Allocation of Resources is provided below. A proposer may customize the resource allocation accordingly.
6. Scope of Work o Provide a detailed scope of services addressing each task in the Scope of Work described in this RFP. Proposals must address all items set forth in Scope of Work section.
o Clearly identify assumptions and exclusions under the applicable task.
o Additional scope of work, which, in your opinion, should be included must be clearly identified. Optional scope of work, if presented, should be clearly identified and included at the end of the scope of work and cost proposal.
7. Experience and Qualifications
1. List of Representative Projects - For each project, provide the project name, location, owner, brief description, construction cost, completion date and status, firm and key personnel roles, and owner contact. Include photographs for each representative project.
2. Qualifications of Prime Consultant and Key Personnel
▪ Prime Consultant and Project Manager: Provide a minimum of three (3) public skatepark design projects. At least two (2) must have been constructed within the last five (5) years. For those two (2) projects, the Prime Consultant must have served as the prime consultant or lead skatepark design firm, or the Prime Consultant's proposed Project
Manager must have served as the project manager. The Prime Consultant may not rely solely on a subconsultant to meet this requirement.
▪ Lead Skatepark Designer: Provide a minimum of three (3) public concrete skatepark projects for which the proposed lead skatepark designer personally led the design. At least two (2) must have been constructed within the last five (5) years.
▪ Civil Engineering Lead: The proposed Civil Engineering Lead shall be a California licensed
Civil Engineer. Provide a minimum of three (3) municipal site improvement projects completed within the last five (5) years that collectively include grading, drainage, accessibility, and utility design. At least two (2) of the projects shall involve a public park or recreation facility. Skatepark experience is preferred.
▪ Public Art Lead: Provide a minimum of three (3) completed exterior public art projects designed or led by the proposed Public Art Lead in parks or other public spaces.
▪ If applicable, the same skatepark projects may be used to demonstrate the experience of the Prime Consultant, Project Manager, and Lead Skatepark Designer.
3. Current City Contracts - Identify all previous and current contracts with the City of Lake
Forest. Include a contact name, description of services, and dates of services performed.
4. Terminated Contracts - List all public agencies, excluding the City of Lake Forest, for which contracts were terminated in the last three (3) years. Include the organization, contact name, telephone number and brief explanation of the reason for termination.
8. Certificate of Proposal o Include a completed copy of the Certificate of Proposal included with this RFP (to be completed as part of the Vendor Questionnaire).
9. Cost Proposal o Include a detailed cost proposal for each task on a time and materials, not to exceed basis.
Identify the proposed staff, hours, hourly rates, and extended costs for each task. Include proposed hourly rate schedules for the Respondent and each subconsultant. Separately identify subconsultant costs, anticipated travel, other direct expenses, and markups. Provide a not to exceed fee for each task and the total Project. Proposed hours shall match the
Allocation of Resources included in the technical proposal. The cost proposal shall be submitted separately from the technical proposal using the Cost Proposal submission feature on the City’s eProcurement site. The Respondent shall also complete the City’s electronic Pricing Table and, upon request, provide an electronic copy in a format acceptable to the City.
Proposal Format
Proposals shall be organized, tabbed, and numbered in the order presented above. Proposals must include page numbers for all pages in the proposal. The Technical Proposal shall not exceed 40 pages and shall use a minimum 12 point font. Front and back covers, the table of contents, required City forms, and the separate Cost Proposal do not count toward the page limit. Tables, schedules, organizational charts, captions, and similar materials may use a minimum 11 point font. An 8.5x11 inch page counts as one page, and an 11x17 inch sheet counts as two pages. Any proposal exceeding the page limit may not be reviewed.
3.2. SUBMITTAL INSTRUCTIONS
Proposals must be received via the City's eProcurement Portal at https://procurement.opengov.com/portal/lakeforestca no later than 3:00 pm on Friday, December 4, 2026.
https://procurement.opengov.com/portal/lakeforestca
4. Scope of Work
4.1. Etnies Skatepark Improvements
The Consultant shall assemble a qualified team and provide the services necessary to prepare a complete, coordinated, permit ready, bid ready, and constructible design. The Consultant shall review the preliminary concept designs, available record drawings, and site conditions; conduct field reconnaissance; and include any additional services reasonably necessary to complete the
Project.
The Consultant shall build upon the City provided preliminary concept designs, develop one final concept for City approval, and prepare a single coordinated construction package unless otherwise authorized by the City. No additional public outreach is anticipated.
The Lead Skatepark Designer shall remain actively involved through final concept design, PS&E, bidding, and construction support. The Public Art Lead shall develop the public art design and coordinate its incorporation into the construction documents.
Anticipated design services include:
• Project management, coordination, scheduling, and quality control.
• Records research, field reconnaissance, topographic survey, utility investigation, potholing, and geotechnical investigation.
• Environmental review, drainage and water quality analysis, utility coordination, and permitting assistance.
• Final concept design and City approval before proceeding with plans, specifications, and estimates.
• 60%, 90%, and final bid ready plans, specifications, and estimates.
• Bidding support, Construction Support Services, final renderings, and record drawings.
The desired skateable area and related site improvements shown in the preliminary concepts are anticipated to include:
• A new all wheel pump track.
• Street Lane and Street Plaza improvements.
• Removal and replacement of the existing Cradle with an island feature.
• Mini Bowl, Clover Bowl, and Flow Bowl improvements.
• Drainage improvements.
• Site amenity improvements and public art design and integration.
• Modification or replacement of the existing monument sign to reflect the approved facility name and branding.
• Accessibility improvements.
GENERAL DESIGN REQUIREMENTS
The Consultant shall provide a complete, coordinated interdisciplinary design that complies with applicable federal, state, and local requirements; City standards; adopted building and accessibility codes; and applicable Low Impact Development and water quality requirements.
Improvements shall be durable, low maintenance, and suitable for a heavily used public facility.
The Consultant shall evaluate accessibility throughout the Project limits, including accessible routes and path of travel improvements affected by the work. The design shall also address safe circulation, construction access and staging, protection of improvements to remain, and construction phasing to maintain operation of the facility to the greatest extent practicable.
The existing time capsule shown on the City provided record drawings will be affected by the
Project. The Consultant may rely on the location shown in the record drawings for design purposes and shall coordinate with the City and include the plans, details, specifications, and other requirements necessary for its protection, temporary removal, relocation, and reinstallation. The time capsule shall not be opened unless directed by the City.
Design of the existing building, site lighting, electrical, and public address system improvements is being performed under a separate contract and is not included in this Scope of Work. The
Consultant shall coordinate with the building improvement consultant to avoid conflicts.
Electrical design shall be included only when required for drainage, utility relocations, monument signage or impacts resulting from this Project.
TASK 1 — PROJECT MANAGEMENT AND COORDINATION
The Consultant shall be responsible for the overall management, coordination, schedule, budget, and quality of the work performed by the Consultant and its subconsultants. The
Project Manager shall serve as the City’s primary point of contact and coordinate with City staff, Community Services, the concurrent building improvement consultant, utility owners, affected agencies, and other parties necessary to complete the Project.
Project management shall include:
o One project kickoff meeting and monthly progress meetings with City staff through design.
o Meeting agendas, minutes, and action item tracking.
o A Critical Path Method schedule identifying tasks, durations, dependencies, submittals, City review periods, permits and approvals, and major milestones. The schedule shall be updated monthly and when significant changes occur.
o Monthly progress reports submitted with invoices summarizing work completed, upcoming activities, outstanding decisions, schedule status, and budget status.
o Coordination among all disciplines and subconsultants to identify and resolve conflicts before each formal submittal.
o Documented internal quality assurance and quality control before each formal submittal.
The Consultant shall identify its assumptions for meetings, site visits, coordination, and other project management activities in its proposal and resource allocation table.
TASK 2 – EXISTING CONDITIONS, SURVEY, UTILITY INVESTIGATION, AND POTHOLING
The Consultant shall review available record drawings, concept materials, prior reports, utility records, survey information, and other City provided documents. The Consultant shall conduct site reconnaissance and field verification sufficient to identify existing conditions that may affect design or construction.
The Consultant shall prepare a topographic survey and base map covering the existing skatepark, proposed pump track area, affected accessible routes and paths of travel, anticipated grading and drainage areas, utility connections or relocations, construction access and staging areas, and other limits necessary to complete the design. A boundary survey is not anticipated to be required.
The survey and base map shall include, as applicable:
• Horizontal and vertical control, benchmarks, project limits, and available property, easement, and right of way information relevant to the Project.
• Existing grades, contours, spot elevations, grade breaks, walls, fences, gates, buildings, hardscape, paving, curbs, ramps, stairs, and other site improvements.
• Existing skatepark terrain and features, including but not limited to: edges, transitions, bowls, decks, coping, rails, and other elements necessary to connect the proposed improvements to the existing facility.
• Drainage facilities, surface flow patterns, and detailed survey information at known drainage problem areas.
• Slopes, cross slopes, spot elevations, landings, gates, ramps, and other features along affected accessible routes and paths of travel.
• Utility structures, visible utilities, available utility record information, and surface markings necessary to identify potential conflicts.
• Landscaping, irrigation features, trees, site amenities, and improvements to remain or be protected.
The Consultant shall research utilities within the Project limits, determine ownership, identify potential conflicts, and coordinate their resolution. If the Project requires relocation of a City owned utility, the Consultant shall design the relocation and include it in the PS&E. For utilities owned by others, the Consultant shall coordinate with the utility owner and incorporate its relocation plans, requirements, and schedule into the Project design.
The Consultant shall perform utility potholing as necessary to support the design. The
Consultant shall include the complete cost of up to five potholes, including permits, utility coordination, traffic or pedestrian control, excavation, documentation of horizontal and vertical location, backfill, restoration in kind, and related work. Pothole information shall be incorporated into the base map and final design documents.
Deliverables shall include the survey signed and sealed by a California licensed professional authorized to perform the work, survey and base map files, utility coordination documentation, and a pothole report identifying the location, depth, elevation, type, size, and material of each exposed utility.
TASK 3 – GEOTECHNICAL INVESTIGATION
The Consultant shall perform the geotechnical investigation necessary to support design of the skatepark improvements, pump track, grading, concrete and pavement sections, foundations, retaining features, drainage facilities, and other proposed improvements. The investigation shall include utility clearance, field exploration, laboratory testing, engineering analysis, and design and construction recommendations appropriate to the Project.
The Consultant shall prepare an exploration plan identifying the proposed locations, methods, and depths of investigation for City review before beginning fieldwork. Exploration locations shall be coordinated with the City. Borings, test pits, and other intrusive work shall avoid existing skateable or improved areas that cannot be restored in kind. All disturbed areas shall be restored to preexisting conditions. Infiltration testing shall be included if necessary to evaluate proposed drainage or water quality improvements.
The Consultant shall prepare a geotechnical report or memorandum signed and sealed by a
California licensed Geotechnical Engineer. The document shall present the investigation, findings, test results, and recommendations for the following, as applicable:
• Grading, earthwork, excavation, and subgrade preparation.
• Concrete and pavement sections.
• Foundations, retaining features, bearing capacity, settlement, lateral earth pressures, and any seismic design parameters, if applicable.
• Groundwater, drainage, infiltration, and soil corrosion.
• Construction observation and materials testing.
The proposal shall describe the assumed field exploration and laboratory testing and include the complete cost of permits, investigation, restoration, analysis, report preparation, and related services.
TASK 4 – ENVIRONMENTAL REVIEW AND DOCUMENTATION
The Consultant shall evaluate the Project for compliance with the California Environmental
Quality Act. A categorical exemption is anticipated. The City will serve as Lead Agency and will review and approve the environmental documentation. The Consultant shall prepare the documentation necessary to support the exemption.
The environmental review shall consider the skatepark improvements and the separately designed building improvements as one overall project and shall be coordinated with both design teams.
The Consultant’s services shall include:
• Confirming the appropriate exemption and evaluating any exceptions to its use.
• Preparing the supporting analysis, findings, and draft Notice of Exemption.
• Identifying any avoidance measures, standard conditions, or other environmental requirements that must be incorporated into the construction documents.
• Addressing City comments and preparing the final documentation and filing materials.
If a categorical exemption cannot be supported, the Consultant shall notify the City and recommend the appropriate CEQA pathway before proceeding with further environmental review.
The City will execute and file the applicable notices and pay filing fees. Federal funding is not anticipated, and NEPA documentation is not required.
The proposal shall describe the Consultant’s approach and assumptions for documenting the anticipated categorical exemption. No separate environmental technical studies are anticipated. If the Consultant believes additional technical analysis is necessary, it shall identify the recommended analysis and basis in its proposal.
TASK 5 – DRAINAGE, WATER QUALITY, AND PROJECT PERMITTING
The Consultant shall evaluate existing drainage conditions and design the improvements necessary for the modified skatepark areas, new pump track, and related site work. The City has identified an area that may require removal and replacement of existing concrete and another area that may require an additional drain. The Consultant shall verify the cause and limits of these issues and develop a design that addresses these issues.
The drainage evaluation shall address, as applicable:
• Positive drainage and prevention of ponding on skateable surfaces.
• Existing surface flow patterns, drainage facilities, and nuisance water.
• Inlet and conveyance capacity, connections to existing facilities, and potential downstream effects.
• Gravity drainage and passive systems that minimize long term maintenance. Pumps or other powered drainage equipment shall be proposed only when gravity drainage is not feasible and shall require City approval.
The Consultant shall prepare a concise drainage memorandum and hydrologic and hydraulic calculations sufficient to support the design and applicable approval requirements.
The Consultant shall determine the applicable stormwater, Low Impact Development, erosion control, and water quality requirements and, as applicable:
• Prepare a Water Quality Management Plan or other required documentation.
• Design required Best Management Practices, including sizing, site constraints, maintenance access, plans, details, quantities, and costs.
• Coordinate required infiltration testing under Task 3.
• Include erosion and sediment control plans, notes, details, and quantities in the construction documents.
The Project is anticipated to disturb less than one acre, and a Storm Water Pollution Prevention
Plan is not anticipated. The Consultant shall confirm this determination. If a Storm Water
Pollution Prevention Plan is required, the construction contractor will prepare and implement it.
The Consultant shall identify in its proposal each permit and approval anticipated for final design and construction, the responsible agency, and the assumptions used to develop the proposed fee.
The Consultant shall provide all permitting services required for the work included in this Scope, including:
• Preparing and submitting applications, exhibits, calculations, and supporting documents.
• Coordinating with reviewing agencies and responding to comments through approval.
• Incorporating permit conditions and requirements into the construction documents.
All permitting reasonably required to complete the Project shall be included, whether or not each permit or approval is specifically identified in the proposal.
The City will sign required applications and pay agency fees. CEQA filings are addressed under
Task 4. Permits required solely for field investigations are included under the applicable investigation tasks. Permits for the separately designed building improvements are not included.
TASK 6 – FINAL CONCEPT DESIGN
The Consultant shall use the City provided preliminary concepts, community input, and site conditions to prepare one final concept consistent with City direction. The final concept may combine and refine elements of the preliminary concepts. Additional concept options are not required.
The Public Art Lead shall develop the public art design with City input and coordinate its integration into the site design and PS&E.
The final concept shall provide enough detail for the Consultant and City to confirm that the design can be built, phased, and reasonably priced before proceeding with PS&E. Deliverables shall include:
• A concept plan showing project limits, feature locations, general shapes, approximate dimensions and elevations, and intended skill levels.
• Rider flow, circulation, accessible routes, connections to the existing park, and improvements to remain, be removed, or be changed.
• Sections and profiles showing key heights, slopes, transitions, and connections.
• Preliminary grading, drainage, utility, landscape, irrigation, and site amenity improvements.
• Public art design identifying the proposed location, scale, materials, appearance, durability, maintenance needs, and general installation requirements.
• Monument sign concept showing the proposed layout, materials, colors, and general improvements.
• A construction phasing plan showing access, staging, restoration, and areas that may remain open.
• Four color renderings illustrating the proposed improvements from locations approved by the City. Animation and video are not required.
• A preliminary construction cost estimate organized by major improvement category and including all related work, allowances, and contingency.
• Cost saving or phasing options if the estimate exceeds the available construction budget.
• A draft and final revised concept addressing City comments.
• Materials and attendance for up to two presentations to the Community Services
Commission and/or City Council.
The Consultant shall obtain written City approval of the final concept and cost estimate before proceeding with PS&E.
TASK 7 – 60% PLANS, SPECIFICATIONS, AND ESTIMATE
Following written City approval of the final concept and cost estimate, the Consultant shall prepare a coordinated 60% PS&E package. A separate 30% PS&E submittal is not required.
The 60% submittal shall include a brief design summary describing the proposed work, key design criteria and assumptions, and any major design, coordination, or construction issues, together with recommended solutions for City review.
The Consultant shall determine the final sheet list. The plans shall include, but not be limited to the following:
• General information, sheet index, notes, references, survey control, and benchmarks.
• Existing conditions, removals, protection, and restoration limits.
• Construction limits, access, staging, and phasing.
• Overall site layout, horizontal control, accessible routes, walls, fences, gates, and site amenities.
• Construction Details to support associated site improvements.
• Grading, drainage, water quality, and erosion control improvements.
• Existing and proposed utilities, pothole information, protection, relocations, and connections.
• Skatepark and pump track layouts, dimensions, elevations, slopes, radii, transitions, riding surfaces, and connections.
• Profiles, sections, and details for concrete, reinforcement, joints, coping, rails, edges, drainage, and embedded items.
• Structural plans and details, where required.
• Landscape, irrigation, and restoration improvements.
• Public art plans and details, including dimensions, materials, fabrication, supports, mounting, and installation requirements.
• Monument sign plans, elevations, details, lettering, materials, structural supports, and electrical modifications necessary.
• Time capsule protection, removal, relocation, and reinstallation details.
The Consultant shall prepare a draft outline of the technical specifications required for the
Project and submit it as part of the 60% submittal package.
The Consultant shall prepare a 60% construction cost estimate organized by the proposed bid items and including all work required to construct the Project. Each lump sum item shall include a supporting cost breakdown.
All technical reports, memoranda, and design calculations supporting the PS&E shall be submitted in draft and final form. Drafts shall be submitted no later than the 60% submittal unless required earlier under another task. Final versions shall address City comments and be submitted with the final bid ready PS&E.
The 60% plans, draft technical specification outline, draft supporting reports and calculations, and construction cost estimate shall be submitted electronically.
TASK 8 – 90% PLANS, SPECIFICATIONS, AND ESTIMATE
The Consultant shall address comments on the 60% submittal and advance the design to the
90% level.
The 90% PS&E shall be substantially complete and coordinated among all disciplines and with the building improvement project.
The 90% submittal shall include:
• Completed and coordinated plans containing the information needed to bid and construct the Project.
• Complete draft technical specifications coordinated with the plans.
• Substantially complete design calculations and supporting documents, as applicable.
• Incorporation of applicable City, utility, agency, and permit comments.
• Identification of any remaining permits, approvals, or City decisions needed before the final submittal.
• An updated construction cost estimate organized by bid item. Each lump sum item shall include a supporting cost breakdown. Significant changes from the 60% estimate shall be explained.
The Consultant shall compile all comments received on the 60% submittal into one response matrix using the City’s format. Each comment shall include a complete response, the action taken, and the location of any revision. Comments not incorporated or requiring City direction shall be clearly identified and explained.
The complete 90% package shall be submitted electronically.
TASK 9 – FINAL BID READY PS&E AND RENDERINGS
The Consultant shall address all comments on the 90% submittal and prepare a complete, bid ready PS&E package. Plans, calculations, and other documents shall be signed and sealed by the responsible California licensed professionals, where applicable.
The final plans, technical specifications, bid items, quantities, and construction cost estimate shall be complete and ready for signature. Applicable permit conditions and agency requirements shall be incorporated into the final documents. The Consultant shall coordinate the technical specifications with the City’s standard bidding documents. The City will provide and compile its standard bidding documents.
The final deliverable shall include:
• Signed and sealed final plans.
• Final technical specifications.
• Final design calculations, technical reports, memoranda, and permit documents, as applicable.
• A complete bid item list, quantities, and final construction cost estimate. Each lump sum item shall include a supporting cost breakdown.
• The four renderings prepared under Task 6, updated to reflect the final design.
• A transmittal and complete list of submitted files.
The Consultant shall compile all comments received on the 90% submittal into a final response matrix using the City’s format. Each comment shall include a complete response, the action taken, and the location of any revision. Comments not incorporated shall be identified and resolved with the City prior to submitting the final bid ready package.
Final electronic files shall be provided as follows:
• Plans in searchable PDF and AutoCAD formats.
• Specifications in searchable PDF and Microsoft Word formats.
• Bid items, quantities, and cost estimate in searchable PDF and Microsoft Excel formats.
• Reports, calculations, memoranda, and permit documents in searchable PDF format.
TASK 10 – BIDDING, CONSTRUCTION SUPPORT, AND RECORD DRAWINGS
TASK 10.1 – BIDDING SUPPORT
The Consultant shall provide technical support during advertisement and bidding that includes the following but is not limited to:
• Attendance at the prebid meeting.
• Responses to bidder questions or requests for information.
• Preparation of bid addenda and related design revisions.
• Assistance with technical bid review.
• Preparation of conformed plans and specifications incorporating all issued addenda.
The proposal shall clearly identify the assumptions used to develop the fee for these services.
TASK 10.2 – CONSTRUCTION SUPPORT
The Consultant shall provide design support during construction that includes but is not limited to:
• Attendance at preconstruction meeting and other construction meetings, if required.
• Responses to RFIs and submittals.
• Review substitutions and approved equal requests.
• Review of change orders involving design matters.
• Preparation of design modifications.
• Site observations during construction.
• Punch list walkthrough.
The proposal shall clearly identify the assumptions used to develop the fee for these services.
TASK 10.3 – RECORD DRAWINGS
Following construction, the Consultant shall prepare record drawings based on the final construction documents, approved changes, and complete contractor field markups provided by the City. The Consultant shall incorporate the markups and identify the drawings as record drawings. Any comments provided by the City shall be incorporated into a final set of record drawings.
The Consultant shall notify the City of missing, conflicting, or unclear information before completing the record drawings. Final record drawings shall be provided in searchable PDF and
AutoCAD formats.
5. Evaluation Details
5.1. Evaluation Criteria
A Selection Committee comprised of City staff will evaluate and rank the proposals. Proposals will be evaluated according to the Evaluation Phases.
5.2. Respondent Presentations/Interviews
The City may, at its discretion, invite a shortlist of Respondents to participate in a panel interview to be held at the City. To be considered for an interview, a Respondent must receive an average score of 60 points (60%) or higher on the qualitative proposal portion of the evaluation. The City may require that
Respondents prepare a presentation as part of the interview. No Respondent shall be entitled to or otherwise guaranteed an interview.
5.3. Contract Award
If awarded, the contract will be awarded on the basis of the evaluation criteria set forth herein. The City reserves the right to reject all proposals and to contract for services in the manner that most benefits the City including awarding more than one contract if desired.
5.4. Protests
In order to be considered, a protest must satisfy the following requirements: Protests based on the content of the RFP shall be submitted to the City Representative no later than ten (10) calendar days prior to the scheduled proposal submittal deadline. If necessary, the proposal submittal deadline may be extended pending a resolution of the protest.
Any respondent protesting the recommended award on any ground not based upon the content of the request for proposals must file a protest with the City within three (3) calendar days after the issuance of a notice of recommendation for award. Any protest shall contain a full and complete written statement specifying in detail the grounds of the protest and the facts supporting the protest.
The procedure and time limits set forth in this section are mandatory and are the sole and exclusive remedy in the event of a protest of this procurement. Failure to comply with these protest procedures shall constitute a failure to exhaust administrative remedies and a waiver of any right to further pursue the protest, including filing a Government Code Claim or legal proceedings.
6. Evaluation Phases
EVALUATION PROCEDURES
1. Selection Committee o Proposals submitted will be evaluated by a Selection Committee, appointed by the City
Manager.
2. Review of Proposals o The Selection Committee will use a weighted point formula during the review process to individually score Project Proposals, as outlined in the “Project Proposal Evaluation
Criteria” and the Evaluation Phases below. The Selection Committee will then be convened to review and discuss these evaluations and combine the individual scores to arrive at an average composite Project Proposal score for each firm. Firms that do not meet “Mandatory
Elements” listed below will be eliminated from further consideration.
o After the composite Project Proposal score for each firm has been established based upon the “Qualitative Evaluation” criteria listed below, the Selection Committee may request oral presentations from those firms with a minimum average score of 60 points (60%). The
Selection Committee may also schedule a site visit, if applicable. The oral presentation will be evaluated based upon the “Oral Presentation/Interview Evaluation” criteria listed below. The sealed Cost Proposal of firms receiving a minimum average score of 60 points on the qualitative review will be opened to ensure that the Cost Proposal is reasonable. A summary of all Project Proposals, qualifying on the basis of the qualitative review, interview, and Cost Proposal evaluation as calculated in Section 6.3 will be submitted to the City
Council for final determination.
3. Project Evaluation Criteria - Proposals will be evaluated using three (3) sets of criteria.
1. Mandatory Elements (Pass/Fail)
▪ Firms meeting the mandatory elements will have their proposals evaluated and scored. The following represent the principal selection criteria which will be considered during the evaluation process.
2. Qualifying Proposal Evaluation (Pass/Fail; Maximum Points = 100, Minimum average of 60% of points or 60 points required to proceed to Interview)
▪ In order to be considered for an oral interview/presentation the proposer must achieve at least a minimum average of 60 points from the Qualitative Evaluation. Scores are calculated using weighted criteria.
3. Presentation/Interview Evaluation (Maximum Points =160, 80%) and Cost Proposal
Evaluation (Maximum Points = 40, 20%)
▪ During the evaluation process, the Selection Committee may request oral presentations from firms with a minimum average score of 60 points (60%). Oral presentations will provide firms with an opportunity to answer any questions the Selection Committee may have on a firm’s Project Proposal. The oral presentation will be scored using weighted criteria.
▪ At the conclusion of each of the interviews, the Purchasing Coordinator shall offer each interviewed firm the opportunity to submit a “revised” cost proposal. The intent of this step is not to require the Project Manager to enter into contract negotiations but rather is intended to provide each firm an opportunity to refine its cost proposal subsequent to oral presentations. Each firm will have three to five (3-5) calendar days from the date of the interview to submit a “revised” cost proposal, or indicate in writing that its original cost proposal is to be opened and reviewed.
▪ The interview process is a valuable tool to assess the communication skills and professional demeanor of proposed project personnel. The interview score is arrived at independently from the qualitative proposal score and the two may differ significantly.
The interview portion allows staff greater flexibility to choose a qualified firm with strong communication skills and technical expertise.
4. Rating Definitions o The rating scale establishes standards by which points are assigned to the proposals and oral interviews and it ensures the Selection Committees evaluate each proposal with consistency.
o The following table is a rating scale that is utilized based on a 0-10 scale:
5. Final Selection o The Selection Committee scoring will be provided to the Department Director. The firm must fully execute the Agreement prior to staff recommendation of the contract award to
City Council. The City, through the Department Director, reserves the right to negotiate the price, terms, and scope of work with the successful proposer prior to making a recommendation to the City Council.
6.1. Mandatory Elements
No. Evaluation Criteria Scoring Method Weight (Points)
1. Required Licenses
The proposed team holds all California licenses required to perform the services.
Pass / Fail 1
(20% of Total)
2. Conflict of Interest
The Respondent and its proposed subconsultants have no conflict of interest that would prevent them from performing the services.
Pass / Fail 1
(20% of Total)
3. Proposal Requirements
The proposal materially complies with the preparation and submission requirements of this RFP.
Pass / Fail 1
(20% of Total)
4. Letter of Transmittal
The firm included a Letter of
Transmittal in the Project Proposal.
Pass / Fail 1
(20% of Total)
5. Minimum Experience and
Qualifications
The Prime Consultant, Project
Manager, Lead Skatepark Designer, Civil Engineering Lead, and Public Art
Lead meet the minimum experience and qualification requirements stated in this RFP.
Pass / Fail 1
(20% of Total)
6.2. Qualifying Technical Proposal Evaluation
No
Evaluation Criteria Scoring
Metho d
Weight
(Points
1. Key Personnel and Team Structure
1. Qualifications, relevant experience, licenses, and availability of the proposed Project Manager, Civil Engineering Lead, Lead Skatepark
Designer, Public Art Lead, QA/QC Lead, and other key personnel.
2. Strength of the team’s combined experience in public skatepark design, municipal civil engineering, and public art.
3. Clarity of roles, responsibilities, reporting relationships, and coordination among the Prime Consultant and subconsultants.
4. Level of involvement and commitment of the Project Manager and Lead
Skatepark Designer throughout final concept design, PS&E, bidding, and construction support.
5. Adequacy of the proposed staffing and allocation of key personnel to the Project.
0-10
Points
(25% of
Total)
2. Project Management, Schedule, and Resources
1. Project management and coordination approach.
2. Logic and feasibility of the proposed schedule.
3. Allocation of staff and hours by task.
4. Coordination among the Prime Consultant, subconsultants, City staff, and the separate building improvement consultant.
5. Quality control and interdisciplinary review procedures.
6. Methods for tracking decisions, resolving issues, and monitoring the
Project schedule and budget.
(20%
3. Project Understanding, Approach, and Scope of Services
1. Understanding of the Project goals, existing conditions, preliminary concepts, and work to be performed.
2. Completeness and appropriateness of the proposed scope in addressing the City’s requirements, tasks, and deliverables.
3. Technical approach to developing the final concept and complete,…
This is the start of the file's text. The full file is on GovTribe.