DTRA Instruction 5000.14
Enclosure 4
Feb 10, 2012
EXCEPTION TO FAIR OPPORTUNITY JUSTIFICATION
1. Nature and/or Description of the Action
The Defense Threat Reduction Agency contracting activity proposes to procure, without requesting proposals from all four contractors under the WMD ID/IQ, an effort entitled
“WEFCOM Methodology Report”. Applied Research Associates (ARA) will be the only contractor solicited to provide the required technical effort.
2. Description of the Supplies/Services Required
The WEFCOM methodology report is a document critical to integrating the WEFCOM code into the Nuclear Capabilities Services (NuCS) Modeling and Simulation configuration. It provides the NuCS developers with a technical description of the overall functionality of the code. The developers require the methodology report for both code integration and the preparation of verification/regression test cases and V&V studies. The work is an estimated $66K.
3. Exception to Fair Opportunity
FAR 16.505(b)(2)(ii), only one awardee is capable of providing the supplies or services required at the level of quality required because the supplies or services ordered are unique or highly specialized;
4. Basis of Action
Each nuclear code integrated into NuCS is required to have a methodology report provided by the developing contractor. ARA is the contractor that originally refactored the WEFCOM code in preparation for integration into NuCS. This action was in response to a DISA requirement (Use
Case 14) submitted to RD-NT. The resulting application will provide DISA the capability to assess communication performance (RF) in a nuclear-disturbed environment. Due to budget restrictions and shifting government priorities placed on the contractor, the methodology report was not created following the refactoring effort. Currently, the WEFCOM code is ready for
V&V and subsequent integration into NuCS. To ensure the success of these efforts, the methodology report must be written. Since ARA refactored the WEFCOM code, they are the subject matter experts to produce the report. Any other contractor would have to perform code analysis to determine the functionality of the code and produce the same report. The code is currently scheduled to undergo integration in July 2012, so both the methodology report and
V&V must be accomplished before June 2012.
DTRA Instruction 5000.14
Enclosure 4
Feb 10, 2012
5. Market Research
The market research consisted of the RFI to the ARA PM to provide an estimated cost/effort to produce the report. Contractors under the current ID/IQ have developed these reports within the estimated cost of developing the WEFCOM methodology report. The costs of these reports will vary with complexity of the code for which they are written and are typically produced with the code as they are developed under the contract where code is developed. Reports developed “after the fact” will have costs associated with the level of work required to either have the developer create the report (lower cost) or less experienced contractor “reverse engineer” the report (higher cost). In this situation, ARA is both the developer/integrator of WEFCOM. Due to budget constraints, they were unable to produce a methodology report with the “refactored” WEFCOM code. ARA has written several methodology reports for codes they have integrated in the past
(ex. LFCOM, DUG1c, IGVN, DGBETS, Hendron-Aiyer). ARA has consistently demonstrated the subject matter expertise deemed necessary to provide the Government with the methodology report with the necessary level of technical detail within cost and schedule limitations.
6. Other Supporting Facts.
Historical data for integrating nuclear codes into the NuCS has shown that highly experienced developers and engineers are required to transition legacy stand-alone nuclear codes into the net-centric architectures. These tasks are extremely complex, and demand developers and engineers with proven, community-recognized expertise in the use of WEFCOM in the prediction of high frequency communication link performance. Assuming a new contractor could be found to meet these requirements, it is estimated that six man months of effort by senior scientists and engineers would be required to fully understand the highly technical aspects of this program and develop the required tools prior to producing the results required by the customer. This course of action would cause an unacceptable increase in cost and schedule.