ESTIMATED SCHEDULE OF EVENTS.docx
DOCX document 15 KB Posted
- Attached to
- Manufacture Spud Rails and Securing Brackets, Replace Spud Rail Securing Brackets for ARDM 4
- Solicitation number
- N6278924R0012
About this file
This document is an Estimated Schedule of Events related to a federal contract opportunity for the Manufacture of Spud Rails and Securing Brackets and Replacement of Spud Rail Securing Brackets for the Navy's Shippingport (ARDM 4) Floating Dry Dock. The contract opportunity, solicitation number N62789-24-R-0012, is being issued by the Naval Sea Systems Command (NAVSEA) as a Request for Proposal (RFP) with a firm fixed price contract anticipated. The key elements include an estimated schedule of events from procurement of materials through completion and testing, with a period of performance from 15 November 2024 to 31 July 2025. The RFP requires vendors to provide pricing details for the manufacture of 3 spud rails, 3 spud rail securing brackets, and the removal and reinstallation of 3 brackets, as well as shipping/delivery and travel costs. The evaluation factors include Qualification, Technical Comprehension, Past Performance, and Cost, with Qualification being the most important factor. Proposals are due by 15 October 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation FINAL.pdf | ||
| ARDM 4 SPUD RAIL SPEC.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ESTIMATED SCHEDULE OF EVENTS
| Procure Material: | 15 November 24 – 15 January 25 | ||
| Prefabrication: | 15 January 25 – 15 March 25 | ||
| Remove Spud Rails: | 15 March 25 – 22 March 25 | ||
| Template Spud Rails: | 22 March 25 – 02 April 25 | ||
| Template Rail Brackets: | 22 March 25 – 02 April 25 | ||
| Complete Rail Fabrication: | 02 April 25 – 15 July 25 |
Complete Fabrication &
| Install of Rail Brackets: | 02 April 25 – 15 July 25 |
| Test Shell Plating: | 15 July 25 to 22 July 25 |
| Letter of Completion: | 31 July 25 |
File details come from the government source that posted it. Updated .