This document is a Statement of Work (SOW) for the repair and testing of the ALFA LAVAL Lube Oil and Fuel Oil Purifiers on the USS Land (AS 39) under Contract No. N40446-23-R-XXXX.
The SOW requires the contractor to provide all necessary labor, materials, and services to repair worn components in the lube oil and fuel oil purifiers, including replacing the worm wheel shaft, worm wheel, and pins in the lube oil purifier, and the clutch and bearing in the fuel oil purifier. The contractor must also reassemble the equipment, conduct operational testing in the presence of the Chief Engineer and MSC Port Engineer, and provide a qualified ALFA LAVAL field service representative to support the repairs and testing. All replacement parts must be OEM factory parts. The work is to be performed at Naval Base Guam's Romeo Pier during the period of 02-14 May 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| OTHER THAN FULL AND OPEN COMPETITION MEMO_Redacted.pdf | ||
| N4044624Q0006.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USS Land
( AS 39 )
| AUXILIARY MACHINERY |
| CONTRACT NO. N40446-23-R-XXXX |
| ITEM NO. 0501 |
| CATEGORY "A" |
| 2023-04-18 |
| LUBE OIL AND FUEL OIL PURIFIER REPAIR |
| Riodique, Angelito |
1. ABSTRACT: This work item describes the requirement to repair and test the ALFA LAVAL Lube Oil and Fuel Oil Purifier for normal operation.
2. REFERENCES/ENCLOSURES
2.1. References:
2.1.1. NSTM T9264-AN-MMC-010, Purification System, Lube Oil Model MAB-104
2.1.2. ALFA LAVAL Instruction Book MAB-104, High Speed Separator
2.2. Location/Quantity
2.2.1. Location:
2.2.1.1. Engine Room (7-110-0-E)
2.2.1.2. EDG Room (3-50-01-E)
2.2.2. Quantity:
2.2.2.1. One (1) ALFA LAVAL Lube Oil Purifier MAB-104
2.2.2.2. One (1) ALFA LAVAL Fuel Oil Purifier MAB-104
3. GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None Additional
4. NOTES: None
5. QUALITY ASSURANCE REQUIREMENTS
5.1. In addition to the contractor’s duties under 29CFR1910.147 or similar local safety regulation, the contractor shall comply with all requirements of equipment lock-out/tag-out (LOTO) program as established by MSC SMS procedure 2.1-004-ALL Lock-out/Tag-out. The Chief Engineer shall administer the program. Prior to the start of work, the contractor shall contact the REP and / or the Chief Engineer to coordinate the implementation of the LOTO program for the entire performance period of this item. The prime contractor shall be responsible for compliance by both prime and subcontractor personnel.
5.2. All replacement parts shall be OEM (original equipment manufacturers) factory parts.
6. STATEMENT OF WORK
6.1. Arrangements/Outfitting:
6.1.1. Provide all material and special equipment. Make all removals and restorations. Remove and replace all interferences, rig and unrig, stage and unstage, make all disassembles and subsequent reassembles, provide and operate equipment, and supply all services and assistance to accomplish the following work. (Material, unless specifically stated as Government Furnished Material (GFM) shall be supplied by the contractor).
6.1.2. Contractor to provide labor and the following Contractor Furnished Materials (CFM) and repair the equipment listed in 3.1.2.
7.1.2.1 Lube Purifier have worn out pins, need cut the worm and horizontal shaft out and replace with new CFM listed below:
Part# 51999381 WORM WHEEL SHAFT CPL, QTY: One Part# 51577603 PCE WORM WHEEL 60 HZ, QTY: One Part# 636200 PCE PIN, QTY: One
7.1.2.1 Fuel Purifier failed Vibration Analysis and will not operate at the operating speed, Vibration Analysis recommend to replace the following CFM:
Clutch, QTY: One Bearing, QTY: One
7.1.3 Reassemble the equipment listed in 3.1.2 in accordance with 2.1 and 2.2.
7.1.4 Inspection/Test:
7.1.4.1 Ship’s Force to conduct an operational test of the equipment listed in 3.1.2 in the presence of CHENG, and the MSC Port Engineer.
7.2 Manufacturer’s Representative:
7.2.1 Provide the services of a qualified ALFA LAVAL Field Service Representative with experience in ALFA LAVAL Purification Systems to accomplish repairs, and testing.
Known Source:
ALFA LAVAL Inc.
5400 Internatinal Trade Drive Richmond VA, 23231
(866) 253-2528 POC: Barbara Moy
E-Mail: barbara.moy@alfalaval.com
GENERAL REQUIREMENTS:
SOR: ESL24-001
Location: Naval Base Guam Romeo Pier
Period of Performance: 02-14 MAY 2024 0501 - 2