This document is an Addendum to a Request for Qualifications (RFQ) issued by the Texas Tech University Health Sciences Center (TTUHSC) for the LARC Renovation project. The purpose of this $15 million project is to expand the current LARC space in the basement of Pod C on the TTUHSC Lubbock campus to meet future research community needs and aid in the expansion of Biomedical Research. The renovated space will create a facility with complete bio-exclusion from the existing LARC, requiring a decontamination room and bulk autoclave. Phasing of the work is critical to avoid disruption to the active research operations. Proposals are due on March 9, 2023 at 3:00 PM and should be submitted through the e-Builder Bid Portal. The evaluation criteria include the quality and qualifications of the proposed project team, the firm's experience with CMAR delivery for higher education projects, and the HUB contracting commitment. The anticipated construction schedule is to be determined following the selection of the CMAR.
The RFQ requires proposers to provide information on their company, project team, and past relevant experience. Proposers must also submit their HUB contracting commitment and plan. TTUHSC is seeking to utilize HUB companies for a minimum of 21.1% of the total contract amount. The HUB Subcontracting Plan must be updated throughout the project duration.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NUMBER ONE (1) Page 1
Date: February 21, 2023
Texas Tech University Health Sciences Center Laboratory Animal Resources Center (LARC) Renovation
Texas Tech University System
Lubbock, Texas
FP&C Number: 22-07
NOTICE TO ALL RESPONDENTS:
The following shall be incorporated in and become a part of the original Request for Qualifications (RFQ) of the above-identified project. Please acknowledge receipt of this Addendum in the space provided on the Form of Response within the RFQ. Failure to do so may subject the Respondent to disqualification.
ITEM #1:
• CMAR pre-response meeting attendance sheet and presentation are attached as information.
Please send any further questions to Richard A. Richeda at rick.richeda@ttu.edu. All answers to questions received will be replied to on the ESBD website/e-Builder Bid Portal as an additional addendum.
END OF ADDENDUM NO. ONE (1)
mailto:rick.richeda@ttu.edu
1. Summary
Meeting title 22-07 LARC - CMAR Pre-Response Meeting
Attended 10
Start time 2/21/23, 9:47:40 AM
End time 2/21/23, 10:22:11 AM
Meeting duration 34m 30s
Average attendance time 22m 17s
2. Participants
Name First join Last leave
In-meeting duration Email Role
Richeda, Rick 2/21/23, 9:47:47 AM 2/21/23, 10:21:53 AM 34m 6s Rick.Richeda@ttu.edu Organizer
Parker Hutchens 2/21/23, 9:58:29 AM 2/21/23, 10:22:00 AM 23m 31s phutchens@teinert.com Teinert Construction
Tyler - Lee Lewis Construction 2/21/23, 9:58:48 AM 2/21/23, 10:22:01 AM 23m 12s LLCI
Brent Adams 2/21/23, 9:59:52 AM 2/21/23, 10:22:03 AM 22m 11s brent.adams@clarkenersen.com Eng'r
Marcie Dorsett 2/21/23, 9:59:54 AM 2/21/23, 10:22:11 AM 22m 16s TTUHSC
Ellis, Jodie 2/21/23, 10:00:34 AM 2/21/23, 10:22:05 AM 21m 31s Jodie.Ellis@ttuhsc.edu TTUHSC
Scott Trasti (Guest) 2/21/23, 10:00:40 AM 2/21/23, 10:21:58 AM 21m 17s TTUHSC
James Beecher 2/21/23, 10:00:50 AM 2/21/23, 10:21:57 AM 21m 7s james.beecher@clarkenersen.com Eng'r
Jeremy (Guest) 2/21/23, 10:03:44 AM 2/21/23, 10:22:01 AM 18m 17s jeremy.dickson@ttuhsc.edu TTUHSC
Lee Lewis Construction (Guest) 2/21/23, 10:06:34 AM 2/21/23, 10:22:00 AM 15m 26s LLCI
3. In Person Participants
Alexis Henry TTUS-Contract Adminstrator
Mike Robertson Western Builders
Brandon Robertson Western Builders
Blake Hoelting AP Construction
Sheila Sims Design Professional of Record
Harry Slife TTUHSC
Aaron Scherpereel TTUHSC
Billy Breedlove TTUS-Vice Chancellor
Todd Hardin TTUS-Associate VC
Stand by, the meeting will begin shortly.
Please provide your contact information to rick.richeda@ttu.edu
Remember to check the Electronic State Business Daily regularly for any addenda.
Request for Qualifications – TTUHSC LARC Renovation
Construction Manager at Risk Pre-Response Meeting Tuesday, February 21, 2023 • 10:00 a.m.
Agenda
Introductions
Project Information
Project Requirements
Evaluation Criteria / Project Schedule
Key Reminders and Questions
Facilities Planning and Construction
Billy Breedlove, Vice Chancellor
Todd Hardin, Associate Vice Chancellor
Rick Richeda, Sr. Program Director
Alexis Henry, Contract Administrator
Design Professional
Sims Architects and Clark & Enersen
Component Institution
Scott Trasti, LARC Director
Marcie Dorsett, Associate LARC Director
Harry Slife, Operations VP
Aaron Scherpereel, Assistant VP
Jeremy Dickson, Operations PM Director
Project Information
Project Requirements
NORTHTexas Tech Health Sciences Center
4th Street
Te xa s Te ch P a rk w a y
In d ia n a A ve n u e
Pod APod BPod C
TTUHSC Lubbock Campus
LARC Renovation
$15,000,000 Total Budget
TTUHSC Lubbock Campus
LARC Renovation
$15,000,000 Total Budget
The purpose of this project is to expand the current TTUHSC Lubbock Laboratory Animal Research Center (LARC) space to meet future research community needs and aid in expansion of Biomedical Research. The renovated space will reside in the basement of Pod C, adjacent to the existing LARC facility. The combined spaces will provide approximately 12,600 sf.
The expansion will create a facility with complete bio-exclusion from the existing LARC facility. The separation will require a decontamination room and bulk autoclave, allowing for sterilization / decontamination.
Phasing work is anticipated to avoid research and operation disruption.
Due to intense MEP requirements, the CMAR will be responsible to be familiar with the existing facility conditions.
Project Information
NORTH
Texas Tech Health Sciences Center LARC Renovation
Preliminary programming plan of renovated area. Spaces include: Cage washing, clean staging, procedure rooms, holding rooms, ante spaces, air locks, and barrier walls.
The existing LARC is active with research project. Phasing and scheduling with the
TTUHSC Operations and LARC director will be critical.
Texas Tech Health Sciences Center LARC Renovation
NORTH
Bsmt POD C
Existing
LARC
Existing
Offices
Project Information
Proposal Requirements
Proposal Requirements
Proposals are due Thursday, March 9, 2023 at 10:00 AM Refer to the “Instructions on Creating a Bid Package
Response”
General Company Information
• History of the company and office locations. Designate the office location responsible project execution.
• Company ownership and contact information.
• Services offered and total number of staff.
• Business volume for past five years.
• CMAR Higher Ed Project Experience summary over the past five years (not in page count).
General Company Information (Cont.)
• Implemented safety and health program.
• Quality control / Quality assurance program, methodology and responsibilities.
• Claims and litigation for the past five years.
• Scheduling systems employed.
• EMR for the past five years.
• Other relevant information.
Proposal Requirements (cont.)
Project Specific Information
Team Information
• Project management team organizational chart.
• Commitment to maintain proposed project CMAR team.
• Qualifications of the proposed project team.
• Current references for each team member.
• Defined roles and responsibilities of each team member.
• Potential project challenges from the proposed team.
Project Specific Information
• Provide information and references for five projects with comparable conditions and circumstances to this project the CM successfully completed using the CMAR delivery.
Methodology (sequenced and phased delivery, occupied facility, constrained site, etc.) Disclose construction team member, their role and their office origin.
• List examples of how the CMAR offered and applied innovative solutions on those projects to successfully maintain the construction budget and schedule and increase quality and safety.
• Form of Response – Signed (front of document)
HUB Contracting Commitment
TTUS wants all contractors to put forth a “good faith effort” in utilizing HUB resources.
• This is a voluntary commitment.
• State goal for Building Construction is 21.1%.
• Indicate your company’s voluntary commitment to the amount of work, as a percent of the total contract amount, performed by certified HUB companies including work your company will self-perform, if it is a certified HUB company.
• HUB solicitation outreach plan.
• If selected, must present a HSP at the pre-construction stage.
HUB Contracting Commitment (cont.)
• Contractors must update their HUB Subcontracting Plan (HSP) during Guaranteed Maximum Price buyout amendment process.
• HSP must be updated at the 50% of completion application for payment.
• Again, HSP must be updated at the 100% final cost application for payment (final payment will not be processed without having received the final 100% HUB Subcontracting Plan).
Project Information
Project Requirements
Evaluation Criteria
Quality and qualifications of the proposed project team.
Demonstrated ability to perform as a member of a collaborative team.
Company’s specific project experience with the specific office and team proposed.
Company’s experience at successfully delivering higher education Construction Manager At Risk projects.
Team’s Performance (list of references).
Pre-construction services provided including constructability reviews, cost analysis & cost control measures.
Scheduling management, include types and examples.
Evaluation Criteria (cont.)
Quality assurance / Quality control plan, responsibilities, and execution - Who ensures the project is meeting the quality and specifications required?
HUB contracting commitment.
Quality, organization, and comprehensiveness of the submission.
The Company’s safety and health program.
Records of claims and litigation.
The Firm’s experience modification ratio (EMR).
Project Schedule Schedule
• Post on ESBD Thursday, February 16, 2023
• Pre-Response meeting 10:00 AM, February 21, 2023
• Written Inquires rec’d by 2:00 PM, March 1, 2023
• Responses due by 2:00 PM, March 2, 2023
• Proposals due 3:00 PM, March 9, 2023
Refer to the “Instructions on Creating a Bid Package Response”
• Shortlist selection March 28, 2023
• Estimated interviews April 19, 2023
• Estimated CMR selection April 20, 2023
• Estimated construction TBD
Project Information
Project Requirements
Don’t Forget Responses are DUE at 3:00 p.m., Thursday, March 9, 2023
• Responses can be uploaded through the e-Builder Bid Portal until 3:00PM, Thursday, March 9, 2023. Upload access will be denied after the submission deadline. Please click the link below to access the e-Builder Bid Portal where the RFQ bidding document is located:
• https://gateway.app.e-builder.net/app/bidders/landing?bidpackageid=f8169861-58f8-4e81-ae59- 99f49d92ce88
• Hard copies will not be accepted.
• Responses must be in pdf format and include a signed Attachment A – Form of Response.
QUESTIONS?
Thank you for attending
Please provide your contact information to rick.richeda@ttu.edu and remember to check the
Electronic State Business Daily regularly for any addenda https://www.txsmartbuy.com/esbddetails/view/22-07_LARC_CMAR_RFQ
| 22-07_TTUHSC Laboratory Animal Resource Center (LARC) Expansion_CMAR_RFQ_Addendum 1_2023.2.21 |
| 22-07 LARC_CMAR Pre-Response Meeting_Attendance report_2023.02.21 |
| 22-07 LARC_CMAR Pre-Response Presentation_2023.02.21 |