ESBD_576101_1794593887959_line replacement sow.docx

DOCX document 13 KB Posted

Attached to
FY27_BWD_line_replacement
Solicitation number
FY27_BWD_line_replacement
Issued by
Burleson County, Texas

About this file

This is a Scope of Work (SOW) document for a plumbing line replacement project. The project involves replacing a 60-foot section of deteriorated cast-iron waste line in a kitchen facility and rerouting drain lines from a scullery area. The scope includes removal and disposal of the existing main line, installation of approximately 60 feet of new 4-inch Schedule 40 PVC drainage piping with appropriate fittings, reconnection of two existing kitchen sinks and one floor drain to the new main, and extension of two existing copper drain lines serving the scullery using approximately 5-10 feet of Schedule 40 PVC piping to reconnect them to the grease trap inlet. Additional work includes excavation and concrete removal as necessary to access connection points, proper bedding and support of new piping, hydrostatic testing before covering, and concrete restoration with appropriate patching and reinforcement to finish level with the surrounding slab.

The SOW specifies that all necessary labor and supplies must be provided by the contractor to complete the work, including nonslip tile removal, saw-cutting and jackhammering of concrete, material backfilling and compaction in lifts, and operational drainage checks following reconnection. The document emphasizes proper installation practices such as establishing correct drainage grade, preventing settlement and damage through proper compaction, isolating retained existing piping during testing, and checking all accessible connections for leakage. No pricing terms, set-asides, contract term information, or funding sources are detailed in this SOW document.

View the file

Other files

File Type Posted
ESBD_576101_1794593840884_line replacement ifb.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace a 60’ section of waste line in the kitchen and tie back in to grease trap, (2)existing sinks and (1) floor drain. Reroute two existing 2” drain lines from scullery over to the inlet side of the grease trap. Below is a pretty comprehensive SOW

Provide necessary labor and supplies to perform the following:

Remove nonslip tile within the required plumbing access area.

Saw-cut, jackhammer, and remove concrete as necessary.

Excavate to expose the specified main and its branch connection points.

Remove and dispose of the deteriorated cast-iron main within the defined replacement area.

Install approximately 60 feet of new 4-inch Schedule 40 PVC drainage piping with approved fittings and transitions appropriate for the existing pipe materials.

Properly bed the piping in suitable granular material, providing continuous support beneath the pipe barrel and along its sides.

Establish proper drainage grade and compact surrounding material to prevent movement, settlement, and damage.

Reconnect serviceable existing kitchen branches to the new main at the exposed connection points.

Connect the new main to the existing end-of-line cleanout, including immediate connection fittings.

Excavate outside the concrete footprint near the grease trap to access two existing copper drains serving the scullery/dish-pit area.

Extend those drains using approximately 5–10 feet of Schedule 40 PVC piping, as required, and reconnect them to the grease-trap inlet piping.

Properly close the superseded connection openings affected by this correction.

Hydrostatic-test the newly installed piping before covering, isolating retained existing piping as necessary.

Check accessible connections for leakage and perform operational drainage checks after reconnection.

Backfill with suitable material and compact in lifts.

Restore concrete within the plumbing access area, including appropriate patch preparation, reinforcement, and doweling as required. Finish level with the surrounding slab for tile installation by others.