ESBD_574944_1794244607970_2026.11.09 - LU New Residence Hall DB 27-05037 - Bid Specification 1st Phase RFQ for Design-Build (final).pdf
PDF 5 MB Posted
- Solicitation number
- 758-27-05037
- Issued by
- Johnson County, Beaumont City, Texas
About this file
Summary
This is a Request for Qualifications (RFQ) issued by The Texas State University System on behalf of Lamar University for the selection of a Design/Build firm to construct a new residence hall in Beaumont, Texas. The project involves approximately 240,000 gross square feet providing approximately 1,000 student beds, primarily in traditional double room configurations with communal bathrooms, shared study and amenity spaces, and building systems, technology, and security improvements. The RFQ is a two-phase selection process where Phase One evaluates qualifications without cost considerations, and Phase Two includes interviews and proposal submissions from shortlisted respondents. The mandatory pre-submission conference is scheduled for November 19, 2026 at 10:30 a.m. at Lamar University in Beaumont, Texas. The deadline for submitting qualifications, VetHUB Commitment Letters, and HUB Subcontracting Plans is December 8, 2026 at 2:00 p.m. Central Standard Time at the Lamar University Purchasing Office. The anticipated project timeline includes Design/Build Agreement execution by March 19, 2027, Notice to Proceed for Construction Phase by August 23, 2027, Substantial Completion by June 1, 2029, and occupancy by August 3, 2029.
The Design/Build Budget Limitation is $113,400,000 with a Construction Cost Limitation of $105,000,000. Phase One qualifications shall constitute up to 50 percent of the total evaluation score based on criteria including firm capability, design/build team qualifications, past performance on representative projects, ability to establish budgets and control costs, ability to meet schedules, knowledge of current construction methodologies and best practices, ability to identify and resolve problems, ability to manage construction safety risks, and warranty and service support programs. No cost or pricing information is required in Phase One. In Phase Two, shortlisted respondents (up to five firms) will be required to submit separate line-item proposals for Pre-Construction Phase Fees, Construction Phase Fees, and General Conditions costs, excluding architectural and engineering fees. The Owner will negotiate with the highest-ranked respondent and proceed sequentially through the ranked list if negotiations fail. The Texas Prevailing Wage Law will be administered, and all contractors must comply with VetHUB utilization requirements, demonstrating good faith efforts to subcontract with service-disabled veteran-owned businesses. The selected Design/Build firm's architect must comply with Chapter 1051, Texas Occupations Code, and the engineer must comply with Chapter 1001, Texas Occupations Code.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUALIFICATIONS
FOR
DESIGN-BUILD SERVICES
FOR
LAMAR UNIVERSITY
BEAUMONT, TEXAS
NEW RESIDENCE HALL
RFQ No.:
758-27-05037
Submission Date:
December 8, 2026 – 2:00 p.m. (C.S.T.)
Prepared By:
Donna Bryce, Senior Contract Administrator
The Texas State University System 601 Colorado Street
Austin, TX 78701-2904 512-463-1808 donna.bryce@tsus.edu
RFQ for Design-Build Services (posted 11/09/2026) New Residence Hall at Lamar University in Beaumont, Texas
RFQ No. 758-27-05037 mailto:peter.maass@tsus.edu
TABLE OF CONTENTS
Section 1 - General Information & Requirements
1.1 General Information
1.2 Public Information
1.3 Type of Contract
1.4 Clarifications and Interpretations
1.5 Submission of Qualifications
1.6 Point-Of-Contact
1.7 Evaluation of Qualifications
1.8 Owner’s Reservation of Rights
1.9 Acceptance of Evaluation Methodology
1.10 No Reimbursement for Costs
1.11 Mandatory Pre-Submission Conference
1.12 Eligible Respondents
1.13 Veteran Heroes United in Business Submittal Requirements
1.14 Certain Proposals and Contracts Prohibited
1.15 Sales and Use Taxes
1.16 Certification of Franchise Tax Status
1.17 Delinquency in Paying Child Support
1.18 State Registration of Architecture Firms
1.19 State Registration of Engineering Firms
1.20 Required Notices of Workers’ Compensation Insurance Coverage
1.21 Insurance Requirements
1.22 Prevailing Wage Rate Determination
1.23 Nondiscrimination
1.24 Non-Boycott Israel Verification
1.25 Cybersecurity Training Program
1.26 Certification Regarding Business with Certain Countries and Organizations
1.27 Firearm Entities and Trade Associations Discrimination
1.28 Energy Company Boycotts
1.29 Vaccine Passport Prohibition
1.30 Critical Infrastructure Affirmation
1.31 Hardening of Texas’s Critical Infrastructure
Section 2 - Executive Summary
2.1 Historical Background
RFQ for Design-Build Services (posted 11/09/2026) New Residence Hall at Lamar University in Beaumont, Texas
RFQ No. 758-27-05037
2.2 Mission Statement
2.3 Project Description, Budget, and Scope
2.4 Project Planning Schedule
2.5 Owner’s Special Conditions
Section 3 - Requirements for Statement of Qualifications
3.1 Respondent’s Ability to Provide Design/Build Services
3.2 Qualifications of the Design/Build Team and the Execution of Services
3.3 Respondent’s Past Performance on Representative Design/Build Projects
3.4 Respondent’s Ability to Establish Budgets and Control Costs
3.5 Respondent’s Ability to Meet Schedules
3.6 Respondent’s Knowledge of Current Construction Methodologies, Technologies, Quality, and
Best Practices
3.7 Respondent’s Ability to Identify and Resolve Problems
3.8 Respondent’s Ability to Manage Construction Safety Risks
3.9 Respondent’s Warranty and Service Support Program for this Project
3.10 Execution of Offer
Section 4 - Format for Statement of Qualifications
4.1 General Instructions
4.2 Page Size, Binding, Dividers and Tabs
4.3 Table of Contents
4.4 Pagination
Section 5 - Attachments to the RFQ
5.1 Attachment A - VetHUB Commitment Letter – Sample
5.2 Attachment B – Design Criteria Package (posted on ESBD)
5.3 Attachment C – Pre-Submission Conference - Parking Map
RFQ for Design-Build Services (posted 11/09/2026) New Residence Hall at Lamar University in Beaumont, Texas
REQUEST FOR QUALIFICATIONS FOR DESIGN/BUILD SERVICES
LAMAR UNIVERSITY
BEAUMONT, TEXAS
NEW RESIDENCE HALL
RFQ No.: 758-27-05037
SECTION 1 – GENERAL INFORMATION & REQUIREMENTS
1.1 GENERAL INFORMATION: The Texas State University System (“Owner”) on behalf of Lamar
University (“Institution”), are soliciting Statements of Qualifications (“Qualifications”) for selection of a Design/Build firm for the New Residence Hall (“Project”), on the University’s site located in Beaumont, Texas. This solicitation sets forth the terms, conditions, and requirements for prospective Design/Build firms to be considered for this work. (Prospective Design/Build firms are hereinafter referred to as “Respondents”).
1.1.1 This Request for Qualifications (“RFQ”) is the first phase in a two-phase process for selecting a Design/Build firm for the Project as provided by Texas Education Code
§51.780. This RFQ provides the information necessary to prepare and submit
Qualifications and for the Owner to evaluate each Respondent’s experience, technical competence, capability to perform, the past performance of the Respondent's team and members of the team, and other appropriate factors submitted in response to the RFQ, except that cost-related or price-related evaluation factors are not permitted through the initial qualification and ranking of the Respondent. Each Respondent must certify to the
Owner that each architect and/or engineer (“A/E”) that is a member of its team was selected based on demonstrated competence and qualifications in the manner provided by Section
2254.004, Texas Government Code. The response to the RFQ will provide all the information necessary for consideration and initial ranking by the Owner. Based on the initial ranking, the Owner may select a short list of up to five (5) of the top ranked
Respondents for an interview. Short-listed Respondents may be required to submit additional information in connection with the interview.
1.1.2 In phase two, the Owner may request additional information regarding each short-listed
Respondent’s demonstrated competence and qualifications, considerations of the safety and long-term durability of the project, the feasibility of implementing the project as proposed, the ability of the Respondent to meet schedules, costing methodology, and other factors as appropriate. The Owner will not require Respondents to submit detailed architectural or engineering designs as part of the proposal. The Owner shall rank each proposal submitted on the basis of the criteria specified in the RFQ, the additional information submitted in connection with the interview, and the interview itself, if held.
The owner shall select the Design/Build firm that submits the proposal offering the best value for the Institution on the basis of the published selection criteria and on its ranking evaluations.
1.1.3 As part of phase two, the short-listed Respondents will be required to submit a proposal on the Owner-provided proposal form. The proposal form shall be submitted in a sealed envelope with the RFQ number and the Respondent’s name clearly stated on the outside of the envelope. The proposal form will include line items that require each of the following to be stated separately: the Proposed Pre-Construction Phase Fee, the Proposed
Construction Phase Fee, and the Proposed General Conditions costs by line item category.
RFQ for Design-Build Services (posted 11/09/2026) New Residence Hall at Lamar University in Beaumont, Texas
All proposed fees and general condition costs shall exclude any and all architectural and engineering fees.
1.1.4 After the evaluation of information provided under phase two, and any subsequent re-ranking of the short-listed Respondents, the Owner shall first attempt to negotiate a contract with the highest ranked Respondent. If the Owner is unable to negotiate a satisfactory contract with the selected Respondent, the Owner shall, formally and in writing, end all negotiations with that Respondent and proceed to negotiate with the next Respondent in the order of the selection ranking until a contract is reached or negotiations with all ranked
Respondents end. In the course of negotiating the contract, the Owner shall rely on the fee and cost proposals provided by the Respondent under phase two. Time is of the essence for the Owner in the negotiation of contracts and Respondent shall take all necessary measures to assure that proposals and revisions to proposals are expedited. Failure of the
Respondent to be responsive and maintain a satisfactory and expedited negotiating schedule shall form the basis for the Owner to end all negotiations with the Respondent.
1.1.5 The Owner has established a Design/Builder’s Budget Limitation (“DBBL”) amount of
One Hundred Thirteen Million Four Hundred Thousand Dollars ($113,400,000) The
DBBL includes a Construction Cost Limitation (“CCL”) of One Hundred Five Million
Dollars ($105,000,000). The selected Design/Build firm will be expected to present a
Guaranteed Maximum Price Amount (including a mutually agreed upon construction contingency) for Owner’s approval at the completion of the one hundred percent (100%)
Design Development Documents.
1.1.6 Following selection of a Design/Build firm, that firm's A/E shall complete the design, submitting all design elements for review and determination of scope compliance by the
Owner before construction. An architect shall have responsibility for compliance with the requirements of Chapter 1051, Texas Occupations Code. An engineer shall have responsibility for compliance with the engineering design requirements and all other applicable requirements of Chapter 1001, Texas Occupations Code.
1.1.7 The successful Respondent will be required to use the Owner’s web-based project management software.
1.2 PUBLIC INFORMATION: All information, documentation, and other materials submitted in response to this solicitation are considered non-confidential and/or non-proprietary and are subject to public disclosure under the Texas Public Information Act (Texas Government Code, Chapter
552.001, et seq.) after the solicitation is completed. The Owner strictly complies with all statutes, court decisions, and opinions of the Texas Attorney General with respect to disclosure of RFQ information. Additionally, pursuant to the provisions of Texas Government Code Section
2261.253, the contract resulting from this solicitation will be posted on the Owner’s website.
Without limiting the foregoing, the requirements of Subchapter J, Chapter 552, Texas Government
Code, may apply to this solicitation and the Respondent agrees that the contract can be terminated if the contractor or vendor entering into the contract pursuant to this solicitation knowingly or intentionally fails to comply with a requirement of that Subchapter.
1.3 TYPE OF CONTRACT: Any contract resulting from this solicitation will be in the form of the
Owner’s Standard Design/Build Contractor Agreement (“Agreement” or “Contract”), a copy of which is posted on Owner’s website at: http://www.tsus.edu/offices/finance/capital-projects.html
RFQ No. 758-27-05037 http://www.tsus.edu/offices/finance/capital-projects.html
1.3.1 The Contract should be viewed as a draft and is subject to change. The 2022 Uniform
General Conditions for Construction Contracts referenced in the Contract may be viewed on the Owner’s website at:
1.4 CLARIFICATIONS AND INTERPRETATIONS: Discrepancies, omissions or doubts as to the meaning of RFQ documents shall be communicated in writing to the Owner for interpretation. Any responses to inquiries, clarifications, or interpretations of this RFQ that materially affect or change its requirements will be issued formally by the Owner as a written addendum. All such addenda issued by the Owner before the Qualifications are due become part of the RFQ. Respondents shall acknowledge receipt of and incorporate each addendum in its Qualifications submittal.
Respondents shall be required to consider only those clarifications and interpretations that the
Owner issues by addenda. Interpretations or clarifications obtained in any other form, including oral statements, will not be binding on the Owner and should not be relied on in preparing
Qualifications. It is the responsibility of all Respondents to check the status of formal addenda regularly and five (5) days before the submission deadline.
1.4.1 The deadline for the receipt of written questions is stated in Section 2.4.
1.4.2 ADDENDA AND AWARD INFORMATION, WILL BE ISSUED BY THE OWNER
FOR THIS RFQ VIA THE ELECTRONIC BUSINESS DAILY WEBSITE AT THE
FOLLOWING LINK:
http://www.txsmartbuy.com/sp
REFERENCE “BOARD OF REGENTS/TEXAS STATE UNIVERSITY SYSTEM – 758”
AND THE RFQ NUMBER PROVIDED IN THIS SOLICITATION.
1.5 SUBMISSION OF QUALIFICATIONS:
1.5.1 The Qualifications, including the VetHUB Subcontracting Plan for the A/E’s services and
VetHUB Commitment Letter for the Builder’s services, must be received at the address specified in Section 1.5.2 prior to the date and time deadline. Please note that overnight deliveries such as FedEx and UPS arrive at a central campus location and are usually not delivered to the specified location until after the time deadline. Respondents are advised to use other methods of delivery or, if using an overnight delivery service, to send the
Qualifications a day earlier than usual. The Owner will not consider any response to this solicitation that is not received at the address specified by the deadline, regardless of whether it has been received by the Institution.
1.5.2 DEADLINE AND LOCATION: The Owner will receive Qualifications at the time and location described below.
December 8, 2026 – 2:00 p.m. (C.S.T.)
Kelli Morris, CTCD
Lamar University Purchasing
Otho H. Plummer Building Room 120
4400 Martin Luther King Parkway
Beaumont, Texas 77705
1.5.3 Submit two (2) identical copies of the Qualifications. An original signature must be included on the Respondent’s “Execution of Offer” document submitted with each copy.
Include two (2) digital versions of the signed Qualifications documents on individual
RFQ for Design-Build Services (posted 11/09/2026) New Residence Hall at Lamar University in Beaumont, Texas
RFQ No. 758-27-05037 http://www.txsmartbuy.com/sp
USB/flash drives in Adobe Acrobat PDF format. The individual USB/flash drives containing the Qualifications must be submitted with the hard copies in a separate, sealed package. Do not include the HSP, or HCL with the Qualifications.
1.5.4 Qualifications must include one (1) original, one (1) hard copy, and two (2) electronic copies on USB/flash drives in Adobe Acrobat PDF format, of the A/E’s HUB
Subcontracting Plan (“HSP”) and Builder’s HUB Commitment Letter (“HCL”); as separate sealed attachments to the Qualifications as described in Section 1.13. Do not include the
Qualifications with the HSP and HCL.
1.5.5 Qualifications received after the stated official deadline in Section 1.5.2 will be returned to the Respondent unopened. The Point-of-Contact identified in Section 1.6 will identify the official time clock at the RFQ submittal location identified above.
1.5.6 The Owner will not acknowledge or receive Qualifications that are delivered by telephone, facsimile (fax), or electronic mail (e-mail).
1.5.7 Properly submitted Qualifications will not be returned to Respondents.
1.5.8 Respondent’s Qualifications materials must be enclosed in a sealed envelope (box or container) addressed to the Point-of-Contact. Packages must clearly identify the submittal deadline, the RFQ title and number, and include the name, email address, and return address of the Respondent’s contact person on all envelopes. The Qualifications must be packaged separately from the HSP and HCL in sealed envelopes within the sealed envelope
(box or container).
1.5.9 Properly submitted Qualifications will be opened publicly and the names of the
Respondents will be read aloud immediately after the submissions of Qualifications deadline in Section 1.5.2.
1.6 POINT-OF-CONTACT: The Owner designates the following person, as its representative and
Point-of-Contact for this RFQ. Respondents shall restrict all contact with the Owner and direct all questions regarding this RFQ, including questions regarding terms and conditions in writing, to the
Point-of-Contact, via email only.
Kelli Morris, CTCD, Assistant Director of Procurement Services
Lamar University
Email Address: kelli.morris@lamar.edu
1.7 EVALUATION OF QUALIFICATIONS: The first phase evaluation of the Qualifications shall be based on the requirements described in this RFQ. All properly submitted Qualifications will be reviewed, evaluated, and ranked by a Selection Committee appointed by the President of Lamar
University, or their designee. Typically, that committee will include both future users of the facilities developed by the Project and facilities professionals, as well as potential representation from The Texas State University System Administration. The top five (5) or fewer ranked
Respondents may be selected by the Owner to participate in phase two of the selection process.
1.7.1 First phase qualifications shall not include any information regarding Respondent’s fees, pricing, or other compensation. Such information will be solicited from firms qualified by the Owner to participate in phase two of the selection process but will exclude any and all architectural and engineering fees.
1.8 OWNER’S RESERVATION OF RIGHTS: The Owner may evaluate the Qualifications based on the anticipated completion of all or any portion of the Project. The Owner reserves the right to divide the Project into multiple parts, to reject any and all Qualifications and re-solicit for new
Qualifications, or to reject any and all responses and temporarily or permanently abandon the
Project. Owner makes no representations, written or oral, that it will enter into any form of agreement with any Respondent to this RFQ for any project and no such representation is intended or should be construed by the issuance of this RFQ.
1.9 ACCEPTANCE OF EVALUATION METHODOLOGY: By submitting its Qualifications in response to this RFQ, Respondent accepts the evaluation process and acknowledges and accepts that determination of the “most qualified” firm(s) will require subjective judgments by the Owner.
Determinations by the evaluation committee will be subjected to routine administrative review by the Owner’s executive officers but, once a selection is announced, it will not be subjected to further review.
1.10 NO REIMBURSEMENT FOR COSTS: Respondent acknowledges and accepts that any costs incurred from the Respondent’s participation in this RFQ process shall be at the sole risk and responsibility of the Respondent. Respondents submit Qualifications and Proposals at their own risk and expense.
1.11 MANADATORY PRE-SUBMISSION CONFERENCE: A mandatory pre-submission conference will be held on:
November 19, 2026 – 10:30 a.m. (C.S.T.)
Lamar University
Dade Phelan Building, Room No. 113
5091 Rolfe Christopher Drive
Beaumont, Texas 77710
• Parking available on-site (see map - Attachment C).
• A guided tour will not be included as part of the Pre-Submission conference.
• Questions regarding the Pre-Submission Conference may directed to Kelli Morris at kelli.morris@lamar.edu; phone (409) 880-8743.
1.12 ELIGIBLE RESPONDENTS: Only individual firms or lawfully formed business organizations may apply (this does not preclude a Respondent from using consultants). The Owner will contract only with the individual firm or formal organization that submits a Qualification, Proposal, HSP and HCL.
1.13 VETERAN HEROES UNITED IN BUSINESS SUBMITTAL REQUIREMENTS: It is the policy of the Owner and each of its member Institutions, to promote and encourage contracting and subcontracting opportunities for service-disabled veterans, referred to as Veteran Heroes United in
Business (“VetHUB” or “VetHUBs”), in all contracts. Accordingly, specific plans and representations by Respondents that appear to facilitate the State’s commitment to supporting
VetHUB enterprises are required in the selection process. Failure to submit specific plans and representations regarding VetHUB utilization, or failure to address the subject at all, will be interpreted by the Selection Committee as an intention not to support the program and will disqualify the Respondent.
1.13.1 A VetHUB Subcontracting Plan (“HSP”) is required by Respondent as a part of the
Qualifications for “Design” A/E services.
RFQ for Design-Build Services (posted 11/09/2026) New Residence Hall at Lamar University in Beaumont, Texas
1.13.2 An HSP is not required by Respondents as part of the Qualifications for the “Builder’s” construction services. The HSP for construction services will be required by the selected
Respondent, upon bidding of construction services. Submit a VetHUB Commitment Letter
(“HCL”) to describe how Respondent will participate and demonstrate a good faith effort in achieving the Owner’s VetHUB goals.
1.13.3 A sample HCL is attached to this solicitation as Attachment A.
1.13.4 Submit one (1) original, one (1) hard copy, and two (2) electronic copies on a USB/flash drive in Adobe Acrobat PDF format, of the A/E’s VetHUB Subcontracting Plan (“HSP”) and Builder’s VetHUB Commitment Letter (“HCL”); in a separate sealed envelope apart from the Qualifications as stated in Section 1.5.4 of this RFQ.
1.13.5 The HSP information may be downloaded from the Texas State Comptroller’s website at the following URL link: VetHUBprogram@cpa.texas.gov
1.13.6 Questions regarding VetHUB HSP and HCL requirements can be directed to:
Jessica Jaeger
HUB Program Manager
Jessica.jaeger@lsco.edu
1.14 CERTAIN PROPOSALS AND CONTRACTS PROHIBITED: Under Section 2155.004, Texas
Government Code, a state agency may not accept a proposal or award a contract that includes proposed financial participation by a person who received compensation from the agency to participate in preparing the specifications or request for proposals on which the proposal or contract is based. All vendors must certify their eligibility by acknowledging the following statement, "Under Section 2155.004, Texas Government Code, the vendor certifies that the individual or business entity named in this bid or contract is not ineligible to receive the specified contract and acknowledges that this contract may be terminated and payment withheld if this certification is inaccurate." If a state agency determines that an individual or business entity holding a state contract was ineligible to have the contract accepted or awarded as described above, the state agency may immediately terminate the contract without further obligation to the vendor. This section does not create a cause of action to contest a proposal or award of a state contract.
1.15 SALES AND USE TAXES: Section 151.311, Texas Tax Code, permits the purchase free of state sales and use taxes of tangible personal property to be incorporated into realty in the performance of a contract for an improvement to realty for certain exempt entities that include the Owner. The section further permits the purchase tax-free of tangible personal property (other than machinery or equipment and its accessories and repair and replacement parts) for use in the performance of such a contract if the property is "necessary and essential for the performance of the contract" and
"completely consumed at the job site. "In addition, the section permits the purchase tax-free of a tangible service for use in the performance of such a contract if the service is performed at the job site and if "the contract expressly requires the specific service to be provided or purchased by the person performing the contract" or "the service is integral to the performance of the contract."
1.16 CERTIFICATION OF FRANCHISE TAX STATUS: Respondents are advised that the successful
Respondent will be required to submit certification of franchise tax status as required by State Law
(Texas Tax Code Chapter 171). The contractor agrees that each subcontractor and supplier under contract will also provide a certification of franchise tax status.
RFQ No. 758-27-05037 https://comptroller.texas.gov/purchasing/vendor/hub/forms.php
1.17 DELINQUENCY IN PAYING CHILD SUPPORT: Under Section 231.006, Texas Family Code, the vendor or applicant certifies that the individual or business entity named in this contract, bid, or application is not ineligible to receive the specified grant, loan, or payment and acknowledges that this contract may be terminated and payment may be withheld if this certification is inaccurate.
1.18 STATE REGISTRATION OF ARCHITECTURE FIRMS: Respondents are advised that the Texas
Board of Architectural Examiners requires that any firm or business entity providing architectural services to the public, other than a sole proprietor doing business under his/her name, must annually register information regarding the firm or business entity with the Texas Board of Architectural
Examiners. Texas Board of Architectural Examiners. 505 East Huntland Drive, Suite 350, Austin, Texas 78752, telephone (512) 305-9000, has jurisdiction over individuals licensed under the
Architects’ Registration Law, Chapter 1051, Texas Occupations Code.
1.19 STATE REGISTRATION OF ENGINEERING FIRMS: Respondents are advised that the Texas
Board of Professional Engineers requires that any entity providing engineering services to the public must register with the Texas Board of Professional Engineers. An entity is defined as a sole proprietorship, firm, partnership, corporation, or joint stock association.
1.20 REQUIRED NOTICES OF WORKERS' COMPENSATION INSURANCE COVERAGE: The
Texas Workers' Compensation Commission has adopted a new rule, Texas Administrative Code
Title 28, Part 2, Chapter 110, Subchapter B, Rule 110.110, relating to REPORTING
REQUIREMENTS FOR BUILDING OR CONSTRUCTION PROJECTS FOR
GOVERNMENTAL ENTITIES. The rule implements sec. 406.096, Texas Labor Code, which requires workers' compensation insurance coverage for all persons providing services on a building or construction project for a governmental entity. The requirements of the rule are set forth in the
Uniform General and Supplementary General Conditions of The Texas State University System
Building Construction Contracts.
1.21 INSURANCE REQUIREMENTS: Bonds and insurance requirements are provided in Article 5 of the Uniform General Conditions and in the Owner’s Standard Contractor Contract as denoted in
Article 1.3 of this RFQ/P. The Owner intends to provide Builders Risk insurance coverage for this
Project.
1.22 PREVAILING WAGE RATE DETERMINATION: Respondents are advised that the Texas
Prevailing Wage Law will be administered. The penalty for violation of prevailing wage rates has been increased from $10.00 per underpaid worker per day or portion thereof to $60.00. The
Prevailing Wage Rate for Jefferson County, Texas, can be found on the following website:
https://sam.gov/wage-determinations
1.23 NONDISCRIMINATION: In their execution of this agreement, Respondent, consultants, their respective employees, and others acting by or through them shall comply with all federal and state policies and laws prohibiting discrimination, harassment, and sexual misconduct. Any breach of this covenant may result in termination of this agreement.
1.24 NON-BOYCOTT ISRAEL VERIFICATION: To the extent required in Chapter 271, Texas
Government Code, Respondent hereby certifies that it does not boycott Israel and will not boycott
Israel during the term of the Agreement. ”Boycott Israel” shall have the meaning set forth in Section
808.001, Texas Government Code.
1.25 CYBERSECURITY TRAINING PROGRAM: Pursuant to Section 2054.5192, Texas Government
Code, Design/Build firm and its subcontractors, officers, and employees, who are provided credentials granting access to Institution’s computer system also known as Institution’s information
RFQ for Design-Build Services (posted 11/09/2026) New Residence Hall at Lamar University in Beaumont, Texas
RFQ No. 758-27-05037 https://sam.gov/wage-determinations system, must complete a cybersecurity training program certified under Section 2054.519, Texas
Government Code as selected by the Institution. The cybersecurity training program must be completed during the term and any renewal period of the Agreement. Design/Build firm shall verify in writing completion of the program to the Institution within the first thirty (30) calendar days of the term and any renewal period of the Agreement. Failure to comply with the requirements of this section are grounds for termination for cause of the Agreement.
1.26 CERTIFICATION REGARDING BUSINESS WITH CERTAIN COUNTRIES AND
ORGANIZATIONS: Pursuant to Subchapter F, Chapter 2252.152, Texas Government Code, Respondent hereby certifies it is not engaged in business with Iran, Sudan, or a foreign terrorist organization. Respondent acknowledges the Agreement may be terminated and payment withheld if this certification is inaccurate.
1.27 FIREARM ENTITIES AND TRADE ASSOCIATIONS DISCRIMINATION: Pursuant to
Chapter 2274, Texas Government Code, Respondent verifies that (i) does not have a practice, policy, guidance, or directive that discriminates against a firearm entity or firearm trade association;
and (ii) will not discriminate during the term of the Agreement against a firearm entity or firearm trade association.
1.28 ENERGY COMPANY BOYCOTTS : Pursuant to Chapter 2274, Texas Government Code, Respondent certifies that it (i) does not boycott energy companies as defined in Section 809.001
(1)(a) Texas Government Code (i.e., fossil fuel companies); and (ii) will not boycott energy companies during the term of the Agreement.
1.29 VACCINE PASSPORT PROHIBITION: Pursuant to Section 161.0085, Texas Health and Safety
Code (as enacted in SB 968 in the 87th Regular Legislative Session [2021]), Respondent hereby certifies that it does not require its customers to provide any documentation certifying the customer’s COVID-19 vaccination or post-transmission recovery on entry to, to gain access to, or to receive service from Respondent’s business. Respondent acknowledges that such a vaccine or recovery requirement would make Respondent ineligible for a state-funded contact and shall be grounds for termination of this Agreement for cause.
1.30 CRITICAL INFRASTRUCTURE AFFIRMATION: Pursuant to Section 2274.0102, Texas
Government Code, Respondent certifies that neither it nor its parent company, nor any affiliate of
Respondent or its parent company, is (i) majority owned or controlled by citizens or governmental entities of China, Iran, North Korea, Russia, or any other country designated by the Governor under
Section 2274.0103, Texas Government Code, or headquartered in any of those countries.
1.31 HARDENING OF TEXAS’S CRITICAL INFRASTRUCTURE. Pursuant to Executive Order
GA-48 (2024), Contractor certifies that it, and, if applicable, any of its holding companies or subsidiaries, is not:
1.31.1 Listed in Section 889 of the 2019 National Defense Authorization Act (“NDAA”); or
1.31.2 Listed in Section 1260H of the 2021 NDAA; or
1.31.3 Owned by the government of a country listed on US Department of Commerce’s foreign adversaries list under 15 C.F.R. Section 791.4; or
1.31.4 Controlled by any governing or regulatory body located in a country on the US Department of Commerce’s foreign adversaries list under 15 C.F.R. Section 791.4.
SECTION 2 – EXECUTIVE SUMMARY
2.1 HISTORICAL BACKGROUND: Lamar University was established in Beaumont, Texas, in 1923 and relocated to its present campus in the early 1940s. As the institution transitioned into a four-year university, the campus expanded significantly, particularly during the 1950s and 1960s, with the addition of numerous facilities to support its growing academic programs and student population. Today, the university’s established campus infrastructure reflects decades of development, creating an ongoing need for facility renewal, modernization, and infrastructure improvements to support university operations.
2.2 MISSION STATEMENT: Lamar University strives to educate leaders, demonstrate excellence in student learning and career readiness, and pursue research with relevance.
2.3 PROJECT DESCRIPTION, BUDGET, AND SCOPE: Lamar University plans to develop one approximately 240,000 gross square-foot residence hall providing approximately 1,000 student beds, primarily in traditional double room configuration, with communal bathrooms, all subject to final programming confirmation. The Project includes shared study and amenity spaces, building systems, technology and security, site and utility improvements, and coordination of owner-furnished furniture.
2.3.1 Project design requirements can be found in the Design Criteria Package included as
Attachment B on ESBD.
2.3.2 The total Design/Build Budget Limitation (“DBBL”) for the Project is: $113,400,000
2.3.3 The total Construction Cost Limitation (“CCL”) for the Project is: $105,000,000
2.4 PROJECT PLANNING SCHEDULE: Key Project planning schedule milestones are:
2.4.1 Owner publishes RFQ/P for D-B Services ........................................................ 11/09/2026
2.4.2 Mandatory Pre-Submittal Conference (10:30 a.m.) .......................................... 11/19/2026
2.4.3 RFQ submittal of questions deadline (12:00 p.m.) ........................................... 11/30/2026
2.4.4 Deadline for submittal of Qualifications, HCL and HSP (2:00 p.m.) ............... 12/08/2026
2.4.5 Respondents name read aloud at Lamar University .......................................... 12/08/2026
2.4.6 Owner selects shortlisted Respondents for interview (if required) ................... 01/12/2027
2.4.7 Interview of shortlisted Respondents (if required) ............................................ 01/21/2027
2.4.8 Owner issues request for phase two information (to short-listed firms) ........... 01/27/2027
2.4.9 Deadline for submittal of phase two information (2:00 p.m.) ........................... 02/04/2027
2.4.10 Owner selects top ranked Respondent .............................................................. 02/08/2027
2.4.11 Owner commences negotiations ........................................................................ 02/15/2027
2.4.12 Owner and Respondent agree to terms of the D-B Agreement ......................... 03/15/2027
2.4.13 Execute D-B Agreement ................................................................................... 03/19/2027
2.4.14 Notice to Proceed for Design/Pre-Construction Services ................................. 03/22/2027
2.4.15 Board of Regents approval of Design Development Submittal ........................ 08/12/2027
2.4.16 Owner approves Guaranteed Maximum Price Proposal ................................... 08/16/2027
2.4.17 Notice to Proceed for Construction Phase issued .............................................. 08/23/2027
2.4.18 Construction Documents complete ................................................................... 10/01/2027
2.4.19 Owner accepts Substantial Completion of Construction ................................... 06/01/2029
2.4.20 Final Completion ............................................................................................... 07/05/2029
2.4.21 Occupancy ......................................................................................................... 08/03/2029
The schedule of events presented above represents a basic timeline for the Project. A final Project timeline will be developed with the Owner and Design/Build firm at a later time. The Owner can be expected to work with the Design/Build firm to validate and improve on this initial schedule.
2.5 OWNER’S SPECIAL CONDITIONS: The Owner requires full compliance with specification
Division 0: Contract Requirements and Division 1: General Requirements, which will be integrated into the specifications for the Project and become part of the Contract. These specification sections shall be a part of the Design/Build Agreement. The sections may be viewed on the Owner’s website at: https://www.tsus.edu/offices/finance/capital-projects.html
SECTION 3 – REQUIREMENTS FOR STATEMENT OF QUALIFICATIONS
Respondents shall carefully read the information contained in the following criteria and submit a complete statement of Qualifications responding to all questions in Section 3 formatted as directed in Section 5.
Incomplete Qualifications will be considered non-responsive and subject to rejection. Qualifications shall constitute up to Fifty (50%) of the total Respondent evaluation score.
3.1 CRITERION ONE: RESPONDENT’S ABILITY TO PROVIDE DESIGN/BUILD SERVICES:
(Criterion Weight: 5%)
3.1.1 Provide a brief history of Respondent’s firm.
3.1.2 Provide the following information on your firm for the past five (5) fiscal years:
3.1.2.1 Volume:
3.1.2.1.1 Annual number, value, and percent change of contracts in Texas per year
3.1.2.1.2 Annual number, value, and percent change of contracts nationally per year
3.1.2.2 Revenues: Annual revenue totals and percent change per year
3.1.2.3 Bonding:
3.1.2.3.1 Total bonding capacity
3.1.2.3.2 Available bonding capacity and current backlog.
3.1.3 Attach a letter of intent from a surety company indicating ability to bond Respondent for the entire construction cost of the Project. The surety shall acknowledge that the
Respondent may be bonded for each stage/phase of the Project (if applicable), with a potential maximum construction cost of One Hundred Five Million Dollars
($105,000,000). Bonding requirements are set forth in Article 17 of the Agreement, the
2022 Uniform General Conditions for Construction Contracts, and Special Conditions, if any.
3.1.4 State whether any firm of the Respondent’s team is currently for sale or involved in any transaction to expand or to become acquired by another business entity. If so, explain the impact both in organization and company direction.
3.1.5 Provide details of any past or pending litigation, or claims filed, against any firm of the
Respondent’s team that may affect its performance under an Agreement with the Owner.
3.1.6 State whether any firm of the Respondent’s team is currently in default on any loan agreement or financing agreement with any bank, financial institution, or other entity. If so, specify date(s), details, circumstances, and prospects for resolution.
3.1.7 State whether Respondent has ever failed to complete any work which it was awarded.
RFQ for Design-Build Services (posted 11/09/2026) New Residence Hall at Lamar University in Beaumont, Texas
RFQ No. 758-27-05037 https://www.tsus.edu/offices/finance/capital-projects.html
3.2 CRITERION TWO: QUALIFICATIONS OF DESIGN/BUILD TEAM AND THE EXECUTION
OF SERVICES: (Criterion Weight: 20%)
3.2.1 Provide resumes of all Respondent’s team members, including architectural, engineering, technical consultants, construction contractors, and subcontractors, that will be dedicated to and directly involved in the Project, including their experience with similar projects, definition of that person’s specific role in the Pre-Construction and Construction phases for the Project, the number of years with their respective firms, and their cities of residence.
3.2.2 For each of the proposed Respondent’s team members identified in 3.2.1, describe their responsibilities in each of the representative projects presented in 3.3, and compare them with their anticipated responsibilities in this Project. List other projects on which the
Respondent’s team members have worked together.
3.2.3 Describe, in graphic and written form, the proposed Project organizational chart indicating assignments and lines of authority and communication for each team member to be directly involved in the Project. Indicate the estimated percent of time these team members will be involved in the Project for Pre-Construction, Construction, Close-Out, and Warranty services.
3.2.4 Describe Respondent’s management and execution plan for providing Pre-Construction
Phase Services required for this Project.
3.2.5 Describe what Respondent perceives as the critical issues for this Project, whether in the
Pre-Construction or Construction Phase.
3.2.6 Describe Respondent’s procedures, objectives, and personnel responsible for reviewing design and Construction Documents and for providing feedback regarding cost, schedule, and constructability to the Owner.
3.2.7 Describe Respondent’s Bid/Proposal Package Strategy for completion of the Construction
Documents and for procuring the work from subcontractors, vendors, suppliers, etc.
3.2.8 Describe Respondent’s constructability program for this Project and how it will be implemented.
3.2.9 Describe Respondent’s philosophy for maximizing Project scope for the Owner during Pre-
Construction services, minimizing risk, and identifying when savings can be returned to the Owner during construction.
3.2.10 For Pre-Construction and Construction services, provide examples of records, reports, monitoring systems, and information management systems Respondent will use on this
3.2.11 Declare if Respondent, or any other company within the same holding group of companies, desires to self-perform work on this Project, and describe the method for determining itself as the “best value” through a competitive proposal process.
3.2.12 Describe Respondent’s approach to coordinating inspections and approvals with the Texas
Department of Licensing and Regulation regarding Texas Accessibility Standards, the
State Fire Marshal and other authorities having jurisdiction over the Project.
3.3 CRITERION THREE: RESPONDENT’S PAST PERFORMANCE ON REPRESENTATIVE
DESIGN/BUILD PROJECTS: (Criterion Weight: 20%)
3.3.1 Identify and describe the Respondent’s team’s past experience for providing Design/Build services that are MOST RELATED TO THIS PROJECT within the last five (5) years.
Provide not less than three (3) but not more than five (5) examples. List the projects in order of priority, with the most relevant project listed first. Provide the following information for each project listed:
3.3.1.1 Project name, location, description, and delivery method if other than
Design/Build
3.3.1.2 Photographic color images of exterior, interior, and floor plans and site plans if applicable
3.3.1.3 Construction cost estimates at Design Development, final GMP amount and final construction cost. Explain the reasons for any deviations.
3.3.1.4 Final project size in gross square feet
3.3.1.5 Type of construction (new, renovation, or expansion)
3.3.1.6 Notice to Proceed date for Pre-Construction Services
3.3.1.7 Originally planned and actual Notice to Proceed, Substantial Completion, and
Final Payment dates for Construction Services. Explain reasons for any deviation.
3.3.1.8 Name of project manager (individual responsible to the owner for the overall success of the project)
3.3.1.9 Name of project superintendent(s) (individual responsible for coordinating the day-to-day work)
3.3.1.10 Names of mechanical, plumbing, electrical, and other major subcontractors
3.3.2 References (for each project listed above, identify the following):
3.3.2.1 The owner’s name and representative who served as the day-to-day liaison during the design and construction phases of the project, including telephone number and email address
3.3.2.2 The A/E’s name and representative who served as the day-to-day liaison during the project, including telephone number and email address
3.3.2.3 Length of business relationship with the owner
References shall be considered relevant based on specific project participation and experience with the Respondent. The Owner may contact references during any part of this process. The Owner reserves the right to contact any other references at any time during the RFQ process.
3.3.3 Has Proposer worked with The System or one of the member Institutions in the past five
(5) years? If “yes,” state The System contact (or member Institution name, department name, and department contact) and provide a brief description of work performed.
3.4 CRITERION FOUR: RESPONDENT’S ABILITY TO ESTABLISH BUDGETS AND
CONTROL COSTS: (Criterion Weight: 15%)
3.4.1 Describe Respondent’s process for validating the Owner’s project budget at the beginning of pre-construction. Explain how Respondent will evaluate the proposed building program, gross square footage, bed count, site development, escalation, market conditions, contingencies, allowances, and other major cost factors to determine whether the Project can be delivered within the established budget. Describe how any identified budget gap
RFQ for Design-Build Services (posted 11/09/2026) New Residence Hall at Lamar University in Beaumont, Texas will be communicated and addressed while maintaining the Owner’s required bed count, operational requirements, and quality expectations.
3.4.2 Describe Respondent’s approach to maximizing value within the established Project
Budget. Identify strategies for optimizing building efficiency, gross square feet per bed, structural and MEP systems, repetitive unit design, material selections, and procurement without compromising durability, life safety, maintainability, or the student residential experience.
3.4.3 Identify a maximum of three (3) projects from Section 3.3 of this RFQ, with GMP contracts, and the amount of savings (if any) returned to the owner.
3.5 CRITERION FIVE: RESPONDENT’S ABILITY TO MEET SCHEDULES: (Criterion Weight:
15%)
3.5.1 Describe Respondent’s approach to developing and managing the Project schedule to achieve the Owner’s required Fall semester occupancy. The schedule shall recognize that failure to achieve occupancy prior to student move-in may result in significant operational disruption and loss of housing revenue. Identify the milestones Respondent considers critical to protecting this date from design initiation through occupancy.
3.5.2 For up to three representative student housing or similar occupancy-driven projects, provide the planned and actual dates for Notice to Proceed, Substantial Completion, occupancy/move-in, and Final Payment. Identify any schedule deviations, explain the reasons for those deviations and any recovery measures implemented, and confirm whether each facility was fully operational by the required occupancy date.
3.5.3 Describe Respondent’s experience with Critical Path Method (“CPM”) scheduling. From any of three (3) of the projects listed in response to Section 3.3 of this RFQ, provide one
(1) sample of the monthly schedule reports, including identified milestones, and any schedule recovery plans.
3.5.4 Provide a simple CPM Milestone schedule on how Respondent perceives this Project could be built. Identify specific critical process, phases, milestones, approvals, and procurements anticipated. Include the ten percent (10%) total project float that will be required in the critical path during the Construction Phase. If Respondent proposes to improve the schedule, describe the impact on quality of services, materials or workmanship that may occur.
3.6 CRITERION SIX: RESPONDENT’S KNOWLEDGE OF CURRENT CONSTRUCTION
METHODOLOGIES, TECHNOLOGIES, QUALITY, AND BEST PRACTICES: (Criterion
Weight: 10%)
3.6.1 Describe Respondent’s quality assurance program. Explain the methods used to ensure quality control during the Design and Construction phases of a project. Provide a specific example from one (1) of the representative projects, listed in response to Section 3.3 of this
RFQ, of how Respondent’s quality control program overcame a difficult design or constructability issue and resulted in higher quality project.
3.6.2 Describe Respondent’s procedures for implementing industry’s “best practices” as defined by the Construction Industry Institute or similar organizations for:
3.6.2.1 Establishing and tracking project objectives.
RFQ for Design-Build Services (posted 11/09/2026) New Residence Hall at Lamar University in Beaumont, Texas
3.6.2.2 Using project scope definition resources (i.e., Project Definitions Rating Index
(PDRI)) in order to obtain complete and accurate design and construction documents from the A/E.
3.6.2.3 Partnering.
3.6.2.4 Cost tracking.
3.6.2.5 Change (order) management systems.
3.6.2.6 Building systems commissioning including coordination with the Owner’s commissioning agent.
3.6.2.7 Total quality management for each phase of the Project, including coordinating with the Owner’s project inspectors, testing, training, close-out, and warranty service.
3.6.3 Describe Respondent’s implementation of a quality control process for this Project during the Design Development stage through completion of Construction Documents stage.
3.6.4 Describe how Respondent’s quality control team will measure the quality of construction and commissioning performed by all trades, but in particular, by mechanical and electrical subcontractors and how Respondent will address non-conforming work.
3.6.5 Describe Respondent’s knowledge of the subcontractor and supplier market applicable to this Project. Identify major trades where Respondent anticipates potential concerns related to competition, labor availability, capacity, escalation, or procurement duration and describe how those risks will be addressed.
3.7 CRITERION SEVEN: RESPONDENT’S ABILITY TO IDENTIFY AND RESOLVE
PROBLEMS: (Criterion Weight: 5%)
3.7.1 Describe Respondent’s understanding of the administrative challenges and opportunities associated with providing Design, Pre-Construction, and Construction services for Owner on this Project, and Respondent’s strategy for addressing these issues.
3.7.2 Understanding the schedule limitations, provide an analysis of the Owner’s project planning schedule in Section 2.4 of this RFQ, describe Respondent’s plan for communicating design, constructability, phasing, value engineering and other budget options in a form that will quickly facilitate the Owner’s decision making.
3.7.3 For any combination of three (3) projects listed in response to Section 3.3 of this RFQ, describe any conflicts with the Owner, consultants, A/E, or subcontractors and describe the methods used by the Respondent to resolve those conflicts.
3.8 CRITERION EIGHT: RESPONDENT’S ABILITY TO MANAGE CONSTRUCTION SAFETY
RISKS: (Criterion Weight: 5%)
3.8.1 Briefly describe Respondent’s approach for anticipating, recognizing, and controlling safety risks and note the safety resources that Respondent provides for each project’s safety program.
3.8.2 Describe the level of importance for enforcement and support of project safety that
Respondent includes in performance evaluations for superintendents and project managers.
3.8.3 Identify the proposed safety management team members for construction services. Include their previous titles, duties, city(s) of residence, experience, and expertise; also, their
RFQ for Design-Build Services (posted 11/09/2026) New Residence Hall at Lamar University in Beaumont, Texas intended percent of monthly involvement and duration for this Project. Include all details necessary to demonstrate the credentials required by project safety specifications.
3.8.4 Describe the methodology, including…
This is the start of the file's text. The full file is on GovTribe.