ESBD_544479_1785438179498_02-3496 CMAR RFP Information Sheet.docx
DOCX document 17 KB Posted
- Solicitation number
- TAMUS-RFP-02-3496
- Issued by
- Texas
About this file
This is a Construction Manager at Risk (CMAR) Request for Proposals Information Sheet issued by the Texas A&M University System Office of Facilities Planning & Construction on behalf of the Board of Regents for the Bright-Slocum Center Renovations project in College Station, Texas. The RFP seeks a qualified CMAR firm to provide pre-construction services including constructability guidance, cost estimates, and construction schedules, followed by a Guaranteed Maximum Price (GMP) and complete construction services. The project focuses on renovating a majority of the first floor with four primary goals: improving facility circulation, renovating player-centric spaces, upgrading player support spaces, and enhancing public spaces. Specific improvements include creating two new corridors, reconfiguring the athletic training area, constructing a new hydrotherapy room, updating the locker room, creating a new player's lounge, relocating staff facilities, and upgrading the lobby and team meeting room. The proposal submission deadline is 2:00 p.m. Central Time on Thursday, August 20, 2026, with submissions required through the eBuilder platform. All addendums will be posted within eBuilder, and respondents should direct questions to Sam Lampe at the Texas A&M University System Office of Facilities Planning & Construction.
The project Planning Amount is $52,000,000, with an Amount Available for Construction Contract (AACC) of $34,092,767; the remaining balance covers fees, furnishings, other work, miscellaneous expenses, and contingencies. The selection process will rank respondents based on best value criteria as published in the RFP, with potential interviews at the Owner's discretion. Respondents must complete the State of Texas Subcontracting Plan (SP) form, and guidance is available through an online tutorial to ensure accuracy. The RFP is conducted in accordance with Texas Education Code 51.782(e), and all RFP documents must be accessed and answered within eBuilder using the provided link. Late submissions will not be accepted under any circumstances.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The Texas A&M University System RFP-02-3496 - CMAR Request for Proposals Bright-Slocum Center Renovations Texas A&M University College Station, Texas The Texas A&M University System Office of Facilities Planning & Construction (FP&C) on behalf of the Board of Regents of The Texas A&M University System (Owner) and Texas A&M University, is accepting proposals for the selection process to enter into a contract with a Construction Manager at Risk (CMAR) firm to provide pre-construction services such as constructability guidance, cost estimates, and construction schedules; provide a Guaranteed Maximum Price (GMP); and perform complete construction services consistent with the CMAR construction delivery process as utilized by The Texas A&M University System for the Bright-Slocum Center Renovations (#02-3496) for Texas A&M University in College Station, Texas.
The Bright-Slocum Center Renovations project will focus on four main goals for renovation of a majority of the first floor: Improving the overall circulation of the facility, renovating player-centric spaces, renovating player support spaces, and renovating public spaces. In support of these goals, the project will create two new corridors, one facilitating flow to and from Kyle Field, and the second will provide a closer path for the players to access the Davis Center on the south edge. The renovation of the player-centric spaces will upgrade their day-to-day experience of the facility. This includes a reconfiguration of the athletic training area, a new hydrotherapy room with a focus on post practice recovery, an updated locker room with larger lockers and new finishes, and a new player's lounge to provide a space for team bonding, mental recovery and around-the-clock nutrition. The player support spaces will include the reconfiguration of the equipment room and the relocation of the staff and student worker locker rooms. A preceding project will relocate the coaches' locker rooms to spaces on the second floor. The renovation of the public spaces includes such spaces as the lobby, giving all visitors a more powerful first impression of the facility, as well as providing opportunities for donor recognition and revenue-generating experiences within the public realm, including upgraded finishes of the lobby restrooms and the team meeting room.
The Planning Amount for the project is $52,000,000, which includes an Amount Available for Construction Contract (AACC) of $34,092,767. Fees, furnishings, other work, miscellaneous expenses, and contingencies make up the balance of the Planning Amount.
This RFP is the process for selecting a CMAR firm for the project as provided by Texas Education Code 51.782(e). The RFP provides the information necessary to prepare and submit Proposals including fee proposals and general conditions prices. The Owner will rank the Respondents in the order that they provide the “best value” for the Owner based on the published selection criteria and on the ranking evaluations. Interviews of CMAR firms may follow at the Owner’s option.
** The RFP package/documents must be accessed and responded to within e‐Builder. The following link provides access to the RFP package/documents:
https://tinyurl.com/ycx9rsaj State of Texas Subcontracting Plan (HSP) Guidance: To assist respondents in completing the required State of Texas Subcontracting Plan (SP) form, the Office of Procurement & Business Services has developed a brief tutorial addressing common errors and questions. The video may be accessed using the following link: How to Complete the State of Texas Subcontracting Plan (SP) Form. Vendors are strongly encouraged to review the tutorial before submitting their SP form to help ensure accuracy and completeness. Questions regarding the SP requirements may be directed to so-hubprogram@tamus.edu.
Follow the instructions on the link to get registered within e‐Builder. All addendums, if any will be posted within this e‐Builder site and NOT on the ESBD posting.
**Important note regarding sharing the link for this eBuilder site: ONLY THE ABOVE LINK should be shared/provided for bidders to access documents. Do not share the URL from the web browser once E-builder is accessed.
Deadline: FP&C will accept proposals uploaded to e‐Builder until 2:00 p.m. Central Time, Thursday, August 20, 2026. e-Builder will not allow uploads after the deadline. It is the responsibility of the respondent to ensure the qualification submission is uploaded prior to the deadline. No exceptions will be allowed for late submittals.
Any questions regarding this RFP shall be directed to:
Sam Lampe The Texas A&M University System Office of Facilities Planning & Construction Phone: (210) 336-8837 E-mail: Slampe@projectcontrol.com
File details come from the government source that posted it. Updated .