About this file
This is a Scope of Work document for culinary plumbing services in Texas. The document outlines requirements for plumbing work related to culinary facilities, detailing the specific tasks, deliverables, and performance standards that the selected contractor must meet. The scope includes installation, maintenance, and repair services for plumbing systems in kitchen and food service environments. The document establishes the technical specifications, quality standards, and compliance requirements that bidders must understand to submit competitive proposals. Specific response dates, due dates, site visit schedules, and bidder conference information should be referenced in the associated contract opportunity posting for complete timeline details.
Pricing terms, contract duration, renewal options, set-asides, incumbent contractor information, and funding sources are not detailed in this scope of work document. For comprehensive information regarding compensation structure, budget allocation, disadvantaged business enterprise considerations, and other financial or administrative requirements, refer to the main contract opportunity announcement and any supplemental procurement documents issued by the contracting agency in Texas.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ESBD_526171_1781196232818_GID Plumbing UpgradeIFB.docx | DOCX document | |
| ESBD_526171_1781196284242_Giddings culinary plumbing floorplan.jpg | JPG image |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
We are looking to upgrade plumbing/fixtures in a classroom at our Giddings State Juvenile Correctional Facility. We will need the following:
1) Install 40 Gallon electric water heater, water heater stand, and drain pan. tie into existing water lines above ceiling for supply. Make proper connections for T&P also run drain line for drain pan.
2) Run water lines to new construction sinks, dishwashers, washing machine outlet box and Ice Machine.
3) Install 2 sinks (Standart Pro 32” single basin 16-gauge stainless steel kitchen sink for undermount installations. Basin rack and strainer included) and faucets (commercial style, gooseneck, single hole) into new construction counter tops.
4) Run all necessary drains and vents inside building. Exit building with drain line provide clean outs and tie new drain line into existing sewer line. Approximately 40’ of asphalt will need to be cut and/or trenched trough to get to main sewer line for tie in. Asphalt will need to be repaired after completion of sewer line tie in.
5) Vendor will provide all plumbing fixtures and connections; Owner will provide and install dishwashers at a later date.
6) Install vent for Dryer through wall.
All Plumbing must meet all State and Local UPC and IPC codes.
Attached is a drawing of approximate locations of existing sewer line, new drain and sewer lines, location of new water heater, washing machine outlet box, ice machine and sinks.
Contractors are recommended to do a site visit before placing bid. Contact Maintenance Supervisor Robbie Toland to set up site visit. (979)716-8275 Please provide bid and details of material and parts you plan to use. Giddings State Juvenile Correctional Facility is a secure facility and everyone entering will have to have an approved background check completed before they can enter.