ESBD_494342_1773949732479_2026-03-19 CBBEP Deadman Island Addendum 1.pdf
PDF 6 MB Posted
- Solicitation number
- 2439
- Issued by
- Angelina County, Texas
About this file
This addendum modifies the contract documents for the Deadman Island Restoration and Protection project, a coastal restoration initiative managed by the Coastal Bend Bays & Estuaries Program (CBBEP) in Aransas Bay, Texas, with engineering services provided by HDR Engineering, Inc. The project encompasses base work and five additive bid options for island restoration, including the placement of approximately 13,300 cubic yards of imported sand fill to create approximately 3.2 acres of island, construction of a 1,750 linear foot breakwater, installation of daybeacons, and aerial photography. Additive bids include raising the breakwater crest elevation from +3.5 feet to +4.0 feet and further to +4.5 feet, placement of approximately 1,600 cubic yards of additional sand material, approximately 2,100 cubic yards of sandy loam material, construction of a 650 linear foot grassed reed oyster reef, and installation of an additional daybeacon. The engineer's estimate for base work ranges from $4,700,000 to $5,400,000. CBBEP anticipates providing notice of intent to award in April 2026 and contract award in July 2026, with all work required to be completed prior to November 31, 2026. The addendum revises the proposal form, specification 01 11 00 (Summary of Work), and construction drawings dated March 2, 2026, replacing them with updated versions dated March 16, 2026, with modifications to Item 1.5 (Sand Fill), Item 2.3 (Raise Crest of Sand Fill), and Item 2.4 (Sandy Loam Fill).
Unit prices submitted by contractors must represent fully installed items and include all costs for material, supervision, labor, profit, overhead, and subsidiary costs, with extended prices calculated by multiplying quantity times unit price. Additive Bid No. 2 (raising breakwater crest from +4.0 feet to +4.5 feet) may only be awarded in conjunction with Additive Bid No. 1. The contract includes standby time provisions that may be activated at CBBEP's discretion through change order, with payment based on actual rental rates of equipment and labor rates of personnel on site or stated rates, whichever is less, covering daily rates (up to 6 days) and weekly rates (up to 4 weeks). Upon notification of award, the selected contractor must execute the formal contract within ten calendar days and provide a Performance Bond and Payment Bond as required. A bid bond equal to 5% of the highest amount bid is required, with provisions becoming the property of CBBEP as liquidated damages if the contract and bonds are not executed within the specified timeframe. Contractors must acknowledge receipt of the addendum on the proposal form and incorporate all changes and modifications into their bids.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HDR Engineering, Inc. 10426649
Addendum No. 1
COASTAL BEND BAYS & ESTUARIES PROGRAM
ADDENDUM NO. 1
SPECIAL PROVISIONS, SPECIFICATIONS AND FORMS OF CONTRACTS AND BONDS
FOR DEADMAN ISLAND RESTORATION AND PROTECTION
MARCH 19, 2026
TO ALL POTENTIAL BIDDERS:
This addendum shall be considered part of the Contract Documents and is issued to change, amplify, or delete from or otherwise explain the drawings and specifications where provisions of this addendum differ from those of the original contract documents. This addendum shall have precedence over the original drawings and specifications and shall govern.
Respondents are hereby notified that they shall incorporate this addendum in their bid, and it shall be construed that the Contractor's Bid shall reflect with full knowledge, all items, changes and modifications to the Contract Documents herein specified.
RESPONDENTS SHALL ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPACE
PROVIDED ON THE PROPOSAL FORM.
SPECIFICATIONS
1. Replace Proposal Form in its entirety with the attached revision. Item 1.5, “Sand Fill,” Item
2.3, “Raise Crest of Sand Fill from +3.5 feet to +4.0 feet,” and Item 2.4, “Sandy Loam Fill,” were modified.
2. Replace Specification 01 11 00, “Summary of Work,” in its entirety with the attached revision.
Paragraph 1.5, B was amended.
3. Page 2 of section 01 22 00, “Measurement and Payment” is duplicated between the end of Section 01 22 00 and the beginning of Section 01 26 00, “Contract Modification Procedures.”
The duplicate page shall be disregarded.
PLANS
Replace Drawings dated 3/2/2026 with the attached Plans dated 3/16/2026. The title block is modified on all sheets, and Detail 1 on Sheet 03C-01 is modified.
ADDITIONAL INFORMATION
1. The following is for information only. Engineer’s estimate for the project is approximately
$4,700,000 to $5,400,000 for Base Work. Owner’s budgetary dollar amount is sufficient to award the Base Work within Engineer’s estimate.
HDR Engineering, Inc. 10426649
Addendum No. 1
END OF ADDENDUM NO. 1
OWNER: COASTAL BEND BAYS & ESTUARIES PROGRAM
ENGINEER: HDR ENGINEERING, INC.
ATTACHMENTS: Revised Proposal Form Revised Specification 01 11 00 Summary of Work Revised Plans
3/19/2026
Proposal
PROPOSAL
Coastal Bend Bays & Estuaries Program, Inc.
1305 N Shoreline Blvd, Suite 205
Corpus Christi, Texas 78401
Having carefully examined the drawings, specifications and contract documents for DEADMAN
ISLAND RESTORATION AND PROTECTION project the undersigned proposes to furnish all labor, equipment and materials necessary to complete all work for the following prices:
THIS SHEET MUST BE COMPLETELY FILLED OUT IN INK OR TYPEWRITTEN WITH ANY
NECESSARY SUPPLEMENTAL INFORMATION ATTACHED.
1. BASE BID
Item Description Quantity Unit Price Extended Price
1.1 Mobilization/Demobilization 1 LS $ ________________ $ ________________
1.2 Construction Surveys 1 LS $ ________________ $ ________________
1.3 Light-Loading Area Survey and Cleanup 1 LS $ ________________ $ ________________
1.4 Breakwater 1,750 LF $ ________________ $ ________________
1.5 Sand Fill 1 LS $ ________________ $ ________________
1.6 Daybeacons 6 EA $ ________________ $ ________________
1.7 Acceptance Aerial Photography 1 LS $ ________________ $ ________________
TOTAL BASE BID (Sum of Items 1.1 through 1.7): $
_____________________________________________________________________________ Dollars
2. ADDITIVE BIDS
Item Description Quantity Unit Price Extended Price
Additive Bid No. 1:
2.1 Raise Crest of
Breakwater from +3.5 feet to
+4.0 feet 1,750 LF $________________ $________________
Additive Bid No. 2:
2.2 Raise Crest of
Breakwater from +4.0 feet to
+4.5 feet 1,750 LF $ ________________ $ ________________
Additive Bid No. 3:
2.3 Raise Crest of Sand
Fill from +3.5 feet to +4.0 feet 1 LS $ ________________ $ ________________
Additive Bid No. 4:
2.4 Sandy Loam Fill 1 LS $ ________________ $ ________________
Additive Bid No. 5:
2.5 Oyster Reef 650 LF $ ________________ $ ________________
2.6 Additional Daybeacon 1 EA $ ________________ $ ________________
ADDITIVE BID NO. 2 WILL ONLY BE AWARED IN CONJUNCTION WITH ADDITIVE BID NO. 1.
UNIT PRICES ARE FOR FULLY INSTALLED ITEMS AND INDICATE ALL COSTS OF MATERIAL,
SUPERVISION, LABOR, PROFIT, OVERHEAD, AND SUBSIDIARY COSTS.
QUANTITY TIMES UNIT PRICE SHALL EQUAL EXTENDED PRICE.
CBBEP ANTICIPATES PROVIDING A NOTICE OF INTENT TO AWARD IN APRIL 2026 AND
PROVIDING CONTRACT AWARD IN JULY 2026. ALL WORK SHALL BE COMPLETED PRIOR TO
NOVEMBER 31, 2026.
3. STANDBY TIME
At any time during the contract performance period, CBBEP may issue a temporary stop work order and activate standby time provisions. If activated, standby time will be paid to the Contractor based on actual rental rates of equipment and labor rates of personnel on site during that time, or based on the stated rates, whichever is less:
3.1 Daily Rate (Up to 6 Days) Labor Rate $ /Day
Equipment Rate $ /Day
Total Daily Rate $ /Day
3.2 Weekly Rate (Up to 4 Weeks) Labor Rate $ /Week
Equipment Rate $ /Week
Total Weekly Rate $ /Week
CBBEP reserves the right to activate, or not to activate, standby time provisions, as it deems appropriate, in the form of a change order to the contract.
The undersigned hereby declares that they have visited the site and has carefully examined the plans, specifications and contract documents relating to the work, that they agree to do the work, and that no representations made by CBBEP are in any sense a warranty, but are mere estimates for the guidance of the Contractor.
Upon notification of award of contract, the undersigned will within ten (10) calendar days execute the formal contract and will deliver a Performance Bond (as required) for the faithful performance of this contract and a Payment Bond (as required) to insure payment for all labor and materials. The bid bond attached to this proposal, in the amount of 5% of the highest amount bid, is to become the property of
CBBEP in the event the contract and bonds are not executed within the time above set forth as liquidated damages for the delay and additional work caused thereby.
The undersigned further declares that they will provide all necessary tools and apparatus, do all the work and furnish all materials and do everything required to carry out the above mentioned work covered by this proposal, in strict accordance with the plans, specifications and contract documents and the requirements pertaining thereto, for the sum or sums above set forth.
Receipt of the following addenda is acknowledged (addenda number): __________________________
Respectfully submitted:
SIGNATURE
PRINT NAME
TITLE
COMPANY
ADDRESS
CITY, STATE, ZIP
TELEPHONE
FAX NUMBER
DATE
Project Number
10426649 SUMMARY OF WORK
01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
1. Location and description of Work and prior uses of the Site.
2. Construction Contracts for this Project.
3. Others retained by Owner for the Project.
4. Sequence and progress of Work.
5. Utility owners.
1.2 LOCATION AND DESCRIPTION OF WORK
A. The Work component at Deadman Island is within the Aransas Bay in Aransas County, Texas.
B. The Work component at Deadman Island is broadly described below, in accordance with the
Contract Documents, with all related appurtenances. Work shown on the Plans, or indicated in the Specifications, or indicated elsewhere in the Contract Documents is part of the Work, regardless of whether indicated below. The Work includes, but is not limited to, the following:
1. Base Work:
a. Placement of approximately 13,300 CY (neatline) of imported sand fill material for creation of approximately 3.2 acres of island.
b. Construction of a 1,750 LF breakwater for containment of the fill material.
c. Installation of 6 daybeacons around constructed island.
d. Aerial photography.
e. Construction surveying.
f. Light-loading Area Survey and Cleanup
2. Additive Bid No. 1:
a. Increasing the template of the breakwater
3. Additive Bid No. 2:
a. Additional increase of the template of the breakwater
4. Additive Bid No. 3:
a. Placement of approximately 1,600 CY (neatline) of imported sand material to increase the fill elevation.
5. Additive Bid No. 4:
a. Placement of approximately 2,100 CY (neatline) of imported sandy loam material.
6. Additive Bid No. 5:
a. Construction of a 650 LF GRR oyster reef
b. Install 1 additional daybeacon.
C. Contracting Method: The Project will be constructed under a single prime construction
Contract.
D. Hazardous Environmental Conditions: To the best of Owner’s knowledge, information, and belief, prior use of the Site excluded activities that may have created hazardous environmental conditions. Known surface and subsurface features at the site are described in the Plans and accompanying geophysical data in Appendix A.
1.3 CONSTRUCTION CONTRACTS FOR THIS PROJECT
A. Single Prime Construction Contract: The Contract requires all the Work for the Project not expressly allocated to Owner or others in the Contract Documents.
Project Number
10426649 SUMMARY OF WORK
01 11 00 - 2
1.4 OTHERS RETAINED BY OWNER FOR THE PROJECT
A. CBBEP’s Engineer:
1. CBBEP’s Engineer is identified in the Agreement.
2. CBBEP’s Engineer’s responsibilities for the Project, relative to Contractor, are indicated throughout the Contract Documents.
3. CBBEP’s Engineer will not furnish the services of a Resident Project Representative (RPR) for this project.
1.5 SEQUENCE AND PROGRESS OF WORK
A. General: The sequence of construction shall be determined by the Contractor, unless otherwise restricted by the Contract Documents. Work components within the project site shall follow the restrictions described in Section 1.5, B. The overall project construction shall be continuous from start to finish with no appreciable shut down periods.
B. Sequencing:
1. Incorporate sequencing of the Work into the Progress Schedule.
2. Sequencing Requirements for work components at Deadman Island:
a. Restrictions: The following construction sequence restrictions shall apply to the work for this project:
1) Prior to commencing construction,
a) Initial survey shall be conducted over all project areas where work will be performed.
b) Pre-Construction Hazard survey shall be performed over all areas where work will be performed.
c) Pre-Construction Aerial photographs shall be conducted prior to commencing any construction activities.
2) Breakwater construction shall be completed prior to placing island fill.
3) Breakwater final survey shall be completed, submitted, and accepted by Engineer prior to placement of island fill.
4) Acceptance Aerial photographs shall be conducted after completion of all construction activities.
1.6 UTILITY OWNERS
A. Utilities known to CBBEP’s Engineer and that may have Underground Facilities or other facilities in the vicinity of the Work are shown on the Plans.
B. Utilities and their owners indicated in the Contract Documents are for Contractor’s convenience.
Neither Owner nor CBBEP’s Engineer will be liable to Contractor or any utility owner for failure to indicate utility, its owner, or complete and correct contact information in the Contract
Documents where Contractor’s reasonable and ordinarily-exercised diligence would reveal the presence of the utility and its owner. Nothing in the Contract mitigates Contractor’s responsibilities under the General Conditions and Provisions; Section 35 00 01, “Construction
Surveying; and Laws and Regulations, including “call before you dig” regulations.
PART 2 - PRODUCTS - (NOT USED)
PART 3 - EXECUTION - (NOT USED)
END OF SECTION
I N D E X O F D R A W I N G S
Sheet Number Sheet Title
GENERAL
00G-00 COVER SHEET AND INDEX
00G-01 GENERAL NOTES, LEGENDS, AND SURVEY MAP
CIVIL
01C-01 EXISTING CONDITIONS
02C-01 PROJECT LAYOUT
02C-02 ENLARGED PROJECT LAYOUT
02C-03 CONSTRUCTION SURVEY PLAN
03C-01 TYPICAL SECTIONS AND DETAILS
04C-01 BREAKWATER AND REEF CROSS-SECTIONS
04C-02 BREAKWATER AND REEF CROSS-SECTIONS
04C-03 BREAKWATER CROSS-SECTIONS
05C-01 SAND FILL CROSS-SECTIONS
05C-02 SAND FILL CROSS-SECTIONS
05C-03 SAND FILL CROSS-SECTIONS
05C-04 SAND FILL CROSS-SECTIONS
C o n s t r u c t i o n D r a w i n g s F o r
COASTAL BEND BAYS &
ESTUARIES PROGRAM
HDR Engineering, Inc.
TBPELS Firm Registration No. F-754
DEADMAN ISLAND
RESTORATION AND PROTECTION
PROJECT
VICINITY
CORPUS CHRISTI SHIP CHANNEL
GULF OF AMERICA
CORPUS CHRISTI BAY
SAN
JOSE
ISLAND
PORT
ARANSAS
G
UL
F
IN
TR
AC
O
AS
TA
L W
AT
ER
W
AY
ROCKPORT
FULTON
ARANSAS
PASS
INGLESIDE
© 2024 Microsoft Corporation Earthstar Geographics SIO
ARANSAS BAY
HDR Project No.
10426649
Aransas Bay, Tx March 16, 2026
T E X A S
CBBEP Project No. 2339
GENERAL NOTES, LEGENDS, AND SURVEY MAP
00G-01.DWG
AS NOTED 00G-01
GENERAL LINE SYMBOLOGY
2,604,803.113,230,063.3
EASTINGNORTHING NAME
877 4513 H
MONUMENTS USED FOR SURVEY CONTROL
C2 SURVEY CONTROL POINT
4.5'
ELEVATION (NAVD88)
-15.3 2022 SPOT ELEVATION, FT
GENERAL NOTES:
1. AERIAL PHOTOGRAPH SHOWN WAS OBTAINED FROM TERRA FLIGHT AERIAL IMAGING, INC. DATED FEBRUARY 2022, UNLESS NOTED OTHERWISE.
2. ALL EXISTING UTILITIES ARE NOT NECESSARILY SHOWN; CONTRACTOR SHALL LOCATE ALL UTILITIES PRIOR TO COMMENCING WORK.
3. CONTRACTOR SHALL VERIFY EXISTING GRADES PRIOR TO COMMENCING CONSTRUCTION ACTIVITIES. CONTRACTOR SHALL NOTIFY CBBEP'S
ENGINEER IMMEDIATELY OF ANY DISCREPANCIES OR CONFLICTS.
4. PROJECT IS WITHIN AND ADJACENT TO ENVIRONMENTALLY SENSITIVE AREAS. CONTRACTOR SHALL AVOID IMPACTS TO THESE AREAS OUTSIDE OF WORK AREAS SHOWN IN THESE DRAWINGS DURING THE COURSE OF WORK. ANY DAMAGE CAUSED BY CONTRACTOR'S ACTIVITIES SHALL BE RESTORED AT THE EXPENSE OF CONTRACTOR AND TO THE SATISFACTION OF OWNER AND RESOURCE AGENCIES. OWNER SHALL BE THE SOLE ASSESSOR AS TO WHETHER ENVIRONMENTAL IMPACTS HAVE OCCURRED AS A RESULT OF CONTRACTOR'S ACTIVITIES. OWNER RESERVES THE RIGHT TO SUSPEND WORK AT ANY TIME IF IMPACTS OCCUR UNTIL SATISFACTORY CORRECTIVE MEASURES ARE IMPLEMENTED BY
CONTRACTOR.
5. CONTRACTOR SHALL OBTAIN PERMISSION FROM PROPERTY OWNERS FOR STAGING AREAS AND CONSTRUCTION ACCESS ROUTES ON PRIVATE PROPERTY. ENVIRONMENTALLY SENSITIVE AREAS SHALL NOT BE USED FOR STAGING OR ACCESS.
6. CONSTRUCTION EQUIPMENT SHALL NOT BE OPERATED OVER EXISTING MARSH VEGETATION, SEAGRASS, OR OYSTER REEFS WITHOUT PRIOR
COORDINATION WITH CBBEP'S ENGINEER.
7. CONTRACTOR SHALL TAKE PRECAUTIONS, SECURE EQUIPMENT, AND PROTECT THE WORK AGAINST ADVERSE WEATHER CONDITIONS AND
SURGE/WAKE FROM PASSING VESSELS REGARDLESS OF MARINE CONDITIONS.
8. UNLESS OTHERWISE NOTED WITHIN DRAWINGS, CONTRACTOR SHALL BE RESPONSIBLE FOR ESTABLISHING INGRESS/EGRESS ROUTES AND STAGING/MOORING AREAS. CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ANY OBSTRUCTIONS OR UTILITIES WITHIN THESE AREAS.
9. CONTRACTOR SHALL ANTICIPATE GROUNDWATER, SURFACE WATER, AND TIDAL WATER ENTERING THE PROJECT SITE AND APPLY
APPROPRIATE MEANS AND METHODS FOR CONSTRUCTION IN SOFT/WET/SATURATED SOILS.
SURVEY NOTES:
1. COORDINATES SHOWN ARE IN U.S. FEET AND ARE REFERENCED TO STATE PLANE, TEXAS SOUTH ZONE, NAD '83 (2011).
2. ELEVATIONS SHOWN ARE IN FEET AND REFERENCED TO NAVD '88, GEOID 18.
3. HYDROGRAPHIC AND TOPOGRAPHIC SURVEYS WERE CONDUCTED BY T. BAKER SMITH ON FEBRUARY 1, 2022 AND MARCH 21, 2025 AND
REPRESENT THE CONDITIONS THAT EXISTED AT THE TIME OF THE SURVEYS.
4. A MAGNETOMETER SURVEY WAS PERFORMED BY T. BAKER SMITH ON MARCH 2, 2022. SEE RESULTS IN APPENDIX E. THIS MAGNETOMETER SURVEY IS PROVIDED FOR INFORMATIONAL PURPOSES ONLY. CONTRACTOR SHALL BE RESPONSIBLE FOR DETERMINING LOCATIONS OF POTENTIAL HAZARDS, OBSTRUCTIONS, AND UTILITIES WITHIN WORK AND NAVIGATION AREAS. SEE SPECIFICATION 35 00 01, "CONSTRUCTION
SURVEYING."
5. MONUMENTS FOR SURVEY CONTROL PROVIDED IN TABLE BELOW.
BREAKWATER AND SAND FILL BASELINE
APPROXIMATE EXISTING GRADE
GEOTEXTILE FILTER FABRIC
GRADED RIPRAP (CROSS SECTION)
GENERAL
SURVEYING/MAPPING
DEMOLITION
CIVIL
DISCIPLINE DESIGNATOR & DISCIPLINE ORDER
G V X C
EXAMPLE
SITE PLAN SYMBOLOGY GENERAL SYMBOLOGY
SHEET NAMING CONVENTION
PLACEHOLDER
SHEET NUMBER
DISCIPLINE DESIGNATOR
SERIES DESIGNATION
0 0
0 1
A
BASEWORK DAYBEACON
* EXCEPTIONS WHERE THE SHEET NUMBER IS REPLACED BY A DASH (-).
1) FOR COMMON DETAILS, SECTIONS, ELEVATIONS OR DETAILS THAT ARE
CUT OR CALLED OUT ON MULTIPLE SHEETS.
2) SECTIONS, ELEVATIONS OR DETAILS THAT ARE LOCATED ON THE SAME
SHEET THEY ARE CUT OR CALLED OUT ON.
PROPOSED BREAKWATER (PLAN VIEW)
SURVEY MAP AND KEY MAP
N.T.S.
ARROW INDICATES
DIRECTION OF
PLAN NORTH
NORTH ARROW
PLAN TITLE
SHEET WHERE DETAIL
IS LOCATED *
DETAIL NUMBER
SHEET WHERE SECTION
VIEW IS FIRST CUT *
SECTION LETTER
SHEET WHERE SECTION
IS LOCATED
SECTION LETTER
FLAG INDICATES DIRECTION
OF SECTION CUT
SECTION CUT MARKER DETAIL MARKER
SECTION TITLE
FOR REFERENCING DETAILS INCLUDED IN DRAWING SET.
DETAIL TITLE
PLAN
1/4" = 1'-0"
X
XXX
X
XXX
SECTION
3/8" = 1'-0"
XXX
X
XXX
DETAIL
1/4" = 1'-0"
SHEET WHERE DETAIL
IS LOCATED *
DETAIL NUMBER
GULF
OF
AMERICAARANSAS
BAY
SURVEY TRANSECT LOCATION
1+00
LAMAR
GULF
IN
TR
AC
OAS
TA
L W
AT
ER
W
AY
SAN JOSE
ISLAND
B
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
A
1 3 4 5 6 7 8
PHILIP J. BLACKMAR
10426649
DESIGNED BY
DRAWN BY
CHECKED BY
COASTAL BEND BAYS AND
ESTUARIES PROGRAM
P. J. BLACKMAR
O. SALAS
C. PERRY
- 03/02/2026 ISSUED FOR BID
1 03/16/2026 ADDENDUM 1
DEADMAN ISLAND
RESTORATION AND
PROTECTION
HDR Engineering, Inc.
TBPELS Firm Registration No. F-754
FULTON
ROCKPORT
COPANO
BAY
01C-01
EXISTING
CONDITIONS
02C-01
PROJECT
LAYOUT
DEADMAN ISLAND
877 4513 H
ABBREVIATIONS
GRADED RIPRAP
GULF INTRACOASTAL WATERWAY
GRR
GIWW
S1 SURVEY TRANSECT POINT
© 2024 Microsoft Corporation Earthstar Geographics SIO
SAND FILL
PROPOSED REEF (PLAN VIEW)
PROPOSED REEF (CROSS SECTION)
PILE
PLATFORM
OBSTRUCTION
SLOPE (PLAN VIEW)
-15.3 2025 SPOT ELEVATION, FT
SANDY LOAM FILL
ADDITIVE BID DAYBEACON
GIWW LIMITS
OBSTRUCTION (TYP.)
PILE (TYP.)
PLATFORM (TYP.)
TO
P
ORT
O'C
ONNOR
TO
A
RAN
SA
S
PA
SS
GULF
IN
TR
AC
OAS
TA
L W
AT
ER
W
AY
-3.77 -3.97
-4.10 -4.27
-4.40 -4.53
-4.66 -5.05
-5.42 -5.32
-5.19 -5.19
-5.19 -5.09
-5.09 -5.19
-5.25 -5.42
-5.58 -6.89
-5.09 -4.79
-5.51 -5.51
-5.78 -5.84
-5.81 -6.10
-6.79 -6.40
-6.83 -6.63
-6.40 -6.24
-6.43 -6.63
-6.92 -7.32
-7.42 -7.42
-7.42 -7.55
-7.58 -7.68
-7.74 -7.74
-7.74
-6.56 -6.53
-6.20 -6.30
-6.07 -5.87
-5.71 -5.91
-5.94 -5.87
-5.84 -5.84
-5.71 -5.64
-5.58 -5.48
-5.38 -5.22
-5.19 -5.12
-4.92 -4.79
-4.69 -4.63
-4.63 -4.43
-4.46 -4.30
-4.10 -4.00
-3.94 -3.81
-3.87 -3.61
-3.58 -3.45
-3.25 -3.18
-3.09 -2.92
-2.86 -2.82
-2.76 -2.66
-2.53 -2.27
-2.27 -2.23
-2.30 -2.23
-2.23 -2.20
-5.28 -5.32
-5.32 -5.28
-5.32 -5.25
-5.38 -5.19
-5.15 -5.28
-4.33 -3.45
-2.92 -2.50
-2.36 -2.36
-2.33 -2.27
-2.30 -2.20
-2.13 -1.90
-2.17 -2.27
-2.46 -2.50
-2.63 -2.53
-2.50 -2.56
-2.53 -2.59
-2.82 -2.82
-2.79 -2.89
-3.22 -3.41
-3.35 -3.58
-3.64 -3.81
-3.87 -4.00
-4.07 -4.17
-4.27 -4.23
-4.33 -4.43
-4.56 -4.69
-4.73 -4.82
-4.92 -4.92
-5.12 -5.19
-5.32 -5.42
-5.55 -5.81
-5.97 -6.24
-6.43 -6.50
-6.60 -6.66
-6.66 -6.73
-6.66 -6.60
-6.47 -6.43
-6.43 -6.50
-6.40 -6.43
-6.50 -6.56
-6.56 -6.69
-6.79 -6.89
-7.12 -7.58
-7.68 -7.74
-7.81 -7.81
-7.81 -7.84
-7.91 -7.91
-7.94 -7.94
-7.97 -8.01
-8.04 -8.04
-8.07
-6.53 -6.27
-6.07 -5.81
-5.84 -5.71
-5.55 -5.45
-5.38 -5.32
-5.19 -5.19
-5.05 -4.86
-4.79 -4.82
-4.59 -4.40
-4.50 -4.40
-4.20 -3.97
-3.94 -3.91
-3.84 -3.68
-3.55 -3.48
-3.35 -3.22
-3.09 -2.89
-2.27 -2.27
-2.40 -2.53
-2.63 -2.69
-2.86 -3.18
-3.45 -3.77
-4.14 -4.23
-4.33 -4.50
-4.59 -4.96
-5.05 -5.12
-5.12 -5.22
-5.15 -5.32
-5.19 -5.28
-5.19 -5.15
-4.89 -4.96
-4.99 -4.82
-4.82 -4.79
-4.53 -4.43
-4.27 -3.71
-3.41 -3.22
-3.22 -3.32
-3.35 -3.38
-3.48 -3.58
-3.68 -3.81
-3.94 -4.00
-4.23 -4.40
-4.59 -4.79
-4.89 -5.09
-5.51
-6.96 -7.02
-6.96 -6.89
-6.83 -6.60
-6.10 -5.68
-5.32 -4.96
-4.63 -4.37
-4.04 -3.81
-3.68 -3.48
-3.28 -3.22
-3.12 -3.02
-3.02 -2.99
-2.99 -2.99
-3.15 -3.68
-3.84 -3.84
-3.81 -3.87
-3.91 -4.07
-4.14 -4.33
-5.38 -5.12
-4.96 -4.33
-3.87 -3.45
-3.22 -3.05
-2.95 -2.89
-3.28 -3.91
-3.97 -3.87
-4.00 -4.00
-4.04 -4.17
-4.23 -4.43
-4.46 -4.63
-4.66 -4.73
-4.82 -4.99
-5.05 -5.19
-5.35 -5.45
-4.96 -4.86
-4.69 -4.50
-4.43 -4.27
-4.07 -3.97
-3.87 -3.68
-3.45 -3.35
-3.22
-4.27 -4.17
-4.14 -4.00
-3.77 -3.61
-3.58 -3.58
-3.48 -3.32
-3.22 -3.09
-3.15 -2.95
-2.89 -2.86
-2.76 -2.69
-2.56 -2.46
-2.43 -2.30
-2.20
-3.38 -3.28
-3.12 -3.09
-3.05 -2.95
-2.82 -2.76
-2.56 -2.43
-2.30 -2.17
-2.10 -2.07
-1.90 -1.90
-1.87 -1.58
-3.09 -2.82
-2.76 -2.69
-2.69 -2.76
-2.76 -2.99
-3.45 -3.74
-4.50 -4.82
-5.15
-5.42 -5.78
-6.17 -6.69
-6.89 -6.83
-6.99 -7.02
-7.02 -7.06
-7.06 -7.06
-7.02 -6.99
-6.99 -7.02
-6.99 -7.02
-6.99 -6.99
-6.92 -6.76
-6.69
-7.15 -7.15
-7.15 -7.15
-6.99 -7.09
-7.06 -6.96
-6.76 -6.27
-5.87 -5.51
-5.19 -4.86
-4.63 -4.20
-4.17 -3.91
-3.94 -3.64
-3.61 -3.35
-3.25 -3.15
-3.02 -2.86
-2.59 -2.59
-2.53 -2.43
-2.50 -2.56
-2.69 -2.76
-2.82 -3.94
-4.00 -4.17
-4.37 -4.43
-4.53 -4.73
-4.92 -5.09
-5.28 -5.61
-5.91 -6.14
-6.92 -6.92
-6.86 -6.89
-6.86 -6.89
-6.83 -6.86
-6.83 -6.79
-6.79 -6.83
-6.83 -6.79
-6.83 -6.79
-6.79 -6.83
-6.60 -5.91
-5.38 -4.96
-4.53 -4.33
-4.00
-6.73 -6.92
-7.02 -7.15
-7.15 -7.09
-7.09 -7.09
-7.02 -6.99
-7.02 -6.99
-6.99 -6.92
-6.96 -6.92
-6.99 -6.89
-6.89 -6.86
-6.83 -6.86
-6.83 -6.76
-6.76 -6.73
-6.73 -6.69
-6.63 -6.56
-6.56 -6.50
-5.94 -5.48
-5.09 -4.76
-4.40 -4.23
-4.07 -3.87
-3.68 -3.48
-3.22 -2.92
-2.69
-2.50 -2.40
-2.50 -2.72
-2.82 -2.69
-2.66 -2.76
-2.82 -2.89
-2.92 -2.99
-3.15 -3.25
-3.28 -3.38
-3.48 -3.64
-3.84 -3.97
-4.14 -4.33
-4.66 -4.96
-5.25 -5.58
-6.07 -6.37
-6.60 -6.86
-6.66 -6.79
-6.83 -6.76
-6.66 -6.69
-6.76
-0.85
-1.72
-2.18
-2.04
-2.16
-1.82
-1.93
-2.13
-0.99 -1.29
-1.55 -1.83
-2.00
-2.15
-0.76
-0.52
-0.34
1.39
1.85
1.08 -0.67
-1.46
-2.21
0.45
0.56
-0.20
2.38
0.30
-0.06
-0.59
-0.90
-1.24
-1.42
-1.67
-1.88
-1.72
-1.50
-1.35
-1.07
-1.01
-0.67
-0.28
0.57
1.68
-0.75 -2.60
-2.08
-2.04
-2.06
-2.07
-2.08
-1.96
-1.94
-1.89
-1.78
-1.67
0.99
2.01
-0.37
-0.84
-1.24
-1.49 -1.69
-1.71
-1.66
-1.43
-1.50
-1.42
-1.24
-0.84
-0.72
-0.43
-0.11
0.15
1.46
3.07
1.94
-0.73
-2.06
0.65 -1.08
-1.41
-1.69
-1.77
-1.67
-2.13
-2.13
-1.77
-1.18
-1.15
-0.97
0.87
-0.55 -1.20
-1.65
-0.82 0.80
-1.47 -1.89
-1.99 -2.04
-1.95 -2.14
-2.19
-2.06
-2.58
-2.93
-3.24
-3.17
-2.83
-3.06
-2.90 -2.64
-2.46
-2.15
-3.14 -3.50
-3.43
-3.35
-3.59 -3.40
-3.29
-3.35
-3.63
-3.73 -3.88
-2.82
-2.75 -2.60 -2.31
-2.21
-2.07
-1.86
-2.21
-2.54
-2.38
-2.29
-2.07
-2.18
-2.02
-2.15
-2.08 -1.78
-1.79
-1.74
-5.84
-5.60
-5.43
-5.36
-5.17
-4.94
-4.83
-3.38
-3.96
-5.74
-5.63
-5.57
-5.52 -5.57
-5.54 -4.13
-2.83
-1.77
-1.55
-4.31 -4.29
-4.10 -4.00
-3.81
-3.73
-3.56 -3.38
-3.28
-3.10
-3.08 -3.51
-3.79
-3.91
-4.09 -6.32
-5.96
-5.43
-5.20
-4.80 -4.54
-4.25
-3.91 -3.65
-3.35
-2.97
-2.82
-3.01
-2.96 -2.81
-2.60
-2.62
-2.55
-2.51
-2.54
-2.55
-2.64
-2.70
-3.56
-3.46 -3.21
-3.12 -2.89
-2.63
-2.53
-2.53
-2.30
-2.21
-2.28
-2.23 -2.05
-2.08
-2.23
-2.21
-2.26 -2.24
-2.31
-2.39 -2.53
-2.35
-2.34 -2.22
-2.54
-2.72
-3.06
-4.25 -4.68
-4.65 -4.18
-3.13
-2.88
-3.16
-4.74
-5.15 -4.62
-2.92
-2.22
-1.29
-5.11 -5.05
-4.77
-4.62
-4.32
-4.08 -3.99
-3.71
-5.05 -4.99
-3.00 -3.41
-2.17 -2.48
-3.40 -3.13
-2.94 -2.80
-2.69 -2.56
-2.46 -2.36
-2.30 -2.35
-2.31 -2.20
-2.22 -2.21
-2.22 -2.31 -2.18
-2.42 -2.53
-2.84 -3.00
-3.12 -3.50
-3.67-3.84 -4.22 -4.36-4.72-5.23
-6.06-6.54
-2.47 -2.66
-3.25 -3.99
-4.14 -4.43-4.72
-5.04 -5.34
-5.49 -5.55
-5.69 -4.24-2.32
-2.00 -1.59
-1.57 -1.71
-1.81-1.55 -1.66
-1.88 -1.96
-2.06 -1.85
-2.01
-1.91 -2.09
-2.32
-2.13
-2.41
-2.87
-3.00
APPROX. PROJECT LIMITS
(SEE SHEET 02C-01)
DEADMAN ISLAND
(3.22 ACRES)
ADDITIVE BID NO. 5 -
OYSTER REEF
(0.90 ACRES)
EXISTING CONDITIONS
01C-01.DWG
AS NOTED 01C-01
00G-01
EXISTING CONDITIONS
SCALE:
B
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
DESIGNED BY
DRAWN BY
CHECKED BY
PROTECTION
HDR Engineering, Inc.
TBPELS Firm Registration No. F-754
NOTES:
1. SEE NOTES ON SHEET 00G-01.
2. CONTRACTOR SHALL BE RESPONSIBLE FOR
DETERMINING LOCATIONS OF ANY OBSTRUCTIONS
AND UTILITIES WITHIN CONSTRUCTION ACCESS
CORRIDOR OR WORK BOUNDARY.
© 2024 Microsoft Corporation Earthstar Geographics SIO
LEGEND
-15.3 2022 SPOT ELEVATION, FT
-15.3 2025 SPOT ELEVATION, FT
GULF
IN
TR
AC
OAS
TA
L W
AT
ER
W
AY
TO
P
ORT
O'C
ONNOR
TO
A
RAN
SA
S
PA
SS
BREAKWATER
ADDITIVE BID NO. 5 -
OYSTER REEF
(0.90 ACRES)
650'
OBSTRUCTION (TYP.)
PILE (TYP.)
PLATFORM (TYP.)
L-1
L-2
C-
C-2
BREAKWATER BASELINE
(SEE SHEET 02C-02)
DB01
DB03
DB06
DB05
BASEWORK -
DAYBEACON (TYP.)
ST
A.
7+
ST
A.
+4
S0+00
S1+00
S2+00
S3+00
S4+00
S5+00
S6+00
S7+00 S7+88.5
ISLAND FILL (SEE SHEET
03C-01 FOR ELEVATION
REQUIREMENTS)
DEADMAN ISLAND
(3.22 ACRES)
ISLAND FILL BASELINE
L-3
0+00/17+50 1+00
2+00
3+00
4+00
5+00
6+00
7+00
8+009+00
10+00
11+00
12+00
13+00
14+00
15+00
+0
17+00
DB02
D B0
D B0
ADDITIVE BID NO. 5 -
DAYBEACON
DAYBEACON COORDINATES
DESIGNATION
DB01
DB02
DB03
DB06
DB05
DB04
DB07
NORTHING
13,213,980
13,213,913
13,213,813
13,213,768
13,213,568
13,213,619
13,213,902
EASTING
2,625,464
2,625,656
2,625,939
2,625,283
2,625,853
2,626,005
2,625,202
SAND FILL BASELINE
STATION
S0+00
S7+88.5
NORTHING
13,213,892
13,213,631
EASTING
2,625,231
2,625,975
PROJECT LAYOUT
02C-01.DWG
AS NOTED 02C-01
00G-01
PROJECT LAYOUT
SCALE:
NOTES:
1. SEE NOTES ON SHEET 00G-01.
2. REFER TO SHEET 02C-02 FOR BREAKWATER
BASELINE COORDINATES.
3. CONTRACTOR SHALL SET TEMPORARY STAKES
FOR BREAKWATER ALIGNMENT, AND
DAYBEACONS FOR REVIEW BY ENGINEER PRIOR
TO CONSTRUCTION.
B
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
DESIGNED BY
DRAWN BY
CHECKED BY
PROTECTION
HDR Engineering, Inc.
TBPELS Firm Registration No. F-754
02C-02ENLARGED PROJECT LAYOUT
02C-03
CONSTRUCTION SURVEY PLAN
© 2024 Microsoft Corporation Earthstar Geographics SIO
BREAKWATER
ADDITIVE BID NO. 5 - OYSTER REEF
(0.90 ACRES)
L-1
L-2
C -1
C-
BREAKWATER BASELINE
BASEWORK -
DAYBEACON (TYP.)
ISLAND FILL (SEE SHEET
03C-01 FOR ELEVATION
REQUIREMENTS)
ISLAND FILL BASELINE
0+00/17+50 1+00 2+00 3+00 4+00 5+00 6+00
7+00
8+
9+0010+0011+0012+0013+0014+0015+00
16+00
17+00
650'
DEADMAN ISLAND
(3.2 ACRES)
ST
A.
+4
ST
A.
7+
L-3
AP
PR
O X.
IS
LA
N D
F
IL
L
LI
M
IT
S
S0+00 S1+00 S2+00 S3+00 S4+00 S5+00 S6+00 S7+00 S7+88.5
ADDITIVE BID NO. 5 - DAYBEACON
BREAKWATER BASELINE
NUMBER
L-1
C-1
L-2
C-2
START
STATION
0+00.0
6+37.3
8+74.8
15+12.1
END
STATION
6+37.3
8+74.8
15+12.1
17+49.6
LENGTH
637.3'
237.5'
637.3'
237.5'
RADIUS
NA
75.6'
NA
75.6'
LINE/CHORD DIRECTION
S70°38'33"E
S19°21'27"W
N70°38'33"W
N19°21'28"E
START NORTHING
START EASTING
13,213,939 2,625,328
13,213,727 2,625,929
13,213,585 2,625,879
13,213,796 2,625,278
END NORTING
END EASTING
13,213,727 2,625,929
13,213,585 2,625,879
13,213,796 2,625,278
13,213,939 2,625,328
03C-01
ENLARGED PROJECT LAYOUT
02C-02.DWG
AS NOTED 02C-02
02C-01
ENLARGED PROJECT LAYOUT
SCALE:
NOTES:
1. SEE NOTES ON SHEET 00G-01.
2. CONTRACTOR SHALL SET TEMPORARY STAKES
FOR BREAKWATER ALIGNMENT AND DAYBEACONS
FOR REVIEW BY CBBEP'S ENGINEER PRIOR TO
CONSTRUCTION.
B
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
DESIGNED BY
DRAWN BY
CHECKED BY
PROTECTION
HDR Engineering, Inc.
TBPELS Firm Registration No. F-754
B 03C-01
SEE
A 03C-01
SURVEY
TRANSECT COORDINATES
POINT
S01
S02
S03
S04
S05
S06
S07
NORTHING
13,213,950
13,213,649
13,213,912
13,213,611
13,213,874
13,213,573
13,213,999
EASTING
2,625,188
2,626,045
2,625,175
2,626,032
2,625,161
2,626,019
2,625,257
BREAKWATER
ADDITIVE BID NO. 5 -
OYSTER REEF
S01 S02
S03 S04
DEADMAN
ISLAND
S05 S06
S07
S08
S09
S10
S11
S12
S13
S14
S15
S16
S17
S18
S19
S20
S21
S22
S23
S24
S25
S26
S27
S28
S29
S30
S31 S32
S33 S34
BREAKWATER
PROFILE SURVEY
(SEE NOTE 3)
SURVEY TRANSECT
(SEE NOTE 2)(TYP.)
SURVEY
TRANSECT COORDINATES
POINT
S08
S09
S10
S11
S12
S13
S14
NORTHING
13,213,891
13,213,793
13,213,855
13,214,042
13,213,739
13,214,012
13,213,709
EASTING
2,625,292
2,625,184
2,625,280
2,625,364
2,625,258
2,625,450
2,625,343
SURVEY
TRANSECT COORDINATES
POINT
S15
S16
S17
S18
S19
S20
S21
NORTHING
13,213,982
13,213,679
13,213,952
13,213,649
13,213,922
13,213,619
13,213,891
EASTING
2,625,536
2,625,429
2,625,622
2,625,515
2,625,708
2,625,601
2,625,793
SURVEY
TRANSECT COORDINATES
POINT
S22
S23
S24
S25
S26
S27
S28
NORTHING
13,213,588
13,213,861
13,213,558
13,213,831
13,213,528
13,213,668
13,213,730
EASTING
2,625,687
2,625,879
2,625,773
2,625,965
2,625,859
2,625,926
2,626,022
SURVEY
TRANSECT COORDINATES
POINT
S29
S30
S31
S32
S33
S34
NORTHING
13,213,632
13,213,524
13,214,017
13,213,782
13,213,985
13,213,750
EASTING
2,625,914
2,625,949
2,625,317
2,625,986
2,625,305
2,625,975
CONSTRUCTION SURVEY PLAN
02C-03.DWG
AS NOTED 02C-03
02C-01
CONSTRUCTION SURVEY PLAN
SCALE:
NOTES:
1. SEE NOTES ON SHEET 00G-01.
2. TRANSECT LOCATIONS SHOWN ON THIS SHEET
SHALL BE SURVEYED BY CONTRACTOR TO
DOCUMENT INITIAL, INTERIM, AND FINAL
CONDITIONS. REFER TO SPECIFICATION 35 00 01
(CONSTRUCTION SURVEYING) FOR ADDITIONAL
SURVEYING REQUIREMENTS.
3. BREAKWATER PROFILE SURVEY TRANSECTS
NOT SHOWN FOR CLARITY. REFER TO
SPECIFICATION 35 00 01.
B
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
DESIGNED BY
DRAWN BY
CHECKED BY
PROTECTION
HDR Engineering, Inc.
TBPELS Firm Registration No. F-754
3.0'
(MIN.)
SWL (VARIES)
ELEV. +4.5' (MIN.)
1' (MIN.) TO
2' (MAX.) (TYP.)
6' (MIN.)
0'
BREAKWATER
ALIGNMENT POINT
TYPICAL DETAIL - DAYBEACON (SEE NOTE 8)
NOT TO SCALE
03C-01
TYPICAL SECTION - GRR BREAKWATER (SEE NOTE 7)
NOT TO SCALE
02C-02
GRADED RIPRAP TYPE 1
GEOTEXTILE
FILTER FABRIC
NOTES:
1. ALL SLOPES SHOWN ARE STEEPEST ALLOWED.
ACTUAL SLOPES MAY BE LESS (I.E. "FLATTER").
2. GRADED RIP RAP PLACEMENT SHALL MAXIMIZE
CONTACT BETWEEN STONES ON ALL SIDES WITH
EACH STONE HAVING AT LEAST THREE POINTS
OF CONTACT WITH OTHER STONES.
3. REFER TO SPECIFICATIONS SECTION 35 31 19.40
"BREAKWATER" FOR ADDITIONAL GRADED RIP
RAP REQUIREMENTS.
4. DAYBEACONS SHALL BE LOCATED
APPROXIMATELY 10 FEET FROM SEAWARD TOE
OF BREAKWATER. ALL DAYBEACON LOCATIONS
SHALL BE COORDINATED WITH CBBEP'S
ENGINEER PRIOR TO DAYBEACON INSTALLATION.
5. GEOTEXTILE FILTER FABRIC SHOWN BELOW
EXISTING GRADE FOR CLARITY. ACTUAL
PLACEMENT WILL BE DIRECTLY ON EXISTING
GRADE IN CONTACT WITH GRADED RIP RAP.
CONTRACTOR SHALL KEY GEOTEXTILE FILTER
FABRIC AT BREAKWATER CREST ON INTERIOR
(FILL SIDE OF BREAKWATER) WHERE FILL WILL
BE PLACED ADJACENT TO BREAKWATER.
CONTRACTOR SHALL MAINTAIN GEOTEXTILE
FILTER FABRIC ON INTERIOR SLOPE UNTIL FILL IS
PLACED TO REQUIRED SPECIFIED ELEVATION.
CONTRACTOR MAY PROPOSE ALTERNATIVE
METHODS TO PLACING FABRIC ON INTERIOR OF
BREAKWATER TO MAINTAIN ISLAND FILL.
APPROVAL OF ALTERNATIVE METHODS WILL BE
DETERMINED BY CBBEP'S ENGINEER.
6. SANDY LOAM IN ADDITIVE BID NO. 4 MUST BE A
MINIMUM OF 6" THICK IN ADDITION TO MEETING
THE ELEVATION REQUIREMENTS SHOWN.
7. TYPICAL SECTION 1 AND 2 ONLY SHOW THE
ADDITIVE BID NO. 2 BREAKWATER AND ADDITIVE
BID NO. 4 ISLAND FILL FOR CLARITY. THE
BASEWORK AND ADDITIVE BID BREAKWATER
SECTIONS ARE SHOWN IN TYPICAL SECTION 4
AND THE ISLAND FILL BASEWORK AND ADDITIVE
BID DETAILS ARE SHOWN IN TYPICAL ISLAND
SECTION A AND B.
8. IF ADDITIVE BID NO. 5 IS AWARDED, THE WORD
"BREAKWATER" ON DAYBEACON DB01, DB02,
AND DB03 SHALL BE REPLACED WITH
"SUBMERGED REEF".
VARIES
VARIES
APPROXIMATE EXISTING GROUND
(ELEVATION VARIES)
BREAKWATER (TYP.)
REEF
A 02C-02
TYPICAL ISLAND SECTION
NOT TO SCALE
B 02C-02
TYPICAL ISLAND SECTION
NOT TO SCALE
BREAKWATER
(TYP.)
03C-01
03C-01
(TYP.)
APPROXIMATE EXISTING GROUND
(ELEVATION VARIES)
APPROXIMATE EXISTING GROUND
(ELEVATION VARIES)
3.0'
(MIN.)
SWL (VARIES)
ELEV. +4.5' (MIN.)
BREAKWATER
ALIGNMENT
6' (MIN.)
0'
BREAKWATER
ALIGNMENT POINT
03C-01
TYPICAL SECTION - GRR BREAKWATER (SEE NOTE 7)
NOT TO SCALE
GRADED RIPRAP TYPE 1
GEOTEXTILE
FILTER FABRIC
ADDITIVE BID NO. 5 - 60' OYSTER REEF
APPROXIMATE EXISTING GROUND
(ELEVATION VARIES)
ELEV. +4.5'
ELEV. +4.5'
1' (-0.25'/+0.5' TOLERANCE) 1' (MIN.) TO
2' (MAX.) (TYP.)
ANGLE OF
REPOSE
2' (MIN.)
2' (MIN.)
BREAKWATER
ALIGNMENT
GRADED RIPRAP TYPE 2
VARIES
VARIES
2' (M
IN.)
3'
ELEV. +5.0'
TOP OF POST SHALL BE
CUT TO A MINIMUM 45 DEG.
ANGLE TO DETER BIRD ROOSTING
(3) 3/4" DIA X 12" LONG A307 (HDG)
DOME HEAD BOLTS WITH OGEE
WASHER AND NUT (TYP.)
RETROFLECTIVE BLACK LETTERS
(TYP) SIGN LETTERING SHALL
CONFORM TO 33CFR, CHAPTER 1,
SUBPART 66.10-25.
3'
0.
0.
3'
0.125" THICK MARINE GRADE
ALUMINUM WITH WHITE
SHEETING (ONE SIDE)
3" ORANGE
RETROFLECTIVE BORDER
(1) 10" DIA X 25' LONG TREATED
TIMBER POST (2.5 CCA)
6" MIN. TIP
DRIVE OR JET TIMBER
POST IN PLACE A
MINIMUM OF 10 FT
BELOW MUDLINE
FRONT REAR
L3X2X1/4" 6061
ALUMINUM
1.
3'
1.
3'
NOTCH PILE
1/8"
SIDE
SIGN
FACE
1" @ 6" TYP.
FT
M
AX
6" MIN.
SANDY LOAM FILL ELEV. +4.5' (MIN.) ADDITIVE BID NO.4 (SEE NOTE 6)
SAND FILL ELEV. +4.0' (MIN.) ADDITIVE BID NO.3
SAND FILL ELEV. +3.5' (MIN.) BASE BID
6" MIN.
SANDY LOAM FILL ELEV. +4.5' (MIN.) ADDITIVE BID NO.4 (SEE NOTE 6)
SAND FILL ELEV. +4.0' (MIN.) ADDITIVE BID NO.3
SAND FILL ELEV. +3.5' (MIN.) BASE BID
3.0'
(MIN.)
SWL (VARIES)
ELEV. +4.5' (MIN.) ADDITIVE BID NO. 2
1' (MIN.) TO
2' (MAX.) (TYP.)
6' (MIN.)
0'
BREAKWATER
ALIGNMENT POINT
03C-01
TYPICAL SECTION - GRR BREAKWATER
NOT TO SCALE
GRADED RIPRAP TYPE 1
GEOTEXTILE
FILTER FABRIC
APPROXIMATE EXISTING GROUND
(ELEVATION VARIES)
BREAKWATER
ALIGNMENT
ELEV. +3.5' (MIN.) BASE BID
ELEV. +4.0' (MIN.) ADDITIVE BID NO. 1
B
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
DESIGNED BY
DRAWN BY
CHECKED BY
PROTECTION
HDR Engineering, Inc.
TBPELS Firm Registration No. F-754
TYPICAL SECTIONS AND DETAILS
03C-01.DWG
AS NOTED 03C-01
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 0+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50-60-70-80-90-100
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 1+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50-60-70-80-90-100
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 2+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50-60-70-80-90-100
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 3+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50-60-70-80-90
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 4+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50-60-70-80-90
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 5+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50-60-70-80-90
BR
EA
KW
AT
ER
BA
SE
LI
N E
6' (MIN.) (TYP.)
ADDITIVE BID NO. 5 - 60' OYSTER REEF
1' (-0.25'/+0.5'
TO
LER
AN
C
E)
(TYP.)
NOTES:
1. SECTIONS VIEWED LOOKING TOWARDS
INCREASING STATIONS.
2. GEOTEXTILE FILTER FABRIC AND SAND NOT
SHOWN FOR CLARITY. REFER TO SHEET 03C-01.
3. QUANTITIES SHOWN FOR CROSS-SECTIONAL
AREAS OF BREAKWATER AND REEF ARE
APPROXIMATE AND PROVIDED FOR
INFORMATIONAL PURPOSES ONLY.
CONTRACTOR IS RESPONSIBLE FOR
PREPARATION OF THEIR OWN ESTIMATES OF
REQUIRED MATERIAL QUANTITIES.
CONTRACTOR SHALL ANTICIPATE SOFT SOIL
CONDITIONS, SETTLEMENT, AND
CONSOLIDATION WHEN ESTIMATING REQUIRED
MATERIAL QUANTITIES. REFER TO APPENDIX A
OF SPECIFICATIONS FOR AVAILABLE
GEOTECHNICAL DATA.
(MIN.)
(MIN.)
EL. 4.5' (MIN.) ADDITIVE BID NO. 2
EL. 4.0' (MIN.) ADDITIVE BID NO. 1
EL. 3.5' (MIN.) BASE BID
MATERIAL(S) AT STATION 2+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 120
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 1+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 142
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 0+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 24
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 5+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 77
15ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 4+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 85
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 3+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 85
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
GRR TYPE 2
GRADED RIPRAP (TYP.)
REEF STONE (TYP.)
2025 APPROX. EXISTING
GROUND (TYP.)
B
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
DESIGNED BY
DRAWN BY
CHECKED BY
PROTECTION
HDR Engineering, Inc.
TBPELS Firm Registration No. F-754
BREAKWATER AND REEF CROSS-SECTIONS
04C-01.DWG
AS NOTED 04C-01
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 6+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50-60-70-80-90
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 7+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 8+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 9+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 10+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 6+38
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50-60-70-80-90
BR
EA
KW
AT
ER
BA
SE
LI
N E
6' (MIN.) (TYP.)
(MIN.)
(MIN.)
NOTES:
1. REFER TO NOTES ON SHEET 04C-01.
EL. 4.5' (MIN.) ADDITIVE BID NO. 2
EL. 4.0' (MIN.) ADDITIVE BID NO. 1
EL. 3.5' (MIN.) BASE BID
ADDITIVE BID NO. 5 - 60' OYSTER REEF
MATERIAL(S) AT STATION 7+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 108
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 6+38
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 94
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 6+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 82
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 9+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 194
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 8+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 142
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 10+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 198
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
GRADED RIPRAP (TYP.)
REEF STONE (TYP.)
2025 APPROX. EXISTING
GROUND (TYP.)
1' (-0.25'/+0.5'
TO
LER
AN
C
E)
(TYP.)
BREAKWATER AND REEF CROSS-SECTIONS
04C-02.DWG
AS NOTED 04C-02
B
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
DESIGNED BY
DRAWN BY
CHECKED BY
PROTECTION
HDR Engineering, Inc.
TBPELS Firm
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 11+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 12+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 13+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 14+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 15+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40-50
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 16+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40
BR
EA
KW
AT
ER
BA
SE
LI
N E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 17+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 300-10-20-30-40
BR
EA
KW
AT
ER
BA
SE
LI
N E
6' (MIN.) (TYP.)
(MIN.)
(MIN.)
NOTES:
1. REFER TO NOTES ON SHEET 04C-01.
EL. 4.5' (MIN.) ADDITIVE BID NO. 2
EL. 4.0' (MIN.) ADDITIVE BID NO. 1
EL. 3.5' (MIN.) BASE BID
MATERIAL(S) AT STATION 12+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 66
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 11+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 116
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 13+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 68
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 15+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 87
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 14+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 78
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 16+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 95
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
MATERIAL(S) AT STATION 17+00
MATERIAL
GRR TYPE 1
AREA (SF)
BASE BID 67
GRR TYPE 2
ADDITIVE BID NO. 1
ADDITIVE BID NO. 2
ADDITIVE BID NO. 5
BID
GRADED RIPRAP (TYP.)
2025 APPROX. EXISTING
GROUND (TYP.)
BREAKWATER CROSS-SECTIONS
04C-03.DWG
AS NOTED 04C-03
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
DESIGNED BY
DRAWN BY
CHECKED BY
PROTECTION
HDR Engineering, Inc.
TBPELS Firm
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 1+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 30 40 50 60 70 80 90 100 110 120 130 1400-10-20-30-40-50-60-70-80-90-100-110-120
SA
N
D F
IL
L
BA
SE
LI
N
E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 0+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 30 40 50 60 70 80 90 100 110 120 130 1400-10-20-30-40-50-60-70-80-90-100-110-120
SA
N
D F
IL
L
BA
SE
LI
N
E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 0+76
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 30 40 50 60 70 80 90 100 110 120 130 1400-10-20-30-40-50-60-70-80-90-100-110-120
SA
N
D F
IL
L
BA
SE
LI
N
E
NOTES:
1. SECTIONS VIEWED LOOKING TOWARDS
INCREASING STATIONS.
2. GEOTEXTILE FILTER FABRIC NOT SHOWN FOR
CLARITY. REFER TO SHEET 03C-01.
3. QUANTITIES SHOWN FOR CROSS-SECTIONAL
AREAS OF SAND FILL ARE APPROXIMATE AND
PROVIDED FOR INFORMATIONAL PURPOSES
ONLY. CONTRACTOR IS RESPONSIBLE FOR
PREPARATION OF THEIR OWN ESTIMATES OF
REQUIRED MATERIAL QUANTITIES.
CONTRACTOR SHALL ANTICIPATE SOFT SOIL
CONDITIONS, SETTLEMENT, AND
CONSOLIDATION WHEN ESTIMATING REQUIRED
MATERIAL QUANTITIES. REFER TO APPENDIX A
OF SPECIFICATIONS FOR AVAILABLE
GEOTECHNICAL DATA.
6" MIN.
MATERIAL(S) AT STATION 1+00
MATERIAL
SAND FILL
AREA (SF)
BASE BID 508
SANDY LOAM FILL
ADDITIVE BID NO. 3
ADDITIVE BID NO. 4
BID
NO WORK THIS SECTION
MATERIAL(S) AT STATION 0+76
MATERIAL
SAND FILL
AREA (SF)
BASE BID 534
SANDY LOAM FILL
ADDITIVE BID NO. 3
ADDITIVE BID NO. 4
BID
MATERIAL(S) AT STATION 0+00
MATERIAL
SAND FILL
AREA (SF)
BASE BID 0
SANDY LOAM FILL
ADDITIVE BID NO. 3
ADDITIVE BID NO. 4
BID
BREAKWATER (TYP.)
APPROXIMATE EXISTING
GROUND (TYP.)
SANDY LOAM FILL EL. +4.5' (MIN.) ADDITIVE BID NO. 4
SAND FILL EL. +4.0' (MIN.) ADDITIVE BID NO. 3
SAND FILL EL. +3.5' (MIN.) BASE BID
SAND FILL CROSS-SECTIONS
05C-01.DWG
AS NOTED 05C-01
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
DESIGNED BY
DRAWN BY
CHECKED BY
PROTECTION
HDR Engineering, Inc.
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 2+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 30 40 50 60 70 80 90 100 110 120 130 1400-10-20-30-40-50-60-70-80-90-100-110-120
SA
N
D F
IL
L
BA
SE
LI
N
E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 3+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 30 40 50 60 70 80 90 100 110 120 130 1400-10-20-30-40-50-60-70-80-90-100-110-120
SA
N
D F
IL
L
BA
SE
LI
N
E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 4+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 30 40 50 60 70 80 90 100 110 120 130 1400-10-20-30-40-50-60-70-80-90-100-110-120
SA
N
D F
IL
L
BA
SE
LI
N
E
NOTES:
1. REFER TO NOTES ON SHEET 05C-01.
12 MATERIAL(S) AT STATION 4+00
MATERIAL
SAND FILL
AREA (SF)
BASE BID 339
SANDY LOAM FILL
ADDITIVE BID NO. 3
ADDITIVE BID NO. 4
BID
MATERIAL(S) AT STATION 3+00
MATERIAL
SAND FILL
AREA (SF)
BASE BID 370
SANDY LOAM FILL
ADDITIVE BID NO. 3
ADDITIVE BID NO. 4
BID
MATERIAL(S) AT STATION 2+00
MATERIAL
SAND FILL
AREA (SF)
BASE BID 420
SANDY LOAM FILL
ADDITIVE BID NO. 3
ADDITIVE BID NO. 4
BID
6" MIN.
BREAKWATER (TYP.)
SANDY LOAM FILL EL. +4.5' (MIN.) ADDITIVE BID NO. 4
SAND FILL EL. +4.0' (MIN.) ADDITIVE BID NO. 3
SAND FILL EL. +3.5' (MIN.) BASE BID
SAND FILL CROSS-SECTIONS
05C-02.DWG
AS NOTED 05C-02
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
DESIGNED BY
DRAWN BY
CHECKED BY
PROTECTION
HDR Engineering, Inc.
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 5+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 30 40 50 60 70 80 90 100 110 120 130 1400-10-20-30-40-50-60-70-80-90-100-110-120
SA
N
D F
IL
L
BA
SE
LI
N
E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 6+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 30 40 50 60 70 80 90 100 110 120 130 1400-10-20-30-40-50-60-70-80-90-100-110-120
SA
N
D F
IL
L
BA
SE
LI
N
E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 7+00
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 30 40 50 60 70 80 90 100 110 120 130 1400-10-20-30-40-50-60-70-80-90-100-110-120
SA
N
D F
IL
L
BA
SE
LI
N
E
NOTES:
1. REFER TO NOTES ON SHEET 05C-01.
12 MATERIAL(S) AT STATION 7+00
MATERIAL
SAND FILL
AREA (SF)
BASE BID 623
SANDY LOAM FILL
ADDITIVE BID NO. 3
ADDITIVE BID NO. 4
BID
MATERIAL(S) AT STATION 6+00
MATERIAL
SAND FILL
AREA (SF)
BASE BID 572
SANDY LOAM FILL
ADDITIVE BID NO. 3
ADDITIVE BID NO. 4
BID
MATERIAL(S) AT STATION 5+00
MATERIAL
SAND FILL
AREA (SF)
BASE BID 476
SANDY LOAM FILL
ADDITIVE BID NO. 3
ADDITIVE BID NO. 4
BID
6" MIN.
BREAKWATER (TYP.)
SANDY LOAM FILL EL. +4.5' (MIN.) ADDITIVE BID NO. 4
SAND FILL EL. +4.0' (MIN.) ADDITIVE BID NO. 3
SAND FILL EL. +3.5' (MIN.) BASE BID
SAND FILL CROSS-SECTIONS
05C-03.DWG
AS NOTED 05C-03
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
DESIGNED BY
DRAWN BY
CHECKED BY
PROTECTION
HDR Engineering, Inc.
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 7+88
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 30 40 50 60 70 80 90 100 110 120 130 1400-10-20-30-40-50-60-70-80-90-100-110-120
SA
N
D F
IL
L
BA
SE
LI
N
E
EL
EV
AT
IO
N , F
T.
(N
AV
D
EL
EV
AT
IO
N , F
T.
(N
AV
D
DISTANCE FROM BASELINE, FT.
STA. 7+13
-8
-6
-4
-2
-8
-6
-4
-2
0 10 20 30 40 50 60 70 80 90 100 110 120 130 1400-10-20-30-40-50-60-70-80-90-100-110-120
SA
N
D F
IL
L
BA
SE
LI
N
E
NOTES:
1. REFER TO NOTES ON SHEET 05C-01.
NO WORK THIS SECTION
MATERIAL(S) AT STATION 7+88
MATERIAL
SAND FILL
AREA (SF)
BASE BID 0
SANDY LOAM FILL
ADDITIVE BID NO. 3
ADDITIVE BID NO. 4
BID
MATERIAL(S) AT STATION 7+13
MATERIAL
SAND FILL
AREA (SF)
BASE BID 646
SANDY LOAM FILL
ADDITIVE BID NO. 3
ADDITIVE BID NO. 4
BID
6" MIN.
BREAKWATER (TYP.)
SANDY LOAM FILL EL. +4.5' (MIN.) ADDITIVE BID NO. 4
SAND FILL EL. +4.0' (MIN.) ADDITIVE BID NO. 3
SAND FILL EL. +3.5' (MIN.) BASE BID
SAND FILL CROSS-SECTIONS
05C-04.DWG
AS NOTED 05C-04
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
FILENAME
SCALE
SHEET
DATE
C
D
DESIGNED BY
DRAWN BY
CHECKED BY
PROTECTION
HDR Engineering, Inc.
| ADDENDUM NO. 1 |
| MARCH 18, 2026 |
| END OF ADDENDUM NO. 1 |