RFQ for Professional Engineering Services - Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System
Solicitation number
758-25-00091
Issued by
Blanco County, Waco City, Texas

About this file

This is Addendum No. 1 to a Request for Qualifications (RFQ) issued by The Texas State University System for professional engineering services related to the Lake Ament Dam Alteration project in Terlingua, Texas. The addendum includes responses to questions from a pre-submittal conference held on December 3, 2024, along with detailed site photographs and technical specifications of the existing dam structure. The project involves engineering services for a rock masonry dam that is 125 feet long, 56 feet high, with a 12-foot top width, originally constructed in the 1910s. Key dates include a question submission deadline of December 10, 2024, at 12:00 p.m. CST and a qualification submittal deadline of January 7, 2025. Site visits during construction will be required at least monthly.

The construction cost limitation is set at $900,000, which covers only construction and demolition costs, not engineering fees. The project includes a HUB (Historically Underutilized Business) requirement where the selected firm must demonstrate good faith efforts to allocate 20% of engineering services to qualified HUB consultants. The dam is classified as "Intermediate" size with a "High" hazard classification by TCEQ, and currently shows multiple structural issues including cracks in both upstream and downstream faces noted in a 2016 TCEQ Dam Safety Inspection Report. The dam's current specifications include a normal pool elevation between 3543.7 feet (low-water mark) and 3551.0 feet (high-water mark), with a surface area ranging from 4.4 to 12.8 acres and a capacity between 16.4 and 76.7 acre-feet.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(i)

(ii)

REQUEST FOR QUALIFICATIONS

FOR

PROFESSIONAL ENGINEERING

SERVICES

FOR

THE TEXAS STATE UNIVERSITY SYSTEM

TERLINGUA, TEXAS

Lake Ament Dam Alteration

RFQ No.:

758-25-00091

Notice To All Respondents:

The following is Addendum No. 1 to the Request for Qualifications (RFQ)

ESBD Posting No. 758-25-00091 was posted on November 20, 2024

Prepared By:

Donna Bryce, Senior Contract Administrator

The Texas State University System

601 Colorado Street

Austin, TX 78701 - 512-463-1808

Donna.Bryce@tsus.edu

Addendum No. 1 Issued December 10, 2024

Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

RFQ No. 758-25-00091

I. GENERAL:

A. The optional Pre-Submittal Conference was held on December 3, 2024, at The Texas State University System office in Austin, Texas and virtually. The Attendance Sign-In Sheets for in-person attendees are included as part of this Addendum along with the questions and answers presented in response to this solicitation as of December 10, 2024:

1. Question: What is the general expectation of the engineer during construction? Specifically, how often do we need to visit the site? We office out of Austin and it is quite a haul.

Answer: The standard language contained in our template agreement requires site visits during construction “no less than monthly” and more frequently depending on planned or actual activities at the site. The actual number of visits needed during the construction phase will be negotiated with the successful respondent.

2. Question: I noticed the 'construction cost limitation' is $900,000. Does this include all design fees? If not, is there a ballpark budget or expectation for design services?

Answer: The $900,000 Construction Cost Limitation is for construction/demolition only. The engineer’s fee will be negotiated with the successful respondent and will be based on the level of effort required to perform the engineering work.

3. Question: What is the TS’s HUB percentage goal for responding firms to meet or exceed? TSU supplied a sample Agreement with the RFQ which states that “The PE agrees to make a Good Faith Effort to allocate twenty percent (20%) of the services required under this Agreement to qualified consultants, which are HUB.” Does this include construction or only engineering services?

Answer: There is no specific HUB percentage goal that must be met.

However, the HUB Subcontracting Plan must demonstrate the Respondent’s good faith effort to allocate twenty percent (20%) of the services required under the agreement to HUBs. If the Respondent has made a demonstrated good faith effort but falls below the stated value, it has satisfied the intent of paragraph 1.13 of the RFQ. This requirement applies only to the PE services. The contractor will have a separate HUB percentage goal.

4. Question: Are there other specific HUB goals required, such as SMBE or WBE goals that will also need to be met?

Answer: No.

Attachments:

(1) Optional Pre-Submittal Attendance Sign-In Sheets

(2) PowerPoint presentation slides from the Pre-Submittal Conference held on December 3, 2024.

- END OF ADDENDUM NO. 1 -

Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

Request for Qualifications for Professional Engineering Services

Lake Ament Dam Alteration for The Texas State University System RFQ No. 758-25-00091

Pre-Submittal Meeting December 3, 2024Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

Lake Ament Dam Located North of Terlingua East of State Highway 118

Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

USGS 2024

Point of entry from State Highway 118

Lake Ament Dam Unpaved Access

Road

Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

Lake Ament Dam Pertinent Data

Location: Brewster County, Texas

Drainage Area: 1.56 square miles

Embankment Type: Rock Masonry (Main Dam): Length: 125 feet Height: 56 feet Top Width: 12 feet Top Elevation: 3578.7 feet

Principal Spillway: Type: N/A

Auxiliary Spillway: Type: N/A

Lake: Normal Pool Elevation: 3543.7 feet (Low-water mark)

3551.0 feet (High-water mark) Surface Area at Normal Pool: 4.4 acres (Low-water mark)

12.8 acres (High-water mark) Capacity at Normal Pool: 16.4 acre-feet (Low-water mark)

76.7 acre-feet (High-water mark) Effective Top of Dam Elevation: 3578.7 feet Surface Area at Top of Dam: 79.2 acres Capacity at Top of Dam: 1274.3 acre-feet

General: TCEQ Size Classification: Intermediate TCEQ Hazard Classification: High Construction History: Originally completed circa 1910s

USACE NID ID: TX06492

Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

Lake Ament Dam in the distance

Upstream Face of Dam

Close-up view with access bridge to the right Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

Upstream Face of Dam

Left Abutment

Right Abutment Cracks in Upstream Face of Dam noted in

TCEQ’s 2016 Dam Safety Inspection Report Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

Bridge to top of Dam

The bridge is supported by a truss-like structure that is structurally compromised

Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

Top of Dam

Cracks at top of Dam noted on TCEQ’s 2016 Dam Safety Inspection Report

Downstream view from top of Dam

Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

Top of Dam

Upstream view of Lake Ament

Downstream view Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

Downstream Face of Dam

Cracks in Downstream Face of Dam noted in TCEQ’s 2016 Dam Safety Inspection Report

Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

Questions?

Submittal of Question Deadline

December 10, 2024 – 12:00 p.m. (C.S.T.)

Deadline for the Submittals of Qualifications January 7, 2025

Send, via email only, to:

peter.maass@tsus.edu

Addendum No. 1 - RFQ for Professional Engineering Services (posted 12/10/2024) Lake Ament Dam Alteration in Terlingua, Texas for The Texas State University System

2024.12.03 - TSUS Lake Ament Dam - PowerPoint Presentation (for addendum#1).pdf
Request for Qualifications for �Professional Engineering Services�Lake Ament Dam Alteration�for The Texas State University System�RFQ No. 758-25-00091�
Slide Number 2
Slide Number 3
Lake Ament Dam�Pertinent Data
Slide Number 5
Slide Number 6
Slide Number 7
Slide Number 8
Slide Number 9
Slide Number 10
Slide Number 11