ESBD_373953_1725459703315_Q&A RFP730-24087_answered.pdf

PDF 103 KB Posted

Attached to
RFP730-24087 EZEKIEL CULLEN DOOR REPLACEMENT, NEW CANOPIES, REPLACE LOCKSETS AND CONCEAL ALL EXISTING ACCESS CONTROL EQUIPMENT
Solicitation number
RFP730-24087
Issued by
Harris County, Texas

About this file

This document contains the questions and answers related to RFP730-24087, a request for proposals issued by the University of Houston for the EZEKIEL CULLEN DOOR REPLACEMENT, NEW CANOPIES, REPLACE LOCKSETS AND CONCEAL ALL EXISTING ACCESS CONTROL EQUIPMENT project located on the university's main campus in Houston, Texas. The project involves the replacement and upgrade of all exterior storefront doors, the addition of canopies at two entry/egress stairs, the concealment of existing electronic control boxes, and the integration of wheelchair door release and card strike buttons into the building facade. A mandatory pre-proposal conference and site visit is scheduled for August 28, 2024.

The RFP provides details on the materials and finishes required, such as the use of Linetec Clear Anodize on Brushed Aluminum for the door frames, rails, and panels, as well as the specification of 3/8" Daltile G331 - Giallo Ornamental Granite from Brazil for the new marble thresholds. The RFP also notes that no asbestos testing has been conducted in the doorway locations, and the designated laydown area will be determined during preconstruction meetings.

View the file

Other files

File Type Posted
ESBD_373953_1726000789335_Addendum 2 - Due Date Extention - RFP730-24087.pdf PDF
ESBD_373953_1724940487315_Signin Sheet RFP730-24087.jpg JPG image
ESBD_373953_1724186135881_EXHIBITS - RFP730-24087.zip ZIP file
ESBD_373953_1724186093485_RFP730-24087 EZEKIEL CULLEN DOOR REPLACEMENT FINAL.pdf PDF
ESBD_373953_1724941272383_Addendum 1 - EC Project Manual.zip ZIP file
ESBD_373953_1725459703315_Q&A RFP730-24087_answered.pdf PDF
ESBD_373953_1724941272383_Addendum 1 - EC Project Manual.zip ZIP file
ESBD_373953_1724940487315_Signin Sheet RFP730-24087.jpg JPG image
ESBD_373953_1724186093485_RFP730-24087 EZEKIEL CULLEN DOOR REPLACEMENT FINAL.pdf PDF
ESBD_373953_1726000789335_Addendum 2 - Due Date Extention - RFP730-24087.pdf PDF
ESBD_373953_1724186135881_EXHIBITS - RFP730-24087.zip ZIP file
ESBD_373953_1724186093485_RFP730-24087 EZEKIEL CULLEN DOOR REPLACEMENT FINAL.pdf PDF
ESBD_373953_1725459703315_Q&A RFP730-24087_answered.pdf PDF
ESBD_373953_1724940487315_Signin Sheet RFP730-24087.jpg JPG image
ESBD_373953_1724941272383_Addendum 1 - EC Project Manual.zip ZIP file
ESBD_373953_1724186135881_EXHIBITS - RFP730-24087.zip ZIP file
ESBD_373953_1724186093485_RFP730-24087 EZEKIEL CULLEN DOOR REPLACEMENT FINAL.pdf PDF
ESBD_373953_1724941272383_Addendum 1 - EC Project Manual.zip ZIP file
ESBD_373953_1724186135881_EXHIBITS - RFP730-24087.zip ZIP file
ESBD_373953_1724940487315_Signin Sheet RFP730-24087.jpg JPG image
ESBD_373953_1724186135881_EXHIBITS - RFP730-24087.zip ZIP file
ESBD_373953_1724186093485_RFP730-24087 EZEKIEL CULLEN DOOR REPLACEMENT FINAL.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A RFP730-24087

1. The Door Information Reference Matrix on Sheet A1.00 indicates frame, rail and panel material tags but does not provide a finish schedule for these items. Please advise.

Answer: Both “PANEL DESIGN - FRAME MATERIAL” (SS-E) and “PANEL DESIGN – STILE/RAIL MATERIAL”

(SS-1) are based on ANO-215AEBS “LINETEC Clear Anodize on Brushed Aluminum Sheet” finish to match existing aluminum doors and mullions.

2. The Door Information Reference Matrix on Sheet A1.00, please clarify what SS-E & SS-1 abbreviations define.

Answer: See answer to “Question 1”

3. Detail 4 on Sheet A4.05 shows new continuous marble threshold, MT-1. Please provide material information, as well as the origin of the material.

Answer: Marble threshold area indicated on Detail 4, Sheet A4.05 is intended to be 3/8” DALTILE G331 -

Giallo Ornamental Granite, Country of Origin is Brazil

4. Have the locations in and/or around the project doorway locations been tested for asbestos? If so, please provide an all-clear letter regarding the asbestos containing materials.

Answer: No testing has been conducted in or around the doorway locations at EC 516 or CPH 517.

5. Please provide the location of the designated laydown area.

Answer: This location is dependent upon the laydown space requirements by the general contractor.

Please identify spatial requirements in you proposal (i.e. portable toilet, site box, parking, remote workspace if deemed necessary). Final location will be determined through preconstruction meetings with building stakeholders.

File details come from the government source that posted it. Updated .